Aesthetic Property Maintenance, Inc. v. Capitol Indemnity Corp.

900 P.2d 1210, 183 Ariz. 74, 197 Ariz. Adv. Rep. 3, 1995 Ariz. LEXIS 80
CourtArizona Supreme Court
DecidedAugust 16, 1995
DocketCV-94-0327-PR
StatusPublished
Cited by29 cases

This text of 900 P.2d 1210 (Aesthetic Property Maintenance, Inc. v. Capitol Indemnity Corp.) is published on Counsel Stack Legal Research, covering Arizona Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Aesthetic Property Maintenance, Inc. v. Capitol Indemnity Corp., 900 P.2d 1210, 183 Ariz. 74, 197 Ariz. Adv. Rep. 3, 1995 Ariz. LEXIS 80 (Ark. 1995).

Opinion

OPINION

MARTONE, Justice.

We are asked to decide whether substantial compliance with our contractor licensing statute can satisfy the licensing prerequisite to a civil action under A.R.S. § 32-1153. We hold that it can.

I. BACKGROUND

Aesthetic Property Maintenance, Inc. (APM) is in the landscaping business. It became a licensed contractor in January, 1990, and renewed its license in December, 1990. It had recently moved and included its new address with the renewal.

In late 1991, the Registrar of Contractors erroneously sent a renewal notice to APM’s old address. APM’s forwarding order with the post office had since expired. APM therefore did not receive the notice and did not renew its license, which was suspended by operation of law on January 1, 1992. APM discovered its suspension in late June, 1992, and immediately sought and received reinstatement. During the lapse, APM maintained its general liability insurance, workers’ compensation insurance and contractor’s license bond.

APM entered into a contract with Howell Constructors, Inc. in mid-December, 1991, (and thus before suspension) to do landscaping and irrigation work on a City of Glendale park. APM finished that project on March 5, 1992 (during suspension). In mid-January, 1992, (during suspension) it entered into another contract with Howell to do similar work for Dysart Junior High School. APM finished that project on August 25, 1992 (after reinstatement).

Because Howell failed to pay in full, APM brought an action against it and its surety, Capitol Indemnity Corporation (Capitol), for the balances due. Howell defaulted. Capitol raised the defense of nonlicensure. Acknowledging a preference for ruling otherwise, but believing that it was constrained by our cases, the superior court granted judgment in favor of Capitol on APM’s and Capitol’s cross-motions for summary judgment.

The court of appeals affirmed. It shared the trial court’s concern, but felt similarly limited by earlier case law. It held that A.R.S. § 32-1153 barred APM from recovering for either project because APM was not licensed at the time the cause of action arose for the Glendale project and at the time it entered into the Dysart contract. We granted review to decide whether § 32-1153 is a bar to an action even where there has been substantial compliance with the licensing statute.

APM concedes that it was not licensed during portions of critical times as required by § 32-1153, but argues that we should follow cases from other states and adopt a *76 substantial compliance test. Capitol argues that § 32-1153 requires strict compliance.

II. ANALYSIS AND RESOLUTION

A. Arizona’s Licensing Scheme

A.R.S. §§ 32-1101 to -1170.03 set forth the requirements for obtaining and keeping a contractor’s license. Among other things, contractors must qualify under § 32-1122, maintain a surety bond or cash deposit, § 32-1152, and not commit any act or omission listed in § 32-1154(A). A.R.S. § 32-1153 sets forth prerequisites for bringing an action for unpaid work. It provides:

No contractor as defined in § 32-1101 shall ... commence or maintain any action in any court of the state for collection of compensation for the performance of any act for which a license is required by this chapter without alleging and proving that the contracting party whose contract gives rise to the claim was a duly licensed contractor when the contract sued upon was entered into and when the alleged cause of action arose.

Although we have not decided whether substantial compliance with the licensing statute satisfies § 32-1153, we have applied the statute before.

