United States v. Tway, Inc.

938 F.2d 583, 37 Cont. Cas. Fed. 76,158, 20 Fed. R. Serv. 3d 1049, 1991 U.S. App. LEXIS 18114
CourtCourt of Appeals for the Federal Circuit
DecidedAugust 12, 1991
Docket90-3484
StatusPublished

This text of 938 F.2d 583 (United States v. Tway, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Tway, Inc., 938 F.2d 583, 37 Cont. Cas. Fed. 76,158, 20 Fed. R. Serv. 3d 1049, 1991 U.S. App. LEXIS 18114 (Fed. Cir. 1991).

Opinion

938 F.2d 583

20 Fed.R.Serv.3d 1049, 37 Cont.Cas.Fed. (CCH) 76,158

UNITED STATES of America for the Use and Benefit of GULF
STATES ENTERPRISES, INC., Plaintiff-Appellant,
v.
R.R. TWAY, INC., Phil Hoffman, Inc., and Federal Insurance
Company, Defendants-Appellees.

No. 90-3484

Summary Calendar.

United States Court of Appeals,
Fifth Circuit.

Aug. 12, 1991.

Charles H. Braud, Jr., Covert & Braud, Baton Rouge, La., for plaintiff-appellant.

Carolyn Pratt Perry, Baton Rouge, La., for defendants-appellees.

Appeal from the United States District Court for the Middle District of Louisiana.

Before JOHNSON, SMITH, and WIENER, Circuit Judges.

PER CURIAM:

Use Plaintiff-Appellant, Gulf States Enterprises Company, Inc., appeals from the magistrate judge's judgment in favor of Defendants-Appellees, R.R. Tway, Inc., Phil Hoffman, Inc., and Federal Insurance Company, on a claim under the Miller Act, 40 U.S.C. Sec. 270a, et seq., for payment of equipment rentals. Finding no error in the magistrate judge's alternative determinations that (1) the Miller Act claims were time barred, (2) Gulf States' connection with the project's prime contractor was too remote to permit recovery under the Miller Act, and (3) Gulf States' claims under Louisiana state law have no merit, we affirm.

I.

FACTS

R.R. Tway, Inc. (Tway), as prime contractor, entered into a contract (the Prime Contract) with the United States to perform work in connection with a Corps of Engineers project, the East Atchafalaya Protection Basin Levee Project (the Project). In accordance with Sec. 1 of the Miller Act, Tway executed a payment bond on which Tway was the principal and Federal Insurance Company was the surety. Phil Hoffman (Mr. Hoffman) approached Tway representatives about the possibility of providing some equipment for use on the Project. On August 2, 1984, Tway and Mr. Hoffman entered into a contract (the Dozer Contract), using a form labeled "Sub-Contract", in which Mr. Hoffman agreed individually to furnish a bulldozer to Tway on a fully operated basis, as needed, for a rate of $42.00 per operating hour. On August 30, 1984, Tway entered into a second contract (the Dragline Contract), again using a form labeled "Sub-Contract", with J.P. Hoffman, Inc.1 (Hoffman, Inc.), in which Hoffman, Inc. agreed to perform "fill" or "dirt" work specified in Tway's prime contract.2 At Tway's request, Mr. Hoffman personally guaranteed his corporation's performance under the Dragline Contract.

Shortly after entering into the Dragline Contract, Mr. Hoffman approached David K. Williams, Jr., owner of Gulf States Enterprises Company, Inc.,3 (Gulf States) about renting a dozer and a dragline from Gulf States. Although there was apparently some discussion about the possibility of Mr. Hoffman buying the equipment, it is clear from the evidence that he rented both pieces of equipment from Gulf States. The rental agreements were oral. Williams was told by Mr. Hoffman that he had a contract with Tway, but Williams was not told by Mr. Hoffman that his corporation, Hoffman, Inc., also had a contract with Tway.

Gulf States rented a Kamatsu dozer and a Northwest 6 dragline to Mr. Hoffman. Gulf States invoiced Mr. Hoffman4 for rental on the dozer from September of 1984 through April 17, 1985 for a total of $50,000.00. Gulf States invoiced Mr. Hoffman5 for the rental of the dragline used in the performance of the Dragline Contract. The invoices covered the period of September 1984 through March 27, 1985, and totalled $36,000.00.

The dozer was not used to perform work under the Dozer Contract after December of 1984, but it was used to perform work under the Dragline Contract until March of 1985.

On June 5, 1985, Tway's attorneys demanded in writing that Gulf States remove the dozer and the dragline from the Project site. Tway refused to accept any further responsibility for the equipment, assumed Mr. Hoffman had abandoned it, and stated that the equipment had not been worked for many weeks. Gulf States removed the Kamatsu dozer on June 28, 1985, but the dragline apparently was not removed. Sometime in late June or early July Gulf States rented that dragline to Circle, Inc., another of Tway's subcontractors, for use in connection with repairing one of Circle's own draglines. Gulf States' dragline was not used in connection with completion of any work under the Dragline Contract after March of 1985.

Over a year later, on July 8, 1986, Gulf States filed suit pursuant to the Miller Act. In that suit Gulf States asserted an alternative basis for recovery under Louisiana law, insisting that it is entitled to recover on the theory that Tway had agreed to pay the debts of Mr. Hoffman and Hoffman, Inc. Gulf States also averred that under Louisiana law it was entitled to recover on the basis of unjust enrichment or quantum meruit.

After a bench trial, the magistrate judge ruled that Gulf States had failed to establish that it had supplied equipment to a "first tier subcontractor," as required by the Miller Act, and that Gulf States' Miller Act claims were barred by the Act's one year limitation period within which to bring suit. The magistrate judge also rejected Gulf States' state law theories of recovery. Gulf States subsequently filed a motion for new trial, which the magistrate judge denied with reasons. Gulf States timely appealed the magistrate judge's decisions.6

II.

STANDARD OF REVIEW

This action was tried by a magistrate judge by consent of the parties, and a judgment was entered by the magistrate judge under 28 U.S.C. Sec. 636(c). We review such judgments under the same standards that we review judgments entered by a district judge. Lockette v. Greyhound Lines, Inc., 817 F.2d 1182 (5th Cir.1987). Conclusions of law are reviewed de novo and findings of fact are upheld unless they are clearly erroneous. Fed.R.Civ.P. 52.

III.

DISCUSSION

A. The Miller Act

The Miller Act requires that any contractor who is awarded a contract for "construction, alteration, or repair of any public building or public work of the United States," must provide a payment bond "for the protection of all persons supplying labor and material in the prosecution of the work provided for in said contract for the use of each such person." Section 270b(a) gives the party supplying labor and material to such a contractor the right to sue on the payment bond for nonpayment of the labor or material supplied. This right extends to those parties "having direct contractual relationship with a subcontractor but no contractual relationship express or implied with the contractor...." (emphasis added).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. City of Bessemer City
470 U.S. 564 (Supreme Court, 1985)
United States v. Aetna Casualty Insurance Company
908 F.2d 375 (Eighth Circuit, 1990)
United States Ex Rel. Altman v. Young Lumber Company
376 F. Supp. 1290 (D. South Carolina, 1974)
United States v. Allegheny-Ludlum Industries, Inc.
517 F.2d 826 (Fifth Circuit, 1975)
Aldens, Inc. v. Kane
425 U.S. 943 (Supreme Court, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
938 F.2d 583, 37 Cont. Cas. Fed. 76,158, 20 Fed. R. Serv. 3d 1049, 1991 U.S. App. LEXIS 18114, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-tway-inc-cafc-1991.