Leeson v. Bartol

99 P.2d 485, 55 Ariz. 160, 1940 Ariz. LEXIS 234
CourtArizona Supreme Court
DecidedFebruary 26, 1940
DocketCivil No. 4139.
StatusPublished
Cited by13 cases

This text of 99 P.2d 485 (Leeson v. Bartol) is published on Counsel Stack Legal Research, covering Arizona Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Leeson v. Bartol, 99 P.2d 485, 55 Ariz. 160, 1940 Ariz. LEXIS 234 (Ark. 1940).

Opinions

ROSS, C. J.

This is an action to foreclose material-men’s liens and the only question is as to whether the liens were perfected within the time and in the manner provided by the statutes.

On June 28, 1937, C. D. Bradley entered into a contract with Robert V. Leeson and Ollie G. Leeson, his wife, to build for them on Lot 6, Stanley Place,- Maricopa county, a dwelling house and garage, furnishing all material and labor, for the sum of $8,300. On November 25, 1937, the Leesons moved into the premises, at which time they claim the dwelling and garage were completed.

W. T. Bartol, doing business as Union Rock Company, on June 8, 1938, filed with the county recorder a notice and claim of lien on the premises for $123.93 for material furnished the contractor and used in the buildings. Later, on June 29, 1938, he filed another notice in the same words except there was added thereto the name of the wife as one of the owners, or reputed owners. These materials, it is shown, were furnished between July 6, 1937, and August 4, 1937.

*163 The Arizona Sash, Door and Glass Company, on June 18, 1938, filed with the county recorder its notice and claim of lien on the same premises for $933.59 for material furnished the contractor between August 24 and November 27, 1937, and used in the buildings.

July 25, 1938, Bartol filed his suit to foreclose lien and therein made contractor Bradley, the Leesons, the Arizona Sash, Door and Glass Company and the First Federal Savings and Loan Association of Phoenix (mortgage lienholder) defendants. Bradley did not appear or answer, but defaulted. The Arizona Sash, Door and Glass Company filed an answer setting up its claim of lien and asked that it be foreclosed. The Leesons and the Loan Association, among other things, alleged in their answer that the so-called liens were not filed with the county recorder within sixty days from completion of improvements and denied that they were ever served with duplicate copies of the liens.

The court, sitting without a jury, heard the evidence and rendered judgment in favor of the lien claimants. The Leesons and the First Federal Savings and Loan Association of Phoenix, have appealed, and as grounds therefor insist the liens were not perfected within the time and in the manner provided by law.

Section 2021, Revised Code of 1928, gives an original contractor ninety days, and every other person claiming a lien on a building, structure, or improvement sixty days after the completion thereof within which to perfect his lien. It provides, among other things, that the lien claimant

“must make duplicate copies of a notice and claim of lien and file one copy thereof with the county recorder of the county in which the property, or some part thereof, is situated, and within a reasonable time thereafter, serve upon the owner of said building, structure or improvement, if to be found within the county, the remaining copy. Such notice and claim of lien shall be made under oath by the claimant or some one with *164 knowledge of the facts, and shall contain, a description of the lands and improvements to be charged with the lien, sufficient for identification; the name of the owner or reputed owner of the property concerned, if known, and the name of the person by whom the lienor was employed or to whom he furnished materials; a statement of the terms, time given and conditions of his contract, if the same be oral, or a copy of the contract, if written, and a statement of the lienor’s demand, after deducting all just credits and offsets. ’ ’

The appellee-lien claimants furnished material to Bradley, the original contractor, who, under the statute, is constituted the agent of the owners for the purposes of the lien law, section 2020, Id., so they fall within the class that must perfect their liens within sixty days after the completion of the dwelling and garage contracted to be constructed by Bradley. It is quite obvious that if these improvements were completed November 25, 1937, the liens claimed were not perfected within the sixty days allowed, since no steps were taken to file liens until June, 1938. But the lien claimants insist, and the trial court found, that the buildings were not completed until May 7, 1938, and if that is the correct date, liens filed in June, 1938, with the county recorder were in time.

