Jeffrey C. Stone, Inc. v. Central & Monroe, L.L.C. (In Re Mortgages Ltd.)

459 B.R. 739, 2011 WL 5022681
CourtUnited States Bankruptcy Court, D. Arizona
DecidedOctober 20, 2011
DocketBankruptcy No. 2:08-bk-07465-RJH. Adversary No. 2:09-ap-00424-RJH
StatusPublished
Cited by3 cases

This text of 459 B.R. 739 (Jeffrey C. Stone, Inc. v. Central & Monroe, L.L.C. (In Re Mortgages Ltd.)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, D. Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jeffrey C. Stone, Inc. v. Central & Monroe, L.L.C. (In Re Mortgages Ltd.), 459 B.R. 739, 2011 WL 5022681 (Ark. 2011).

Opinion

OPINION DENYING PARTIAL SUMMARY JUDGMENT RE: MECHANICS’ LIEN PRIORITY

RANDOLPH J. HAINES, Bankruptcy Judge.

The issue here is whether various mechanics’ lien claimants, who claim priority dating from the commencement of construction in November 2006, have priority over a construction deed of trust that was recorded in May of 2007. Among other defenses, the construction lender asserts the doctrine of equitable subrogation gives it priority back to that of a prior deed of trust because a portion of the construction lender’s loan was used to pay off the prior debt. And it argues that the second general contractor cannot claim a priority dating from the commencement of work by a prior general contractor.

BACKGROUND FACTS

The construction project at issue is the remodeling or refurbishment of an existing building commonly known as the Hotel Monroe. Its owner, Central and Monroe, LLC, first obtained a loan from First Commonwealth Mortgage Trust in the amount of $3.2 million, secured by a deed of trust recorded in May, 2002. In July, 2005, that loan was refinanced by an $8.5 million dollar loan provided by Mortgages Ltd., secured by a deed of trust recorded that same month. Almost $3 million of the proceeds of that loan were used to satisfy *741 the First Commonwealth debt and obtain a release of the First Commonwealth deed of trust.

In December, 2006, the owner obtained a new loan from Choice Bank in the amount of $9.3 million. It was secured by a deed of trust recorded that same month. Approximately $7.3 million of the proceeds of the Choice loan were used to satisfy the debt to Mortgages Ltd. and obtain a release of its 2005 deed of trust.

By the time the Choice Bank deed of trust was recorded in December, 2006, however, work was already underway on the remodeling. KGM was the general contractor who had a contract with the owner in October, 2006, to perform demolition work. KGM asserts, and it is apparently undisputed, that KGM first supplied labor and materials to its construction project on November 15, 2006, more than a month prior to the recordation of the Choice Bank deed of trust. 1

The Choice Bank debt was refinanced by another loan from Mortgages Ltd. in the amount of $75.6 million, in May, 2007. The deed of trust securing that debt was recorded on May 16, 2007. From the proceeds of this second Mortgages Ltd. loan, more than $8.9 million was used to satisfy the Choicé Bank debt and obtain a release of its 2006 deed of trust.

More than six months later, the owner signed another contract with another general contractor, Summit Builders. It commenced work on January 1, 2008, and recorded its notice and claim of mechanics’ and materialmen’s lien in July, 2008.

Summit claims that although it had a separate contract with the owner, some of the work it contracted to do was on the same “project” that KGM had worked on, the demolition of the interior of the building to prepare for the substantial remodeling.

THE ISSUES

Mortgages Ltd. has moved for summary judgment against Summit Builders and all of its subcontractors. Mortgages asserts that because portions of the proceeds of its loan were used to pay off prior secured debts, Mortgages Ltd. is entitled to the priority of those prior deeds of trust under the doctrine equitable subrogation.

And even if Mortgages is not subrogated to the priority of the Choice deed of trust, it asserts that its own deed of trust is prior to Summit’s liens, because Summit did not begin work until after recordation of Mortgages deed of trust and a second general contractor cannot claim priority back to the commencement of work by a prior general contractor, KGM. This could be called the “separate contract” theory, as distinguished from the “single project” theory of the priority of mechanic’s liens.

EQUITABLE SUBROGATION

Probably the most accurate and authoritative statement of the doctrine of equitable subrogation as now recognized in Arizona is found in the 1965 Court of Appeals decision in Petermanr-Donnelly:

[A] third person, having agreed to advance money to discharge an encumbrance on property of another, where he is not a volunteer, and where payment is made under an agreement that he will be substituted in place of the holder of the encumbrance, is entitled to subrogation, whether such agreement is express or whether such agreement is implied. 2

*742 There is no dispute here that Mortgages Ltd. agreed to advance money to discharge the owner’s obligation to Choice Bank. Nor is there any dispute that in doing so, Mortgages was not acting as a volunteer. Most of the argument has focused on the nature of the express or implied agreement that Mortgages would be substituted in place of Choice Bank as to lien priority.

Arizona case law seems to hold that the subsequent lender’s intent to obtain first lien priority is sufficient evidence, standing alone, to satisfy the agreement requirement. In Lamb, 3 the Court of Appeals found sufficient evidence of the agreement to subrogate from the escrow closing instructions that required a title insurance policy showing the lender to have a valid first lien against the property. Those same facts exist here. It is significant that in Lamb, the trial court had denied equitable subrogation and granted summary judgment in favor of the lien claimants, but the Court of Appeals reversed based upon that escrow closing instruction. Summit’s only argument on this point is that “the fact that ML required that a title insurance policy insure it for first lien position does not evidence the meeting of the minds required for an express or implied agreement.” But that is essentially the holding of Lamb, that such an escrow requirement can provide sufficient evidence to satisfy the requirement of an implied agreement to subrogate.

But Lamb did not hold that such an escrow requirement itself satisfies the requirement of an agreement to subrogate. If the escrow requirement were conclusive, then the Court of Appeals would have remanded with instruction to enter judgment in favor of the lender. Instead, the Court of Appeals merely reversed the summary judgment that the trial court had granted in favor of the lien claimants and remanded for “further proceedings consistent with this opinion.”

Thus the holding of Lamb was that while an escrow instruction can provide some evidence of an implied agreement to subrogate, such evidence must be weighed with all other evidence of such an agreement or the lack of any such agreement.

This Court initially granted summary judgment for Mortgages Ltd. because the lien claimants had not responded to the motion with any evidence to the contrary. They have moved for rehearing, however, based on documents subsequently disclosed by Mortgages Ltd., which they contend provide evidence that there was no actual or implied agreement to subrogate.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sourcecorp, Inc. v. Norcutt
274 P.3d 1204 (Arizona Supreme Court, 2012)
Sourcecorp Inc v. D norcutt/S Norcutt
Arizona Supreme Court, 2012

Cite This Page — Counsel Stack

Bluebook (online)
459 B.R. 739, 2011 WL 5022681, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jeffrey-c-stone-inc-v-central-monroe-llc-in-re-mortgages-ltd-arb-2011.