United States Ex Rel. Gulfport Piping Co. v. Monaco & Sons, Inc.

222 F. Supp. 175, 1963 U.S. Dist. LEXIS 7734
CourtDistrict Court, D. Maryland
DecidedSeptember 24, 1963
DocketCiv. A. 12996
StatusPublished
Cited by15 cases

This text of 222 F. Supp. 175 (United States Ex Rel. Gulfport Piping Co. v. Monaco & Sons, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Ex Rel. Gulfport Piping Co. v. Monaco & Sons, Inc., 222 F. Supp. 175, 1963 U.S. Dist. LEXIS 7734 (D. Md. 1963).

Opinion

WINTER, District Judge:

...Hi this suit, brought under the Miller ’ Act, 40 U.S.C.A. § 270a et seq., Gu-lfpol# • Piping Company (hereafter called “Gulf-- s port”) is the use plaintiff. Named as de-: fendants are Monaco and Son, Inc. (Rere-" after called “Monaco”), Durant Insulate'#'’ Pipe Company, Inc. (hereafter Called' “Durant”), and Hartford Accident an#^ Indemnity Company (hereafter called; “Hartford”), the corporate surety-oh-.the' Miller Act bond provided by Monaco after-', the -award to it of a contract for the con- - struction and completion of a steam-d-is- ’ tribution system at Andrews Air Force" Base, located in the State of Maryland. : The contract was awarded, on June'3'0,..' 1959,' through the United States Corps of Engineers. On July 13, 1959 Monaco ,was_given notice to proceed. .......

Monaco was the successful bidder on the contract, and the work to be performed under the contract was divided into five categories: (1) concrete, (2) excavation, trenching and backfilling, (3) heat distribution system, (4) storm drains, and (5) waterproofing. Prior to its bid, Monaco had obtained from Durant a quotation for furnishing certain of the materials required for the heat distribution system and, indeed, had obtained some assistance from Durant in preparing its bid. About three weeks after Monaco was notified by the Corps of Engineers to proceed, it issued a purchase order to - Durant to “furnish all underground conduit, accessories and necessary fittings for a complete installation as required by the project plans and specifications and all addenda,” as required by the contract. Durant, in turn, gave a purchase order to Associated Piping and Engineer- * ing Company, Inc. (hereafter called “Associated”) to furnish materials and fab- , ricate the heat distribution system. The materials were sold to Durant f. o. b. Gulfport, Mississippi, and were to be : shipped to Monaco at Andrews Field. Durant was to be billed in accordance with a letter agreement between Durant and Associated. It may be noted that deliveries were not billed on a monthly , basis, as contemplated by the letter s> agreement. On or about December 31, 1959, Associated, which had partially '.-performed the contract, sold its physical " assets to the use plaintiff Gulfport, to which was assigned Durant’s purchase order to Associated and which completed .^performance of the contract.

Monaco made payments to Durant from time to time, beginning October 27, 1959, ''other than in accordance with the letter ’agreement, but Durant did not make payara ent to Gulfport. This suit ensued. iGplfport’s theory of the case is that Durant was a subcontractor to Monaco, ’ -the prime contractor, and Gulfport as a supplier to a subcontractor is entitled to the protection of a Miller Act bond, MacEvoy Co. v. United States, 322 U.S. 102, 64 S.Ct. 890, 88 L.Ed. 1163 (1944). Monaco and Hartford contend that Dur *178 ■ant was a supplier to Monaco, and Gulf-port a supplier to a supplier; hence, Gulfport is beyond the scope of protection of a Miller Act bond, MacEvoy Co. v. United States, supra. Even if Durant be determined to be a subcontractor to Monaco, Monaco and Hartford contend that Gulfport is barred from recovery by estoppel and principles of the law of agency applicable to undisclosed principals. The latter contention is that Durant acted as agent for Gulfport, the undisclosed principal, so that payment to Durant constituted full discharge of Monaco’s obligations, if any, to Gulfport. If, in fact and in law, Durant was a subcontractor, Monaco and Hartford make no contention that Gulfport has not fully complied with the procedural requirements of the Miller Act as to notice, time of notice and sufficiency of notice.