Ordinarily we would accept without question the trial court’s finding to.the effect that the liens were perfected within the time allowed by law, but in Morgan v. O’Malley Lumber Co., 39 Ariz. 400, 7 Pac. (2d) 252, 253, we said “trifling adjustments or corrections . . . made long after the expiration period’’ would not extend the time for perfecting a materialman’s lien, and the appellants contend the facts here bring this case within the rule announced in the Morgan case.

Robert V. Leeson testified on cross-examination as follows:

“Q. Well, isn’t it a fact, Mr. Leeson, that the situation was this, that you moved into the house before *165 you were willing to accept the job as completed? A. The contractor told us the house was through so far as he was concerned, and that he would make these corrections. He knew what they were.
“Q. And you knew what they were? A. Yes.
“Q. And you continued to insist on him fulfilling the contract? Isn’t that so? A. Rightly so.
“Q. And you insisted on that to and including the seventh day of May, 1938, when that final work was done on the basement? Isn’t that so? It isn’t so? A. Probably would have been calling for it yet if it hadn’t been done.”

From this testimony we understand that it was agreed that the building job was not complete on November 25, 1937, but that the contractor would see that it was completed later. From then on, the contractor returned to the premises several times to do something toward fulfilling his contract. A plasterer testified that on May 7,1938, he worked three hours in finishing incomplete work in the basement and in pouring two window sills. On that same day painting was done, as requested by the owners. For the same reason painting was done in the dinette and on the service porch on or about the last of April, 1938. In fact, the contractor from November 25, 1937, to May 7, 1938, did several jobs to make the work conform with the owners’ interpretation of the contract.

There is quite a discrepancy in the evidence of the appellees and appellants as to the amount and character of the work that was done on the improvement after November 25, 1937, and up to May 7, 1938. The appellants greatly minimize the amount of work, whereas the appellees ’ evidence tends to show that the work was substantial in its character. The lower court evidently accepted the evidence of the appellees on the dispute.

To assure that this work would be done, the owners held back from the contractor $164.57 until the latter *166 would finish his contract to their satisfaction. This balance, which, by the way, was the balance owing on the contract sixty days after November 25, 1937, was paid to the contractor May 11,1938.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Delmastro & Eells v. Taco Bell Corp.
Court of Appeals of Arizona, 2011
Performance Funding, L.L.C. v. Arizona Pipe Trade Trust Funds
49 P.3d 293 (Court of Appeals of Arizona, 2002)
Aesthetic Property Maintenance, Inc. v. Capitol Indemnity Corp.
900 P.2d 1210 (Arizona Supreme Court, 1995)
Fields v. CAPITOL INDEMNITY CORPORATION
884 P.2d 198 (Court of Appeals of Arizona, 1994)
Columbia Group, Inc. v. Jackson
725 P.2d 1110 (Arizona Supreme Court, 1986)
Wooldridge Construction Co. v. First National Bank
634 P.2d 13 (Court of Appeals of Arizona, 1981)
Gene McVety, Inc. v. Don Grady Homes, Inc.
581 P.2d 1132 (Arizona Supreme Court, 1978)
Lewis v. Midway Lumber, Inc.
561 P.2d 750 (Court of Appeals of Arizona, 1977)
Wahl v. Southwest Savings and Loan Association
476 P.2d 836 (Arizona Supreme Court, 1970)
Peterman-Donnelly Engineers & Contractors Corp. v. First National Bank
408 P.2d 841 (Court of Appeals of Arizona, 1965)
Ranch House Supply Corporation v. Van Slyke
370 P.2d 661 (Arizona Supreme Court, 1962)
Kerr-McGee Oil Industries, Inc. v. McCray
361 P.2d 734 (Arizona Supreme Court, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
99 P.2d 485, 55 Ariz. 160, 1940 Ariz. LEXIS 234, Counsel Stack Legal Research, https://law.counselstack.com/opinion/leeson-v-bartol-ariz-1940.