Cemex Construction Materials South, LLC v. Falcone Brothers & Associates, Inc.

349 P.3d 210, 237 Ariz. 236, 711 Ariz. Adv. Rep. 16, 2015 Ariz. App. LEXIS 53
CourtCourt of Appeals of Arizona
DecidedApril 30, 2015
Docket2 CA-CV 2014-0044
StatusPublished
Cited by3 cases

This text of 349 P.3d 210 (Cemex Construction Materials South, LLC v. Falcone Brothers & Associates, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cemex Construction Materials South, LLC v. Falcone Brothers & Associates, Inc., 349 P.3d 210, 237 Ariz. 236, 711 Ariz. Adv. Rep. 16, 2015 Ariz. App. LEXIS 53 (Ark. Ct. App. 2015).

Opinion

OPINION

KELLY, Presiding Judge:

¶ 1 Falcone Brothers & Associates, Inc. (Falcone) appeals from the trial court’s judgment awarding damages to Cemex Construction Materials South, LLC (Cemex) for materials and labor Cemex provided to a public works construction project for which Falcone was the general contractor. Falcone argues the court erred in concluding that notices sent by Cemex to Falcone regarding amounts Cemex was owed satisfied the requirements of Arizona’s “Little Miller Act.” See A.R.S. § 34-223(A) (requiring material-man to provide estimate of costs within twenty days of supplying labor or materials and notice of any unpaid balance within ninety days of completion). Falcone contends Cemex’s notices, which were sent by first class mail with a certificate of mailing, did not comply with § 34-223(A), and Cemex therefore was precluded from bringing its action. For the following reasons, we vacate the judgment and remand for a new trial.

Factual and Procedural Background

¶ 2 The record supports the following facts and procedural history. Falcone was the general contractor for a City of Tucson public works improvement project. The project was bonded and guaranteed by The Guarantee Company of North America (GCNA). Falcone subcontracted with J & S Commercial Concrete Contractors, Inc. (J & S) for concrete work on the project and J & S, in turn, subcontracted with Cemex to provide construction materials.

¶ 3 In 2011, Cemex filed a complaint against J & S, Falcone, and GCNA, alleging it had not been paid for the materials it had supplied to the project. J & S did not answer the complaint, and Cemex obtained a default judgment against it. Cemex then moved for summary judgment against Falcone and GCNA, claiming it was entitled to recover against the statutory payment bond. In its motion, Cemex asserted that it had filed four preliminary twenty day notices to Falcone pursuant to § 34-223(A) before filing suit, and that each notice had been mailed separately via first class mail, postage prepaid, with a certificate of mailing.

¶ 4 In its response to Cemex’s motion, Falcone asserted that “[a]t no time before, during or after The Project did [it] receive a Preliminary Twenty-Day Notice from [Cemex] for materials” Cemex had supplied to J & S, as is required by § 34-223(A). 1 This *238 claim was supported by a declaration from Falcone’s owner, who asserted Falcone had not received any twenty day notices. Falcone also contended that genuine issues of material fact existed regarding whether Cemex had delivered any concrete to the project and the amount of concrete delivered. Subsequently, the trial court granted Cemex’s request to withdraw its motion for summary judgment, allowing the parties additional time for disclosure and discovery.

¶ 5 In December 2012, Cemex renewed in part its motion for summary judgment on the issue of damages, urging that Falcone’s discovery responses indicated Cemex had “supplied at least 837 cubic yards of concrete to the project.” Falcone agreed the project had required 837 cubic yards of concrete but maintained that a genuine issue of material fact existed regarding “how much concrete Cemex actually provided to J & S” for the project.

¶ 6 Falcone then filed a motion for summary judgment, claiming it had not received the statutorily required twenty day notices and Cemex therefore was precluded from bringing its action. It further contended the notices were insufficient to satisfy the statutory requirements because they were sent by first class, rather than by registered or certified mail. Cemex maintained that the four preliminary twenty day notices it had sent by first class mail with certificates of mailing satisfied the statute’s requirements.

¶ 7 In March 2013, the trial court denied Cemex’s motion for partial summary judgment on the issue of damages. After a hearing, the court also denied Falcone’s motion for summary judgment, concluding that Cemex’s certificates of mailing and affidavits were “sufficient to meet the purposes of’ § 34-223(A). After a bench trial on the sole issue of damages, the court entered judgment in favor of Cemex, awarding it $81,913.04 in damages along with prejudgment interest, costs, and attorney fees. Falcone timely appealed. 2 We have jurisdiction pursuant to A.R.S. § 12-2101(A).

Discussion

¶ 8 Falcone argues the trial court erred by concluding that the twenty day notices Cemex sent to Falcone by first class mail satisfied § 34-223(A) as a matter of law. 3 Falcone asserts the statute specifies that both twenty and ninety day notices must be sent only by registered or certified mail, as provided for in the last sentence of that section. See § 34-223(A) (“Such notice shall be served by registered or certified mail, postage prepaid....”). Cemex, by contrast, claims that because this sentence contains the singular form (“[s]uch notice”), it applies only to ninety day notices; this, according to Cemex, leaves an “unfilled statutory gap,” which we should fill by applying the mailing provision found in A.R.S. § 33-992.01(F) (the mechanic’s lien law). Because § 33-992.01 allows for service by first class mail with a certificate of mailing, Cemex maintains its notices were sufficient. We review issues of statutory interpretation and application de novo. Schwarz v. City of Glendale, 190 Ariz. 508, 510, 950 P.2d 167,169 (App.1997).

¶ 9 “The primary rule of statutory construction is to find and give effect to legislative intent.” Mail Boxes, Etc., U.S.A. v. Indus. Comm’n, 181 Ariz. 119, 121, 888 P.2d 777, 779 (1995). To determine that intent, we look first to the plain language of the statute. Canon Sch. Dist. No. 50 v. W.E.S. Constr. Co., 177 Ariz. 526, 529, 869 P.2d 500, 503 (1994). “When a statute is clear, we do not ‘resort to other methods of *239 statutory interpretation to determine the legislature’s intent because its intent is readily discernible from the face of the statute.’ ” In re Estate of Wyatt, 235 Ariz. 138, ¶ 5, 329 P.3d 1040, 1041 (2014), quoting State v. Christian, 205 Ariz. 64, ¶ 6, 66 P.3d 1241, 1243 (2003). But when a statute’s language is ambiguous, we resort to principles of statutory interpretation to discern the legislature’s intent. Bentley v. Building Our Future, 217 Ariz. 265, ¶ 13, 172 P.3d 860, 865 (App.2007).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shoni v. Hansen
Court of Appeals of Arizona, 2020
J. Ball Trust v. Phx Orchard
Court of Appeals of Arizona, 2018
Coombs v. Maricopa County Special Health Care District
387 P.3d 743 (Court of Appeals of Arizona, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
349 P.3d 210, 237 Ariz. 236, 711 Ariz. Adv. Rep. 16, 2015 Ariz. App. LEXIS 53, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cemex-construction-materials-south-llc-v-falcone-brothers-associates-arizctapp-2015.