As a result of the initial complaint, Hartford filed a cross claim against Monaco, based on the provisions of an indemnity agreement between them entered into in connection with the giving of the bond praying a judgment over if it be held liable to Gulfport. Linked to its defense that Durant was an agent for the undisclosed principal, Gulfport, Monaco filed a counterclaim against Gulf-port to recover damages for various alleged defaults of Durant in the performance of its contract. Other causes of action and cross claims were also filed, but, by stipulation, settled prior to the trial.

With regard to the main issue in the original suit, the leading ease on the question of the scope of protection of the Miller Act, and bonds given in compliance with the Act, is MacEvoy Co. v. United States, supra, and that case undertakes to define what is a subcontractor. In that case the court pointed out (322 U.S. p. 108, 64 S.Ct. p. 894, 88 L.Ed. 1163) “In a broad, generic sense a subcontractor includes anyone who has a contract to furnish labor or material to the prime contractor,” but after considering the state of the law prior to the enactment of the Miller Act and the legislative history of the Miller Act the court concluded that the word “subcontractor” as used in the Miller Act was used (322 U.S. p. 110, 64 S.Ct. p. 895, 88 L.Ed. 1163) “ * * * in its technical sense so as to exclude materialmen and laborers.” The court defined the technical meaning of the word “subcontractor” as (322 U.S. p. 109, 64 S.Ct. pp. 894-895, 88 L.Ed. 1163) “ * * * one who performs for and takes from the prime contractor a specific part of the labor or material requirements of the original contract, thus excluding ordinary laborers and materialmen.” Coupled with this definition, the court admonished the lower courts (322 U.S. p. 107, 64 S.Ct. p. 893, 88 L.Ed. 1163) “The Miller Act * * * is highly remedial in nature.

It is entitled to a liberal construction and application in order properly to effectuate the Congressional intent to protect those whose labor and materials go into public projects. * * * But such a salutary policy does not justify ignoring plain words of limitation and imposing wholesale liability on payment bonds.” (emphasis supplied)

Like so many cases of this type, factually, its precise counterpart is not to be found among the decided cases, and not all of the facts as disclosed by the evidence point unerringly to the conclusion that Durant either was or was not a subcontractor to Monaco. I find the following facts to support the conclusion that Durant was a subcontractor to Monaco:

1 — Subject to basic design by the Corps of Engineers and the specifications of the contract, and with supervision and approval of the Corps of Engineers, the entire responsibility for the precise design, fabrication and installation of the heating distribution system was vested in Monaco. Under the prime contract, Monaco was obligated to furnish shop drawings of the system. Monaco did not prepare these shop drawings. It acted as a conduit in transmitting them to and from the Corps of Engineers, but the responsibility of preparing them was delegated to and carried out by Durant. In addition, Durant was required to make certain engineering calculations in *179 connection with the system, including, ■' return look stress calculations, anchor details, gauge of steel bands, and thick’-; ness of end casings. The design .of ex^ pánsion loops was another responsibility placed on Monaco by the prime contract * and, thus, delegated to and performed, by-Durant.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States ex rel. Adams Steel, LLC v. Elkins Contractors, Inc.
225 F. Supp. 3d 351 (D. South Carolina, 2016)
Preussag International Steel Corp. v. March-Westin Co.
655 S.E.2d 494 (West Virginia Supreme Court, 2007)
Unadilla Silo Co. v. Hess Bros.
586 A.2d 226 (Supreme Court of New Jersey, 1991)
United States v. Morrison-Knudsen Company, Inc.
687 F.2d 129 (Sixth Circuit, 1982)
UNITED STATES, ETC. v. Lane Const. Corp.
477 F. Supp. 400 (M.D. Pennsylvania, 1979)
United States Ex Rel. Altman v. Young Lumber Company
376 F. Supp. 1290 (D. South Carolina, 1974)
McElhose v. Universal Surety Co.
158 N.W.2d 228 (Nebraska Supreme Court, 1968)
United States v. Lembke Construction Company
370 F.2d 293 (Tenth Circuit, 1966)
United States v. Msi Corporation
350 F.2d 285 (Second Circuit, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
222 F. Supp. 175, 1963 U.S. Dist. LEXIS 7734, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-gulfport-piping-co-v-monaco-sons-inc-mdd-1963.