Jeffrey C. Stone, Inc. v. Central & Monroe, L.L.C. (In re Mortgages Ltd.)

482 B.R. 298
CourtUnited States Bankruptcy Court, D. Arizona
DecidedSeptember 27, 2012
DocketBankruptcy No. 2:08-bk-07465-RJH; Adversary No. 2:09-ap-00424-RJH
StatusPublished
Cited by2 cases

This text of 482 B.R. 298 (Jeffrey C. Stone, Inc. v. Central & Monroe, L.L.C. (In re Mortgages Ltd.)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, D. Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jeffrey C. Stone, Inc. v. Central & Monroe, L.L.C. (In re Mortgages Ltd.), 482 B.R. 298 (Ark. 2012).

Opinion

OPINION RE: LIEN PRIORITY

RANDOLPH J. HAINES, Bankruptcy Judge.

The issue here is whether various mechanics’ lien claimants, who claim priority dating from the commencement of construction in October, 2005, have priority over a construction deed of trust that was recorded in May of 2007. The lender, Mortgages, Ltd., maintains that even if there is but a single project or “work,” a mechanics’ lien has priority only dating from the general contract for which the work was performed (the “separate contracts doctrine”), and that in any event Mortgages is entitled to be equitably sub-rogated to a prior deed of trust that was paid off and released by some of the proceeds of Mortgages’ loan.

BACKGROUND FACTS

The construction project at issue is the remodeling or refurbishment of an existing building commonly known as the Hotel Monroe. Its owner, Central and Monroe, LLC, first obtained a loan from First Commonwealth Mortgage Trust in the amount of $3.2 million, secured by a deed of trust recorded in May, 2002. In July, 2005, that loan was refinanced by an $8.5 million dollar loan provided by Mortgages Ltd., secured by a deed of trust recorded that same month. Almost $3 million of the proceeds of that loan were used to satisfy the First Commonwealth debt and obtain a release of the First Commonwealth deed of trust.

In December, 2006, the owner obtained a new loan from Choice Bank in the amount of $9.3 million. It was secured by a deed of trust recorded that same month. Approximately $7.3 million of the proceeds of the Choice loan were used to satisfy the debt to Mortgages Ltd. and obtain a release of its 2005 deed of trust.

By the time the Choice Bank deed of trust was recorded in December, 2006, however, work was already underway on the remodeling. The first general contract for this remodeling project was an October 18, 2005 contract with Contractors Abate[301]*301ment Services, Inc. (“CASI”) for demolition and asbestos abatement. On October 12, 2006, the owner signed a second general contract for the remodeling project, this time with KGM Builders, Inc. (“KGM”), who is one of the mechanics’ lien claimants asserting priority in this case. KGM then entered into a subcontract for CASI to continue its asbestos abatement work. The principal of KGM, Kevin Markham, was also hired by the owner to act as the owner’s representative for all facets of the renovation project. As early as May, 2007, the owner and Markham recognized that a larger general contractor would be required once the renovation plans were finalized, and had identified Jeffrey C. Stone, Inc., dba Summit Builders (“Summit”) as that general contractor. Summit began work on the demolition and renovation in October, 2007, and finalized its Cost Plus form of construction contract with the owner on December 12, 2007, for a cost plus budgeted amount in excess of $27.7 million. While work continued, the parties waited until a permitted set of construction plans were available to sign the prime contract; the owner signed on April 9, 2008 and Summit signed on April 18, 2008.

In the meantime, while the CASI and KGM demolition and abatement work was going on, the Choice Bank debt was refinanced by another loan from Mortgages Ltd. in the amount of $75.6 million, in May, 2007. The deed of trust securing that debt was recorded on May 16, 2007. From the proceeds of this second Mortgages Ltd. loan more than $8.9 million was used to satisfy the Choice Bank debt and obtain a release of its 2006 deed of trust.

When it made its construction loan and recorded its deed of trust, Mortgages understood that it was making a “broken priority loan” because the construction work was already underway. Consequently it obtained from the owner’s principals a general Indemnity Agreement and Indemnification Agreement for Mechanics’ and Materialman’s Liens, and it required an assignment from the owner of the owner’s rights in the general contract with Summit, even though it had not yet been finalized and signed. Mortgages did not, however, require or obtain any subordination agreements from any of the general or subcontractors performing the work.

Mortgages did not have the $75.6 million necessary to fund the loan that it made to Central and Monroe. Mortgages’ business plan had been to raise the necessary funds from its investors, but by May, 2007, it was already having difficulty raising as much funds as it had committed to lend. When the loan closed on May 16, 2007, Mortgages paid itself in excess of $5.4 million for a “Loan Discount,” “Construction Admin. Fees,” “Rev Op Fees,” and a “Processing Fee.” It agreed with the owner to a “delayed funding” arrangement, purportedly to reduce the owner’s interest accrual but more likely because it did not have the funds to advance. That arrangement called for about $44.7 million to be funded to a “Construction Impound” account by October, 2008, and an additional $9.4 million for interest reserves by the month after that. The initial delayed funding was funded on July 13, 2007.

But by November, 2007, just as the form of contract was being finalized and Summit took over as general contractor, Mortgages already needed to withdraw funds that it had previously paid into the Construction Impound account. Mortgages agreed with the owner to “borrow” back $2.5 million that had been funded, promising to replace $1 million of those funds on 10 days’ notice, another $1 million on 20 days’ notice, and the full balance within 30 days of the owner’s demand. Seven days after the parties agreed upon the form of the general contract with Summit, and while [302]*302Summit was performing work at the Project, the owner demanded the first $1 million to be repaid to the Construction Impound account. Mortgages never honored that demand. Instead it not only stopped funding but diverted more money from the Construction Impound account, including more than $788,000 in April, 2008 and another half million dollars in May. The owner apparently agreed to these diversions because some of that money was used to fund some of the owner’s other projects. Neither KGM nor Summit was ever informed of the withdrawals and diversions from the Construction Impound account or, indeed, of the whole “delayed funding” scheme.

By the spring of 2008 the construction impound account was insufficient to pay the accruing construction costs. Summit’s first two draws were paid by the owner itself because there was insufficient money in the impound account. About $1.6 million was deposited in May, sufficient to pay Summit’s third draw. By June the account was empty, although Mortgages had approved draws in excess of $10 million. Mortgages’ principal Scott Coles committed suicide on June 2, and Mortgages was placed into involuntary bankruptcy on June 23.

PROCEDURAL POSTURE

This litigation was originally filed in Maricopa County Superior Court and was removed to this Court, pursuant to 28 U.S.C. § 1441, in connection with the pending bankruptcy case of Mortgages, Ltd. Rexel Phoenix Electric and some of the other subcontractors of general contractor Summit moved to remand the adversary proceeding to state court. All parties who had appeared in the action agreed that the adversary proceeding should be remanded but only after this Court ruled on the threshold “issue of lien priority,” and on September 10, 2009, the Court entered an order to that effect.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Keeler
561 B.R. 804 (N.D. Georgia, 2016)
Markham Contracting Co. v. Federal Deposit Insurance Co.
379 P.3d 257 (Court of Appeals of Arizona, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
482 B.R. 298, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jeffrey-c-stone-inc-v-central-monroe-llc-in-re-mortgages-ltd-arb-2012.