Wooldridge Construction Co. v. First National Bank

634 P.2d 13, 130 Ariz. 86, 1981 Ariz. App. LEXIS 506
CourtCourt of Appeals of Arizona
DecidedJuly 16, 1981
Docket1 CA-CIV 4687
StatusPublished
Cited by15 cases

This text of 634 P.2d 13 (Wooldridge Construction Co. v. First National Bank) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wooldridge Construction Co. v. First National Bank, 634 P.2d 13, 130 Ariz. 86, 1981 Ariz. App. LEXIS 506 (Ark. Ct. App. 1981).

Opinion

OPINION

HAIRE, Presiding Judge.

This appeal involves two questions:
1) Did appellant, Wooldridge Construction Company, Inc., a general contractor, timely file its mechanic’s lien, pursuant to A.R.S. § 33-993, and, if it did,
2) Is appellant’s lien entitled to priority over First National Bank’s deed of trust, pursuant to A.R.S. § 33-992?

Proeedurally, the appeal is from a judgment after a full evidentiary trial with an advisory jury in equity proceedings. The proceedings involved various parties and claims. The only aspect pertinent to this appeal is that appellee First National Bank sought to foreclose its deed of trust and that appellant sought to establish the priority of its allegedly enforceable mechanic’s lien claim on the same property. Appellant appeals from that portion of the trial trial court’s judgment declaring that appellant had no enforceable materialmen’s lien against the subject property and foreclosing First National Bank’s deed of trust as against Wooldridge.

Before proceeding to the resolution of the substantive legal questions presented, we first delineate the material facts. In so doing we must view the evidence in a light most favorable to the appellee, resolving conflicts in the evidence in favor of sustaining the judgment. See Wilson v. Coerver, 35 Ariz. 488, 279 P. 253 (1929).

In February 1974, appellant contracted to construct a two-story, steel-frame office building for Deise Realty, Inc., (hereinafter Deise), the owner of the property. Shortly thereafter, and pursuant to the overall construction contract, appellant commenced preparation of the site. By March 11, 1974, appellant’s subcontractor had removed trees, grass and weeds, cut curbs and sidewalks, removed irrigation pipes, and scarified the land.

Appellee, First National Bank, provided Deise with financing for the construction project, taking a deed of trust on the property as security for the loan. The deed was recorded at 8:00 a.m. on March 11, 1974. At the time appellant’s subcontractor had begun work on the site, appellant had no *88 actual or constructive knowledge of First National Bank’s deed of trust.

The construction of the building continued throughout the summer. By August the building was ninety percent complete and approximately forty percent of the contract price had been paid. In early September 1974, the building’s power was turned on and Deise began occupying one small area, although some of appellant’s subcontractors were still working in other areas of the building. Also during September, appellant applied for full payment and determined that the project was “substantially complete” which, by contract, precipitated an inspection by an architect. Thereafter an architect inspected the building, compiling a detailed “punch list” of the items that needed to be changed or added in order to comply with the terms of the contract. By letter dated November 20, 1974, Deise presented appellant with this “punch list”. He demanded that appellant promptly correct the work, with holding full payment until the requested changes were made and basing his request upon his rights under the terms of the contract.

The uncontroverted evidence reveals that at least ninety hours of work were done by appellant’s crews after November 28, 1974, including the following:

1) Re-plumbing a drinking fountain
2) Smoothing rough concrete
3) Re-striping the parking lot
4) Replacing ceiling tiles
5) Installing missing duct insulation
6) Touching-up interior paint
7) Caulking joints
8) General cleanup

This work was done pursuant to the owner’s request and to accommodate his interpretation of the contract. The owner had retained a percentage of the contract price and conditioned payment of that fund upon prompt and satisfactory completion of the work. This procedure was provided for in the contract and the work performed was not a mere afterthought on the part of appellant. There is no allegation that the work done was intended to circumvent the statutory time limitation on the filing of materialmen’s liens.

Appellee, in his brief, raised questions as to whether the facts as stated above could properly be relied upon by this court in view of the trial court’s rejection of certain advisory jury findings. The trial was conducted as an equity proceeding before a judge with an advisory jury. See Rule 39(7), Rules of Civil Procedure, 16 A.R.S. The trial court could either accept or reject the jury’s findings, as they were advisory only. See Rule 39(7), Rules of Civil Procedure, 16 A.R.S.

In the event an advisory jury’s findings are rejected, a trial court usually makes findings of its own, see Rule 52(a), Rules of Civil Procedure, 16 A.R.S., in which case the court’s findings, not the jury’s, are those upon which the judgment is based. Merryweather v. Pendleton, 90 Ariz. 219, 367 P.2d 251 (1961); Mullins v. Horne, 120 Ariz. 587, 587 P.2d 773 (App. 1978). In such a case the court becomes the trier of fact and if there is substantial evidence to support the trial court’s finding on an issue, it must be left undisturbed on appeal. Mullins v. Horne, supra.

In the present case, however, the trial court made no factual findings independent of the jury’s findings. The final judgment included a section entitled “Findings of Fact and Conclusions of Law”, in which the court recited the four interrogatories propounded to the jury, together with the jury’s answers. With respect to two of the answers, the court made no further comment. In that context we must assume that the court adopted those findings. They were as follows:

“INTERROGATORY # 1
“I instruct you that the Bank’s Trust Deed was recorded at 8:00 o’clock a. m. on Monday, March 11, 1974. Do you find that any labor was performed on the site of the Deise Building, or materials furnished to the site before the Bank’s Trust Deed was recorded.
“Answer: Yes.
*89 “INTERROGATORY # 3
“Do you find that the Plaintiff, WOOL-DRIDGE, had actual or constructive notice of the Bank’s Trust Deed at the time any labor was commenced or materials furnished to the site of the Deise Building?
“Answer: No.”

The court, however, rejected the jury’s answer to the other two interrogatories. Interrogatory # 2 read as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Singh v. Malhotra
Court of Appeals of Arizona, 2018
Thienes v. City Center
Court of Appeals of Arizona, 2016
Jp Morgan v. Mgm
Court of Appeals of Arizona, 2016
Personal Restraint Petition Of Sione P. Lui
Court of Appeals of Washington, 2016
Interiors Contracting, Inc. v. Smith, Halander & Smith Associates
827 P.2d 963 (Court of Appeals of Utah, 1992)
Pds Engineering Const. v. Double Rs, No. Cv90-0378684 (Dec. 19, 1991)
1991 Conn. Super. Ct. 10306 (Connecticut Superior Court, 1991)
S.K. Drywall, Inc. v. Developers Financial Group, Inc.
799 P.2d 1362 (Court of Appeals of Arizona, 1990)
Scottsdale Memorial Health Systems, Inc. v. Clark
759 P.2d 607 (Arizona Supreme Court, 1988)
In Re Zachman Homes, Inc.
47 B.R. 496 (D. Minnesota, 1984)
Kaibab Shop v. Desert Son, Inc.
662 P.2d 452 (Court of Appeals of Arizona, 1982)
Felix v. Olivas
643 P.2d 1031 (Court of Appeals of Arizona, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
634 P.2d 13, 130 Ariz. 86, 1981 Ariz. App. LEXIS 506, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wooldridge-construction-co-v-first-national-bank-arizctapp-1981.