United States Ex Rel. Potomac Rigging Co. v. Wright Contracting Co.

194 F. Supp. 444, 1961 U.S. Dist. LEXIS 5350
CourtDistrict Court, D. Maryland
DecidedMay 11, 1961
Docket11772
StatusPublished
Cited by7 cases

This text of 194 F. Supp. 444 (United States Ex Rel. Potomac Rigging Co. v. Wright Contracting Co.) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Ex Rel. Potomac Rigging Co. v. Wright Contracting Co., 194 F. Supp. 444, 1961 U.S. Dist. LEXIS 5350 (D. Md. 1961).

Opinion

CHESNUT, District Judge.

This is a suit under the Miller Act (40 U.S.C.A. §§ 270a and 270b) which provides :

“§ 270a. Bonds of contractors for public buildings or works; waiver of bonds covering contract performed in foreign country
“(a) Before any contract, exceeding $2,000 in amount, for the construction, alteration, or repair of any public building or public work of the United States is awarded to any person, such person shall furnish to the United States the following bonds, * * *.
“(2) A payment bond with a surety or sureties satisfactory to such officer for the protection of all persons supplying labor and material in the prosecution of the work provided for in said contract for the use of each such person. * *
“§ 270b. Same; rights of persons furnishing labor or material
“(a) Every person who has furnished labor or material in the prosecution of the work provided for in such contract, in respect of which a payment bond is furnished under section 270a of this title and who has not been paid in full therefor before the expiration of a period of ninety days after the day on which the last of the labor was done or performed by him or material was furnished or supplied by him for which such claim is made, shall have the right to sue on such payment bond for the amount, or the balance thereof, unpaid at the time of institution of such suit and to prosecute said action to final execution and judgment for the sum or sums justly due him: Provided, however, That any person having direct contractual relationship with a subcontractor but no contractual relationship express or implied with the contractor furnishing said payment bond shall have a right of action upon the said payment bond upon giving written notice to said contractor within ninety days from the date on which such person did or performed the last of the labor or furnished or supplied the last of the material for which such claim is made, * * * ”.

On December 16, 1957 the Wright Company, a Georgia corporation, entered into a contract with the United States Government (Department of the Interi- or) for the construction of certain highway work on the George Washington *446 Memorial Parkway in Montgomery County, Maryland, in the amount of $1,037,235. The contract, among many provisions, required the construction in connection with retaining walls or abutments for the roadway, of a certain amount of “cribbing” consisting of precast concrete. On April 16, 1958 the contractor by written order purchased this cribbing from the Prestressed Structures, Inc. The order required that the cribbing should be delivered at or near the job site at the “truck site” promptly as required. In due course it was all delivered and was fully paid for by the Wright Company to the Prestressed Company. In order to make the deliveries as required by the purchase order, Prestressed employed the Potomac Rigging Company, a trucker, to transport the cribbing from the Prestressed plant to the truck site. In due course Potomac Rigging Company, the plaintiff in this case, rendered bills for hauling services from time to time to Prestressed; but these bills were not paid by Prestressed before the latter went into voluntary liquidation and so notified the Potomac Company on January 16, 1959. Thereafter, about March 3, 1959 Potomac, not having been paid by Prestressed, notified Wright that it claimed payment from it as the prime contractor in the amount of $1252.45, and now alleges that the last of the deliveries was within 90 days before the receipt of said notice.

The principal and the critical point to be decided is whether, in all the circumstances of the case, the Prestressed Company can properly be considered as a subcontractor or was only a supplier of materials. As there was no direct contractual relationship between the use plaintiff and the Wright Company it is apparent at once that the case is governed by the proviso in section 270b (a) above quoted. In the case of MacEvoy Co. v. United States, 1944, 322 U.S. 102, 64 S.Ct. 890, 88 L.Ed. 1163, it was held by the Supreme Court in construing and applying this proviso that, as the statute does not in itself define what constitutes a subcontractor (as compared with a material supplier) the meaning of the term must be found in the usage of the trade.

The important facts and circumstances are these:

1. It is not disputed that to warrant a recovery in this case the plaintiff has the burden of proof to show (a) that Prestressed was a subcontractor and not only a material supplier and (b) that the notice from Potomac to Wright was within 90 days after the last delivery of cribbing. As the Potomac Company had no contractual relations with the Wright Company and its relation to the matter was limited to mere transportation of the cribbing from Prestressed to the truck site, it cannot recover in this case even if it gave the required notice within 90 days unless it can show that the transportation it performed was for a “subcontractor” of the Wright Company. That is to say, the plaintiff’s right to recover in this case depends upon the status of Prestressed, whether a subcontractor or merely a material supplier.

2. The total amount to be paid by the Government to Wright for the work to be done was $1,037,235. The amount paid by Wright to Prestressed was $13,-936.16. All of the latter had been paid by Wright long prior to the notice from Potomac to Wright.

3. Prestressed was not asked by Wright to furnish a payment bond or any security for the full performance of the obligation under the accepted purchase contract.

4. In Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects, (Defendant’s Exhibit No. 1, page 19), it is stated:

“Section 8 — Prosecution and Progress
Article 8.1 Subcontracting.

* * * No portion of the contract shall be sublet except with the written consent of the engineer. Requests for permission to sublet any portion of the contract shall be in writing and accompanied by a showing that the organiza *447 tion that will perform the work is particularly experienced and equipped for the work. Written consent to sublet any portion of the contract shall not be construed to relieve the contractor of any of his responsibility under the contract.”

On page 3, Article 1.2, a subcontractor is defined as — "Any individual, firm, or corporation to whom the contractor, with the written consent of the engineer, sublets any part of the contract.”

No request was ever made by Wright for approval of Prestressed as a subcontractor and the evidence does not show that the Government, by its engineer, approved Prestressed as a subcontractor.

5. The contract for the work (page D.5) provides with respect to the cribbing separately between the “materials” constituting it and the construction of the cribbing on the site of the work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
194 F. Supp. 444, 1961 U.S. Dist. LEXIS 5350, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-potomac-rigging-co-v-wright-contracting-co-mdd-1961.