W.F. Magann Corp. v. Diamond Manufacturing Co.

580 F. Supp. 1299, 32 Cont. Cas. Fed. 72,702, 1984 U.S. Dist. LEXIS 19283
CourtDistrict Court, D. South Carolina
DecidedFebruary 22, 1984
DocketCiv. A. 81-1149-1
StatusPublished
Cited by5 cases

This text of 580 F. Supp. 1299 (W.F. Magann Corp. v. Diamond Manufacturing Co.) is published on Counsel Stack Legal Research, covering District Court, D. South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
W.F. Magann Corp. v. Diamond Manufacturing Co., 580 F. Supp. 1299, 32 Cont. Cas. Fed. 72,702, 1984 U.S. Dist. LEXIS 19283 (D.S.C. 1984).

Opinion

ORDER AND JUDGMENT

HAWKINS, District Judge.

This case, heard by the court without a jury during its July 1983 term in Charleston, South Carolina, arose as a result of a dispute between the primary contractor on the Corps of Engineers Murrell’s Inlet Navigation Project (“Project”), W.F. Ma-gann Corporation (“Magann”), and the dredging subcontractor, Diamond Manufacturing Company, Inc. (“Diamond”). Ma-gann brought this action against Diamond and its surety, Aetna Casualty and Surety Company (“Aetna”), alleging breach of the subcontract. Diamond, in three counterclaims against Magann and in a counterclaim and cross-claim against Magann and Aetna in quantum, meruit under the Miller Act, 40 U.S.C. §§ 270a-270d, alleges defective specifications, changed conditions, differing site conditions, improper application of specifications, and impossibility, all amounting to a breach of the subcontract.

Having heard the testimony, having studied the exhibits, and having reviewed all the evidence, the court makes the following findings of fact and conclusions of law.

FINDINGS OF FACT

A. BACKGROUND

On September 2, 1977, Magann entered into a contract with the United States Army Corps of Engineers (“Corps”) for construction of a channel and jetty system to provide a navigable entrance to Mur-rell’s Inlet from the Atlantic Ocean. The Project consisted of the construction of stone jetties seaward of the Inlet and the dredging of channels and a deposition basin in and about the Inlet.

The contract between Magann and the Corps provided that it was to be performed in accordance with the General Provisions and Specifications DACW 60-77-B-0014, dated 14 June 1977, as amended.

The “General Provisions” and the “Specifications” are set forth in a document entitled “Specifications for Construction of *1302 Channel and Jetty System, Murrell’s Inlet Navigation Project, Murrell’s Inlet, South Carolina.”

Subsequently, by instrument dated October 19, 1977, Magann entered into a subcontract with Diamond whereby Diamond agreed to perform “[a]ll dredging work required by Specifications ...” according to varying unit prices for various aspects of the dredging.

The Subcontract further provided that payment to Diamond by Magann should be expressly subject to the provisions of Article 7 — “Payments to the Contractor” of the General Provisions of the Construction Contract and to Paragraphs 1-9 “Payments” and 1-10 “Payments for Mobilization and Demobilization” of the Specifications — Special Provisions of the Construction Contract.

It also provided that payment should be made on the basis of written requisitions from Diamond “as approved by [Magann] and to the extent that payment therefor has been received by [Magann] from [The Corps]____” (Emphasis added.)

Diamond assumed full responsibility for site conditions that might impact the dredging work. Section 5(d) of the Subcontract provides:

PERFORMANCE REQUIREMENTS:

Site Inspection and Conditions: [Diamond] acknowledges and accepts the sole responsibility for unanticipated costs which may result from the nature and location of work and the general and local conditions; those conditions affecting transportation, access, disposal, handling and storage of materials; availability and quality of labor; availability of water and electric power; availability and condition of roads, climatic conditions and seasons; river and ocean hydrology, river stages and ocean tides; physical conditions at the work-sites and the Project area as a whole; topography and ground surface conditions; nature and quantity of surface materials to be encountered; subsurface conditions, if such subsurface conditions would reasonably be expected to be a part of Subcontractor’s Work; equipment and facilities needed preliminary to and during performance of the Subcontract; and all other matters which can in any way affect performance of the Subcontract, or the cost associated with such performance. Failure of Subcontractor to acquaint itself with any applicable condition will not relieve it from the responsibility for the difficulties or the costs of successfully performing the Subcontract. (Emphasis added.)

It further provides under Part I, Special Provisions:

(c) Additionally, [Diamond] shall fully comply with all other applicable provisions, terms and conditions of the Specifications, including without limitation the Construction Contract, the General Provisions (Construction Contract), the General Requirements and the Technical Provisions. (Emphasis added.)

The dredging work required by the Specifications is described in Part VII of the Technical Provisions of the Specifications and in amended paragraphs 4-4, 4-22, 4-22.1 and 4-22.2 of Part IV of the Technical Provisions.

Under Part VII of the Technical Provisions of the Specifications, the method of payment for dredging is set forth in detail:

7-9. ESTIMATED QUANTITIES. The total estimated quantity or quantities of material necessary to be removed from within the specified limits to complete the work are as follows:

*1303 [[Image here]]

7-9.1. The quantities shown above are computed from the latest survey as reflected on the contract drawings. They have not been increased to allow for shoaling because of the unpredictable shoaling pattern.
7-9.2. Within the limit of available funds, the Contractor will be required to excavate the entire quantity of material necessary to complete the work specified herein, be it more or less than the amounts above estimated, all work to be done in accordance with the contract at the contract price or prices, except as may be affected by Variations in Estimated Quantities, paragraph 1-12.
7-10.1. OVERDEPTH. To cover inaccuracies of the dredging process, material actually removed from within the specific areas to be dredged to a depth of not more than two feet below the required depth will be estimated and paid for at the contract price.
7-11. SIDE SLOPES. Material actually removed, within limits, approved by the Contracting Officer, to provide for final side slopes no flatter than one vertical on four horizontal, but not in excess of the amount originally lying above this limiting side slope will be estimated and paid for, whether dredged in original position or by dredging space below the pay slope plane at the bottom of the slope for upslope material capable of falling into the cut. In computing the limiting amount of side slope dredging, an overdepth of two feet measured vertically will be used.
7-15. MEASUREMENT AND PAYMENT.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
580 F. Supp. 1299, 32 Cont. Cas. Fed. 72,702, 1984 U.S. Dist. LEXIS 19283, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wf-magann-corp-v-diamond-manufacturing-co-scd-1984.