Peterman-Donnelly Engineers & Contractors Corp. v. First National Bank

408 P.2d 841, 2 Ariz. App. 321
CourtCourt of Appeals of Arizona
DecidedDecember 17, 1965
Docket2 CA-CIV 82
StatusPublished
Cited by35 cases

This text of 408 P.2d 841 (Peterman-Donnelly Engineers & Contractors Corp. v. First National Bank) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Peterman-Donnelly Engineers & Contractors Corp. v. First National Bank, 408 P.2d 841, 2 Ariz. App. 321 (Ark. Ct. App. 1965).

Opinion

MOLLOY, Judge.

This is an appeal and a cross-appeal from partial summary judgments granted below to both appellant and appellee, which determined lien priorities between the parties.

A parcel of land was donated to the Chamber of Commerce of Apache Junction, on which the Chamber undertook to construct a baseball park. The Chamber committed itself to an outside organization, the Houston Sports Association, to complete the park by February 1, 1962. To finance the project, the Chamber borrowed $10,000.00 from one L. D. Eyre, and secured the loan by a mortgage to Eyre.

Later, in an effort to forestall organizational delays, the Chamber caused The Lost Dutchman Baseball Association, Inc., to be created to construct and operate the baseball park. At the time the Association was incorporated, August 4, 1961, the Chamber decided to deed the parcel to the Association, and an appropriate deed was executed. The conveyance was not delivered however, or recorded, until October 3, 1961, at which time the Association borrowed $35,000.00 from the appellee, First National Bank of Arizona. Part of this money was used to satisfy the Eyre mortgage and the remainder was to be used to further the project.

Improvement of the parcel commenced before the Association was incorporated, and on September 18, 1961, before the conveyance to the Association was recorded, or the bank loan placed, the Association entered a contract with the appellant Peterman-Donnelly Engineers & Contractors Corporation for the construction of a major portion of the baseball park. The appellant commenced work shortly thereafter. Appellant worked on the project until about January 25, 1962, at which time it discontinued further services because of the failure of the Association to pay sums owed to it under this contract.

Appellant filed a notice and claim of lien, and subsequently prevailed in foreclosure proceedings. Execution was stayed pending determination of priorities between appellant and appellee. Both parties moved for summary judgment, and each motion was granted in part. Wc are concerned with an appeal and a cross-appeal from the judgment granted below as to priorities.

The cross-appeal will be considered first. Appellee-bank contends that appellant-contractor failed to perfect its lien against the Association and that the appellee, therefore, must be awarded priority over any claim of the appellant. Appellee grounds its argument on the requirements of A.R.S. § 33-993, and contends that the statute *323 was not followed in two respects: first, a copy of the notice and claim of lien was not served on the owner; and secondly, the notice and claim of lien did not contain a copy of the written contract between appellant and the Association.

The statute is as follows:

“In order to impress and secure the lien provided for in this article, every original contractor, within ninety days, and every other person claiming the benefits of this article, within sixty days after the completion of a building, structure or improvement, or any alteration or repair thereof, shall make duplicate copies of a notice and claim of lien and file one copy with the county recorder of the county in which the property or some part thereof is located, and within a reasonable time thereafter serve the remaining copy upon the owner of the building, structure or improvement, if he can be found within’ the county. The notice and claim of lien shall be made under oath by the claimant or some one with knowledge of the facts, and shall contain:
1. A description of the lands and improvements to be charged with a lien, sufficient for identification.
2. The name of the owner or reputed owner of the property concerned, if known, and the name of the person by whom the lienor was employed or to whom he furnished materials.
3. A statement of the terms, time given and conditions of the contract, if it is oral, or a copy of the contract, if written.
4. A statement of the lienor’s demand, after deducting just credits and offsets.” A.R.S. § 33-993.

The notice did not have attached thereto a copy of the construction contract. Service of the claim was attempted by serving a duplicate copy upon the law partner of the statutory agent of the Association, and the statutory agent subsequently executed a formal acknowledgment of service.

