United States Ex Rel. Altman v. Young Lumber Company

376 F. Supp. 1290, 20 Cont. Cas. Fed. 83,335, 1974 U.S. Dist. LEXIS 8151
CourtDistrict Court, D. South Carolina
DecidedJune 11, 1974
DocketCiv. A. 73-1062
StatusPublished
Cited by23 cases

This text of 376 F. Supp. 1290 (United States Ex Rel. Altman v. Young Lumber Company) is published on Counsel Stack Legal Research, covering District Court, D. South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Ex Rel. Altman v. Young Lumber Company, 376 F. Supp. 1290, 20 Cont. Cas. Fed. 83,335, 1974 U.S. Dist. LEXIS 8151 (D.S.C. 1974).

Opinion

ORDER

SIMONS, District Judge.

This action was instituted pursuant to 40 U.S.C. § 270b, commonly referred to as the Miller Act, alleging claims based upon the rental of a bulldozer and tractor to the defendant, Young Lumber Company, while Young Lumber Company was a sub-contractor to the defendant, Ruscon Construction Company, in the construction of two barracks at Parris Island, South Carolina, for the United States Navy. The Peoples Bank of Beaufort, S. C., was made a third-party defendant by the defendants, who alleged that the bank had agreed to indemnify Ruscon Construction Company against the claim of the plaintiffs herein.

This matter was tried before the court without a jury at Charleston on April 1, 1974. Thereafter, counsel for the parties submitted proposed orders and memoranda. This memorandum of decision shall constitute the court’s findings of fact and conclusions of law as required by Rule 52, Federal Rules of Civil Procedure.

Certain factual matters are not in dispute. In late 1970, the defendant, Ruscon Construction Company (hereinafter “Ruscon”) entered into a contract with the United States by the terms of which Ruscon was to act as general contractor for the construction of two barracks for the United States Marine Corps at Parris Island, S. C. The defendant Young Lumber Company (“Young Lumber”) was issued a subcontract for the performance of certain clearing, grading, demolition, paving, sewer and drain installation, and grassing and landscaping. Pursuant to the Act, Ruscon was required to furnish a payment and performance bond, and the defendant Travelers Indemnity Company (“Travelers”) acted as the bonding company for Ruscon.

As the subcontract began to be performed in January 1971, the plaintiff Altman and the defendant Young were associated, and the nature of that relationship is one of the issues raised in this proceeding. Both Altman and Oscar Young, former president of Young Lumber, testified that Altman was to be Young’s superintendent on the job. It was Altman who had estimated the job for Young. Young and Altman were to receive an equal salary by check on a weekly basis during the job, and at the end of the job they were to split the profits. Altman testified that he had no ownership in Young Lumber Company, and that he was its employee. Young testified that the two men had planned for Altman to buy stock in and become an officer of the company, and to this end Altman paid Young Four Thousand ($4,000.00) Dollars. However, negotiations fell through and Young refunded Altman’s Four Thousand ($4,000.00) Dollars.

Some time during the performance of the subcontract, a source who was supposed to supply equipment to Young defaulted on its agreement, and Altman brought on the job the tractor and bulldozer in dispute. It is Altman’s contention that at this time he and Young entered into an oral agreement whereby Young agreed to pay Altman a reasonable rental for this equipment. According to Young, nothing was said about equipment rental when Altman brought this machinery on the job; Young spe *1294 eifically denies that there was any understanding at all between he and Altman as to the rental of this equipment. It is for the rental value of these two pieces of machinery that this suit is brought. 1

Altman submitted bills to Young Lumber asserting that the tractor and its attachments were used on the job from May to November 1971, and from March to August 30, 1972, for which Altman claims a rental value of Four Thousand, Eight Hundred ($4,800.00) Dollars. The bulldozer is shown by the invoice to have been on the job from February 1, 1971, to August 30, 1972, for which Altman billed Young Lumber rental value, of Fifteen Thousand, Two Hundred ($15,200.00) Dollars. Thus the last date for which equipment rental is claimed by plaintiff is August 30, 1972.

