United States of America, for the Use and Benefit of Ray Moody v. The American Insurance Company

835 F.2d 745, 34 Cont. Cas. Fed. 75,418, 98 A.L.R. Fed. 769, 1987 U.S. App. LEXIS 16287, 1987 WL 22824
CourtCourt of Appeals for the Tenth Circuit
DecidedDecember 15, 1987
Docket85-2792, 86-2042
StatusPublished
Cited by20 cases

This text of 835 F.2d 745 (United States of America, for the Use and Benefit of Ray Moody v. The American Insurance Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States of America, for the Use and Benefit of Ray Moody v. The American Insurance Company, 835 F.2d 745, 34 Cont. Cas. Fed. 75,418, 98 A.L.R. Fed. 769, 1987 U.S. App. LEXIS 16287, 1987 WL 22824 (10th Cir. 1987).

Opinion

BALDOCK, Circuit Judge.

After examining the briefs and the appellate record, this three-judge panel has determined unanimously that oral argument would not be of material assistance in the determination of this appeal. See Fed. R.App. 34(a); 10th Cir.R. 34.1.8(c). The cause therefore is ordered submitted without oral argument.

Between 1982 and 1984, the United States government built an Indian Hospital for the Indian Health Services at Tahle-quah, Oklahoma. The general contractor on the project was Robert E. McKee, Inc. (contractor), who was bonded, pursuant to the Miller Act, 40 U.S.C. § 270a, 1 by defendant-appellant American Insurance Co. (surety). Contractor subcontracted with Green Country Contractors, Inc., who in turn subcontracted with plaintiff-appellee Ray Moody d/b/a A.T. & C. (subcontractor) to perform the following work:

Ceilings (accoustical and drop-in gyp. bid.), Fireproof beams and Columns, Fireproof ceilings with firecode gyp. bid. Including suspension system....

Rec. vol. I, pleading 1, at 3.

The following is a general summary of the controverted facts. Contractor asked subcontractor to lay between 7,000 and 17,-000 square feet of ceiling that were neither drop-in gypsum board nor accoustical board, as specified in the subcontract. Subcontractor alleges that he protested this work soon after the request because he considered it to be work outside the contract. He claims to have first verbally notified an employee of contractor, Everett Barnes, in April or May of 1983 and then to have given written notice prior to completing the work in February, 1984. The notice stated that he objected to the work because it was additional to the contract and that he expected additional compensation. Subcontractor claims that his protests were met by contractor threatening to forfeit payment for the completed work or to charge him one-hundred dollars per hour unless he did the additional work. After notifying the contractor, subcontractor returned to work until the project was completed in February, 1984.

Contractor maintains that the work was part of the contract because the contract language indicated that subcontractor was required to construct all ceilings. He also claims that he discussed the contract coverage with subcontractor, and that subcontractor did not object to this interpretation of the contract. He further asserts that subcontractor did not notify him that he wanted additional payment for that work until he had completed approximately ninety percent of the non-accoustical and non-drop-in gypsum board ceilings in January, 1984. He also denies threatening subcontractor to force subcontractor to do the alleged additional construction.

Contractor refused to pay subcontractor for the alleged additional work. Subcontractor sued surety for $85,784.77 under the Miller Act, 40 U.S.C. § 270b, alleging nonpayment for supplying labor and materials under his contracts with contractor and Green Country Contractors, Inc. On October 25, 1985, a jury awarded subcontractor $55,426.80 in damages. Subsequently, both parties filed motions for attorney’s fees. After a hearing on the issue, the district court denied surety’s motion, and awarded attorney’s fees of $11,-034.00 to subcontractor.