In Northen v. Elledge, 72 Ariz. 166, 232 P.2d 111 (1951), a contractor knowingly allowed his license to expire before finishing a project, and made no effort to renew it. The owner defaulted. Northen brought an action in which the owner raised the predecessor to § 32-1153 as a defense.. That earlier statute only required licensing at the time the cause of action arose, and we thus rejected North-en’s argument that his license at the time he entered into the contract was adequate. Id. at 171, 232 P.2d at 116. We also rejected his argument that equity favored his recovery, and noted that if contract performance were the only test, the statute would have little effect. Id. at 173, 232 P.2d at 118. But Northen never argued that in addition to performing his contract he substantially complied with the licensing statute. Nor could he have in light of the facts of the case. He knew his license had expired, but continued to work and never bothered to renew it, even up to the time of bringing the action. Thus, this court did not have an opportunity to decide whether substantial compliance with the licensing statute is adequate under § 32-1153. The issue is therefore one of first impression. 1

B. Substantial Compliance and Statutory Purpose

Our eases suggest that whether a rule of strict or substantial compliance applies depends upon which rule promotes legislative purpose. In Matcha v. Wachs, 132 Ariz. 378, 646 P.2d 263 (1982), we held that substantial compliance with mortgage redemption statutes was “sufficient to perfect a hen creditor’s right to redeem.” Id. at 379, 646 P.2d at 264. A lienholder tardily filed documents required to redeem foreclosed property and improperly filed copies instead of originals. We said that “[wjhether a statute should be given a strict or equitable interpretation must be decided in accordance with the legislature’s intent in enacting that statute.” Id. at 381, 646 P.2d at 266. The statute’s purpose was to insure that property is sold at a fair price and that creditors are paid in order of priority. A rule of substantial compliance would not defeat that purpose. We considered “the nature and extent of the deviation from the statutory plan, the fulfillment or nonfulfillment of the statutory purpose, and the prejudice or lack of prejudice to junior creditors” whom the statute was designed to protect. Id.; see also State v. McEuen, 42 *77 Ariz. 385, 392, 26 P.2d 1005, 1008 (1933) (“The first and most important principle of statutory interpretation is that the intent of the legislature is to be ascertained and followed____ The second, at least in Arizona, is that statutes shall be liberally construed to effect their objects and to promote justice.”).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Marketech v. Process Service
Court of Appeals of Arizona, 2025
Greenwell v. Allen
Court of Appeals of Arizona, 2022
Chavira v. Armor Designs of Delaware, Inc.
356 P.3d 334 (Court of Appeals of Arizona, 2015)
Kost v. Aroc
Court of Appeals of Arizona, 2014
Wb, the Building Company, LLC. v. El Destino
257 P.3d 1182 (Court of Appeals of Arizona, 2011)
Smith v. Pinnamaneni
254 P.3d 409 (Court of Appeals of Arizona, 2011)
Baltimore Street Builders v. Stewart
975 A.2d 271 (Court of Special Appeals of Maryland, 2009)
Fowler Brothers, Inc. v. Bounds
2008 NMCA 091 (New Mexico Court of Appeals, 2008)
Marco C. v. Sean C.
181 P.3d 1137 (Court of Appeals of Arizona, 2008)
Martinez v. Goddard
521 F. Supp. 2d 1002 (D. Arizona, 2007)
TOWN OF GILBERT PROSECUTOR'S OFC. v. Downie
162 P.3d 669 (Court of Appeals of Arizona, 2007)
Town of Gilbert Prosecutor's Office v. Downie
162 P.3d 669 (Court of Appeals of Arizona, 2007)
Twin Peaks Construction Inc. v. Weatherguard Metal Construction, Inc.
154 P.3d 378 (Court of Appeals of Arizona, 2007)
Bentivegna v. Powers Steel & Wire Products, Inc.
81 P.3d 1040 (Court of Appeals of Arizona, 2004)
Crowe v. Hickman's Egg Ranch, Inc.
41 P.3d 651 (Court of Appeals of Arizona, 2002)
State v. Wilkinson
10 P.3d 634 (Court of Appeals of Arizona, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
900 P.2d 1210, 183 Ariz. 74, 197 Ariz. Adv. Rep. 3, 1995 Ariz. LEXIS 80, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aesthetic-property-maintenance-inc-v-capitol-indemnity-corp-ariz-1995.