Young testified that the subcontract eventually “started to go sour” and that when the job was over, he was approximately $50,000 deeper in debt than he was when the job began. Apparently because of these financial difficulties, Young Lumber left the job sometime in August, 1972. Although the project was very nearly complete at that time, there remained some grading, top soiling, and grassing to be completed and curbing was to be adjusted, according to Altman’s testimony. Altman agreed to perform this work, but required payment in advance. Therefore, Young deposited with Ruscon project superintendent Joe Wooten One Thousand ($1,000.00) Dollars for project completion, and when Altman completed this work on or about September 8, 1972, Wooten paid him the One Thousand ($1,000.00) Dollars. Thus although Altman did work on the project after August 30, that is the last date for which he claims monies due from Young Lumber for the rental of his equipment.

In compliance with the Act’s requirements, Altman notified defendant Ruscon in September, 1972, that plaintiff looked to it for payment of Twenty Thousand ($20,000.00) Dollars allegedly due as rental for the equipment. Ruscon contends, and the court does not understand plaintiff to dispute, that Ruscon has paid Young in full for the subcontract. Plaintiff’s complaint against Young Lumber, Ruscon, and Travelers was filed in this court on August 31, 1973. Ruscon and Travelers thereafter filed a third party complaint against the Peoples Bank of Beaufort on the basis of an indemnity agreement. The bank admits its liability in the event a judgment is rendered against Ruscon and Travelers.

The defendants collectively rely on three defenses: (1) that the Miller Act statute of limitations providing that no suit shall be brought after the expiration of one year after the date on which the last labor or material was supplied bars plaintiff’s claim in this case; (2) that plaintiff Altman and the defendant Young Lumber were either partners or joint venturers in the performance of this subcontract, and that as Ruscon has paid Young in full for *1295 performance of the subcontract, Altman’s claim is thereby barred; and (3) that there simply was no contract, expressed or implied, between Altman and Young for the rental of Altman’s equipment. 2 These defenses will be discussed seriatim.

Timeliness of suit. As to time for institution of suit, the Miller Act provides in pertinent part as follows:

“[N]o such suit shall be commenced after the expiration of one year after the day on which the last of the labor was performed or material was supplied. . . .”40 U.S.C. § 270b(b).

As plaintiff concedes that the period for which he seeks equipment rental ceased on August 30,1972, and as the complaint instituting this action was not filed until August 31, 1973, defendants contend that the action is barred by the Act’s statute of limitations.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Southern Electrical Health Fund v. Kelley
308 F. Supp. 2d 847 (M.D. Tennessee, 2003)
United States v. W.H. Cates Construction Co.
972 F.2d 987 (Eighth Circuit, 1992)
Shaw v. Delta Airlines, Inc.
798 F. Supp. 1453 (D. Nevada, 1992)
COSTA AND SONS CONSTRUCTION COMPANY, INC. v. Long
412 S.E.2d 450 (Court of Appeals of South Carolina, 1991)
United States v. Tway, Inc.
938 F.2d 583 (Federal Circuit, 1991)
Bailey v. Faux
704 F. Supp. 1051 (D. Utah, 1989)
W.F. Magann Corp. v. Diamond Manufacturing Co.
580 F. Supp. 1299 (D. South Carolina, 1984)
United States v. White Contracting Company
649 F.2d 29 (First Circuit, 1981)
Eastern Electrical Co. v. Taylor Woodrow Blitman Construction Corp.
414 N.E.2d 1023 (Massachusetts Appeals Court, 1981)
Stone v. First Wyoming Bank
625 F.2d 332 (First Circuit, 1980)
Stone v. First Wyoming Bank N. A.
625 F.2d 332 (Tenth Circuit, 1980)
Sasportes v. Copacabana
581 F.2d 1204 (Fifth Circuit, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
376 F. Supp. 1290, 20 Cont. Cas. Fed. 83,335, 1974 U.S. Dist. LEXIS 8151, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-altman-v-young-lumber-company-scd-1974.