Concerning the contention that the notice and claim of lien did not contain a copy of the contract, the following language from that notice is revelant:

“3. * * * that on September 18, 1961 the Peterman-Donnelly Engineers & Contractors Corporation entered into a contract with The Lost Dutchman Baseball Association, Inc. which, together with change orders thereafter agreed upon, was for the construction of fences, batter’s eye, bleachers, ramps, box seats, dugouts, dugout tunnel, backstop, press box and other miscellaneous improvements.
“4. * * * that the original contract was for a price of $19,800.00; in addition thereto, by change orders and additions agreed to by the parties, $12,-545.38 in other work has been performed.”

Obviously the quoted portions of the notice do not strictly satisfy the statutory requirement of a “ * * * copy of the contract, * * * ” but it is equally evident that the principal terms of the agreement have been incorporated into the notice: the parties, the date, the purpose and the consideration. In addition, elements of subsequent oral agreements are included. What is lacking is a recital of the fine print terms of a standard form contract. The question is, does such an omission so avoid the statutory requirement as to negative the legislative intent? We think not.

The purpose of the requirements of A.R.S. § 33-993 is to give the property owner an opportunity to protect himself and time to investigate the claim and determine whether it is a proper charge, Leeson v. Bartol, 55 Ariz. 160, 99 P.2d 485 (1940), and the lien statutes, being remedial, are to he liberally construed. Ranch House Supply Corporation v. Van Slyke, 91 Ariz. 177, 370 P.2d 661 (1962); Kerr-McGee Oil Industries, Inc. v. McCray, 89 Ariz. 307, 361 P.2d 734 (1961). Substantial compliance not inconsistent with the legislative purpose is sufficient. Leeson v. Bartol, supra.

*324 If we were to require more than substantial compliance, we would be inviting an absurdity. Construction contracts, typically, are lengthy documents. Specifications, plans and general conditions are usually incorporated and made a part of the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

The Weitz Company v. Nicholas Heth
Arizona Supreme Court, 2014
Weitz Co. v. Heth
333 P.3d 23 (Arizona Supreme Court, 2014)
Weitz Co. v. Heth
314 P.3d 569 (Court of Appeals of Arizona, 2013)
Wilmington Trust FSB v. A1 Concrete Cutting & Demolition, LLC
289 P.3d 1199 (Nevada Supreme Court, 2012)
Sourcecorp, Inc. v. Norcutt
274 P.3d 1204 (Arizona Supreme Court, 2012)
Sourcecorp Inc v. D norcutt/S Norcutt
Arizona Supreme Court, 2012
BAC Home Loans Servicing, LP v. Semper Investments L.L.C.
277 P.3d 784 (Court of Appeals of Arizona, 2012)
Sourcecorp, Inc. v. Norcutt
258 P.3d 281 (Court of Appeals of Arizona, 2011)
Fagerlie v. MARKHAM CONTRACTING CO., INC.
258 P.3d 185 (Court of Appeals of Arizona, 2011)
In Re Mortgages Ltd.
444 B.R. 585 (D. Arizona, 2011)
Kline v. Kline
212 P.3d 902 (Court of Appeals of Arizona, 2009)
Land Title Insurance Corp. v. Ameriquest Mortgage Co.
207 P.3d 141 (Supreme Court of Colorado, 2009)
Ameriquest Mortgage Co. v. Alton
726 N.W.2d 424 (Michigan Court of Appeals, 2006)
Lamb Excavation, Inc. v. Chase Manhattan Mortgage Corp.
95 P.3d 542 (Court of Appeals of Arizona, 2004)
Lamb Excavation v. Torrejon
Court of Appeals of Arizona, 2004
Richards v. Security Pacific National Bank
849 P.2d 606 (Court of Appeals of Utah, 1993)
MLM Const. Co., Inc. v. Pace Corp.
836 P.2d 439 (Court of Appeals of Arizona, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
408 P.2d 841, 2 Ariz. App. 321, Counsel Stack Legal Research, https://law.counselstack.com/opinion/peterman-donnelly-engineers-contractors-corp-v-first-national-bank-arizctapp-1965.