Stone v. Central & Monroe, L.L.C. (In re Mortgages Ltd.)

444 B.R. 585
CourtUnited States Bankruptcy Court, D. Arizona
DecidedFebruary 15, 2011
DocketBankruptcy No. 2:08-bk-07465; Adversary No. 2:09-ap-00424-RJH
StatusPublished
Cited by1 cases

This text of 444 B.R. 585 (Stone v. Central & Monroe, L.L.C. (In re Mortgages Ltd.)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, D. Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stone v. Central & Monroe, L.L.C. (In re Mortgages Ltd.), 444 B.R. 585 (Ark. 2011).

Opinion

MEMORANDUM DECISION GRANTING PARTIAL SUMMARY JUDGMENT IN FAVOR OF MORTGAGES LTD.

RANDOLPH J. HAINES, Bankruptcy Judge.

The issue here is whether various mechanics’ lien claimants, who claim priority dating from the commencement of construction in November 2006, have priority over a construction deed of trust that was recorded in May of 2007. Among other defenses, the construction lender asserts the doctrine of equitable subrogation gives it priority back to that of a prior deed of trust because a portion of the construction lender’s loan was used to pay off the prior debt.

BACKGROUND FACTS

The construction project at issue is the remodeling or refurbishment of an existing building commonly known as the Hotel Monroe. Its owner, Central and Monroe, LLC, first obtained a loan from First Commonwealth Mortgage Trust in the amount of $3.2 million, secured by a deed of trust recorded in May, 2002. In July, 2005, that loan was refinanced by an $8.5 million dollar loan provided by Mortgages Ltd., secured by a deed of trust recorded that same month. Almost $3 million of the proceeds of that loan were used to satisfy the First Commonwealth debt and obtain a release of the First Commonwealth deed of trust.

In December, 2006, the owner obtained a new loan from Choice Bank in the amount of $9.3 million. It was secured by a deed of trust recorded that same month. Approximately $7.3 million of the proceeds of the Choice loan were used to satisfy the debt to Mortgages Ltd. and obtain a release of its 2005 deed of trust.

By the time the Choice Bank deed of trust was recorded in December, 2006, [594]*594however, work was already underway on the remodeling. KGM was the general contractor who had a contract with the owner in October, 2006, to perform demolition work. KGM asserts, and it is apparently undisputed, that KGM first supplied labor and materials to its construction project on November 15, 2006, more than a month prior to the recordation of the Choice Bank deed of trust.1

The Choice Bank debt was refinanced by another loan from Mortgages Ltd. in the amount of $75.6 million, in May, 2007. The deed of trust securing that debt was recorded on May 16, 2007. From the proceeds of this second Mortgages Ltd. loan, more than $8.9 million was used to satisfy the Choice Bank debt and obtain a release of its 2006 deed of trust.

More than six months later, the owner signed another contract with another general contractor, Summit Builders. It commenced work on January 1, 2008, and recorded its notice and claim of mechanics’ and materialmen’s lien in July, 2008.

Summit claims that although it had a separate contract with the owner, some of the work it contracted to do was on the same “project” that KGM had worked on, the demolition of the interior of the building to prepare for the substantial remodeling.

THE ISSUES

Mortgages Ltd. has moved for summary judgment against Summit Builders and all of its subcontractors on essentially three theories:

Mortgages Ltd. asserts that at a status conference on July 6, 2010, Summit’s counsel announced in court that it would be dismissing its lien claim. It was not until a subsequent status conference on October 25 that Summit’s counsel announced that Summit had changed its mind and would not be dismissing its lien claim. Mortgages Ltd. argues that the intended dismissal that was announced on the record should be enforced as a settlement agreement.

Mortgage’s second basis for summary judgment is that Summit’s lien is invalid because Summit failed to provide Mortgages Ltd. with a preliminary twenty-day lien notice as required by statute.2

Finally, Mortgages asserts that because portions of the proceeds of its loan were used to pay off prior secured debts, Mortgages Ltd. is entitled to the priority of those prior deeds of trust under the doctrine equitable subrogation.

ANALYSIS

The court is not inclined to grant summary judgment on the theory that Summit’s stated intent to dismiss its lien claim constituted a settlement agreement. It does not appear that it was so much of an agreement as merely a unilateral decision and announcement by Summit. Although a unilateral statement of position can be enforced either as a judicial estop-pel or as quasi-judicial estoppel, those doctrines generally apply only if there has been some benefit obtained as a result of this statement, or some detrimental reliance by the court or other parties. Here no such showings have been made.

[595]*595 PRELIMINARY 20-DAY NOTICE ISSUE

But Mortgages Ltd. might be entitled to summary judgment due to the failure of Summit to provide the preliminary 20-day notice required by A.R.S. § 3S-992.01(B). There can be no dispute that Mortgages Ltd. qualified as a “construction lender” or a “reputed construction lender” as referred to in this statute. Summit had constructive notice at the time that it commenced work in January of 2008 that Mortgages Ltd. was such a construction lender because its deed of trust had been of record for more than seven months.

Summit’s defense is that it substantially complied with the statute by providing a preliminary 20-day notice to the owner, and that Mortgages Ltd. was not prejudiced by the failure of notice because it had actual knowledge that the construction was going on. But while case law has upheld liens when there has been substantial compliance with the 20-day preliminary notice requirement even though the notice failed to include all of the statutorily required elements,3 neither the statute nor case law suggests that failure to serve a party any notice can constitute substantial compliance because other parties were served. It is undoubtedly true that the primary purpose of the 20-day notice requirement is to protect owners, primarily by advising them of what might otherwise be regarded as secret lien rights.4 It is also true that statutory purpose has been substantially fulfilled here, both by the service of the notice on the owner and by the alleged actual knowledge of Mortgages Ltd. But another key factor in ascertaining substantial compliance is “the nature and extent of the deviation from the statutory plan.”5 This court cannot predict that an Arizona Court would find substantial compliance despite a complete failure to provide any kind of preliminary 20-day notice to one of the parties that is statutorily entitled to it.

Summit has a better argument that Mortgages is statutorily estopped from asserting the preliminary 20-day notice defense because the owner failed to correct the failure of the notice to identify Mortgages Ltd. as its construction lender. Arizona law provides that the owner has ten days after receipt of a preliminary 20-day notice to identify its construction lender and to correct any misinformation contained in the notice.6 The statute further provides that if the owner fails to furnish or correct that misinformation, then the owner is estopped “from raising as a defense any inaccuracy of the information in a preliminary twenty-day notice.”7

Of course Mortgages Ltd. was not the owner at the time that the preliminary twenty-day notice was given to the owner. But Mortgages Ltd.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Mortgages Ltd.
444 B.R. 585 (D. Arizona, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
444 B.R. 585, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stone-v-central-monroe-llc-in-re-mortgages-ltd-arb-2011.