Surety appeals the judgment on several grounds. First, surety asserts that the *747 notice from subcontractor failed to comply with the procedural requirements of the Miller Act, 40 U.S.C. § 270b, 2 on three grounds: (1) it was not timely because it was sent prior to completion of the work; (2) it was not sent by the proper means because it was sent by regular mail rather than by one of the methods prescribed in the statute; and (3) it did not specify the amount of money owed subcontractor under the contract. Second, surety asserts that the trial court erred by refusing to admit the W-2 forms of subcontractor’s employees as evidence relating to subcontractor’s credibility. Third, it proposes that subcontractor’s claim for extra compensation is prohibited under the contract. Finally, surety argues that the attorney’s fees were erroneously granted to subcontractor because such fees are prohibited under the Miller Act.

In general, the Miller Act is ‘entitled to a liberal construction and application in order properly to effectuate the Congressional intent to protect those whose labor and materials go into public projects.’” United States v. Carter, 353 U.S. 210, 216, 77 S.Ct. 793, 796, 1 L.Ed.2d 776 (1957) (quoting Clifford F. MacEvoy Co. v. United States, 322 U.S. 102, 107, 64 S.Ct. 890, 893, 88 L.Ed. 1163 (1944)). The purpose of the notice requirement is to protect the prime contractor by fixing a date beyond which he will not be liable for the subcontractor’s debts. See United States use of Kinlau Sheet Metal Works, Inc. v. Great American Ins. Co., 537 F.2d 222, 223 (5th Cir.1976).

Few circuits have addressed the issue of whether notice prior to completion of the contract is sufficient to meet the “ninety-day” requirement of the Miller Act. The Fourth Circuit has recognized that denying claims under the Miller Act on the ground that the notice was insufficient due to delivery prior to completion of the contract would defeat the purpose of the statute. United States use of Honeywell, Inc. v. A & L Mechanical Contractors, Inc., 677 F.2d 383, 385-86 (4th Cir.1982). The Fourth Circuit also has deemed precompletion notice sufficient because the Miller Act “ninety-day” notice requirement is intended merely to extend the final period within which subcontractors can assert a claim against the general contractor and its surety; it is not to preclude notice prior to the completion of supplying labor or materials Noland Co. v. Allied Contractors, Inc., 273 F.2d 917, 920-21 (4th Cir.1959); cf. United States use of Kinlau Sheet Metal Works, Inc. v. Great American Ins. Co., 537 at 224 (recognizing the fact that notice was sent prior to completion of the contract as merely one factor to be considered in determining the sufficiency of the notice).

Similarly, the Supreme Court has stated that the manner of notice specified in the Act is merely “to assure receipt of the notice, not to make the described method mandatory so as to deny right of suit when the required written notice within the specified time had actually been given and received.” Fleisher Engineering & Constr. Co. v. United States,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Ex Rel. Solsbury Hill v. Liberty Mut.
2012 NMCA 032 (New Mexico Court of Appeals, 2012)
State ex rel Solsbury Hill, LLC v. Liberty Mut. Ins. Co.
2012 NMCA 32 (New Mexico Court of Appeals, 2011)
Tekeley v. Government Accountability Office
173 F. App'x 820 (Federal Circuit, 2006)
Southern Electrical Health Fund v. Kelley
308 F. Supp. 2d 847 (M.D. Tennessee, 2003)
Terry Matthews, Inc. v. C & L CONTRACTING, INC.
959 F. Supp. 1434 (W.D. Oklahoma, 1997)
Vacuum Systems, Inc. v. Washburn
651 A.2d 377 (Supreme Judicial Court of Maine, 1994)
Pipkin v. United States Postal Service
951 F.2d 272 (Tenth Circuit, 1991)
US FOR USE OF LABORERS'PEN. TR. v. Safeco Ins.
707 F. Supp. 286 (E.D. Michigan, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
835 F.2d 745, 34 Cont. Cas. Fed. 75,418, 98 A.L.R. Fed. 769, 1987 U.S. App. LEXIS 16287, 1987 WL 22824, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-of-america-for-the-use-and-benefit-of-ray-moody-v-the-ca10-1987.