United States Ex Rel. Carlisle Construction Co. v. Coastal Structures, Inc.

689 F. Supp. 1092, 41 Cont. Cas. Fed. 77,067, 1988 U.S. Dist. LEXIS 5969, 1988 WL 64289
CourtDistrict Court, M.D. Florida
DecidedMarch 21, 1988
Docket86-783-CIV-ORL-19
StatusPublished
Cited by8 cases

This text of 689 F. Supp. 1092 (United States Ex Rel. Carlisle Construction Co. v. Coastal Structures, Inc.) is published on Counsel Stack Legal Research, covering District Court, M.D. Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Ex Rel. Carlisle Construction Co. v. Coastal Structures, Inc., 689 F. Supp. 1092, 41 Cont. Cas. Fed. 77,067, 1988 U.S. Dist. LEXIS 5969, 1988 WL 64289 (M.D. Fla. 1988).

Opinion

ORDER

FAWSETT, District Judge.

This case was tried by the Court sitting as jury on January 13,1988. After hearing the testimony and observing the demeanor of the witnesses, reviewing the evidence and the law, and being otherwise duly advised, the Court enters its Findings of Fact and Conclusions of Law pursuant to Federal Rule of Civil Procedure 52.

FINDINGS OF FACT

Plaintiff Carlisle Construction Company, Inc. (“Carlisle”) filed a Three Count Complaint which sought damages against Defendant Dependable Insurance Company, Inc. (“Dependable”) in Count One pursuant to the provisions of the Miller Act, 40 U.S. C. Section 270a et seq., and in Count Three based on quantum meruit. In Count Two of the Complaint, Carlisle sought damages against Defendant Coastal Structures, Inc. (“Coastal”), for breach of contract. Coastal is also a defendant under the Miller Act claim. 1 At the trial of this action, Dependable made an ore tenus motion to dismiss without prejudice its cross-claim against Coastal and its third party claim against Third Party Defendants Gary J. McGeddy and Roxanne McGeddy, which motion was granted.

This case involves a crane owned by Car-lisle which was used at a Naval construction project located in Andros Island, Bahamas. Until August 12, 1986, Coastal was general contractor for the Andros construction project, and Dependable acted as surety for Coastal. (Plaintiff’s Exhibit 6).

On May 19, 1986, Coastal executed an Equipment Rental Agreement with Carlisle whereby Coastal rented a crane from Car-lisle. Pursuant to this Agreement, Carlisle caused the crane to be transported to the Port of Palm Beach where it originally was to be loaded onto a Coastal barge and transported to the Florida Keys for a construction project. However, upon arrival in the Port of Palm Beach, the crane was loaded on a barge and was instead taken by Coastal to the Andros Island project. The crane arrived at Andros Island on June 12, 1986 and was unloaded on June 18, 1986 (Deposition of Engleberth, page 21). The crane was utilized by Coastal in the project construction prior to Coastal’s termination *1094 as general contractor of the project on August 12, 1986.

Subsequent to the termination of Coastal as general contractor, Dependable entered into a takeover agreement with the Navy and commenced to complete the construction required pursuant to the provisions of the contract previously entered between Coastal and the Navy. To accomplish its obligations under this contract with the Navy, Dependable entered into a contract completion agreement with a subcontractor, Piling and Structures, Inc., for completion of a portion of the contract which required use of a crane. Thereafter, Piling and Structures, Inc. entered into an Equipment Rental Agreement with Carlisle under which Piling and Structures, Inc. was authorized to use the Carlisle crane to complete the work designated under the contract between Piling and Structures, Inc. and Dependable.

Piling and Structures, Inc. used the Car-lisle crane on the Andros project beginning November 21, 1986 for approximately fifteen days and had the crane in its possession until January 28, 1987 (Deposition of Thaggard, page 16). Upon completion of its work utilizing the crane, Piling and Structures, Inc. caused the crane to be transported from Andros Island to Jacksonville, Florida where it was returned to Car-lisle.

The Equipment Rental Agreement between Carlisle and Coastal provided for rental of the crane at the rate of $6,500 a month. 2 (Plaintiffs Exhibit 2). The contract also provides for an inland transportation charge of $7,000 consisting of $3,500 to get the crane into the position of assembly from Orlando to the Port of Palm Beach and $3,500 to get the crane out of the position of assembly from the Port of Palm Beach to Orlando. 3 This charge was related to the cost of eight or nine lowboy loads to transport the units of the crane to the delivery site and the cost of the employees required for this transport.

Under the contract heading “Special Provisions”, the parties agreed that Coastal would pay to Carlisle $3,000 as the cost of erection and $3,000 as the cost for dismantling. The erection of the crane involved a rigging crew of five to six people and one 80 ton crane or two 40 ton cranes to lift the crane in question off the truck at the delivery site and to assemble it. To assemble the crane, a task which Carlisle agreed to perform, required approximately one and a half to two days of time. Dismantling of the crane involved the same procedure in reverse.

The contract also provides under “Terms of Payment” that a service charge of one and a half percent of the unpaid balance computed monthly or the maximum rate allowed by law, whichever is less, would be added and that any expense incurred in collecting the delinquent rental payment, included but not limited to court costs and attorney fees, would be paid by Coastal. 4

Finally, the contract provided that all applicable taxes would be paid by Coastal.

When the disassembled crane was delivered to the Port of Palm Beach by Carlisle, additional time was incurred in unloading the crane due to initial misdirection to an improper dock. While the contract provided under “Transportation Charge” that two hours of standby time for unloading would be included, additional time was specified to be charged at the rate of $75.00 per hour. The charge for the additional time incurred by Carlisle was $1,046.25.

*1095 Additionally, Carlisle was required to pay on behalf of Coastal a charge in the amount of $3,090.23 for use of the dock at the Port of Palm Beach for loading the barge, 5 so that the crane could be transported to its destination.

Gary Daniel Hoffman, Vice President of Sales for Carlisle, testified that the rental period for this crane began on June 2, 1986 and that on August 11, 1986 Carlisle received a letter from Coastal dated August 7, 1986 (Plaintiffs Exhibit 3) in which Coastal assured that the cost of mobilization and demobilization of the crane and other obligations under the contract would be honored. Hoffman testified that he heard second hand in late August or early September of 1986 that Coastal had been terminated from the construction job in Andros Island. Coastal did not contact Carlisle about return of the crane either before or after its termination as general contractor on this project.

The Carlisle crane was left on Andros Island after Coastal vacated the project. This crane, a Manitowoc 4000W Crawler, had a 150 ton lift capacity, had a boom in excess of 300 feet, and weighed 400,000 pounds. It was used on large construction projects and was worth approximately $350,000 at the time of its rental to Coastal.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City Rentals, LLC v. BBC Co.
947 N.E.2d 1103 (Massachusetts Appeals Court, 2011)
A.G. Gaston Const. Co., Inc. v. Hicks
674 So. 2d 545 (Court of Civil Appeals of Alabama, 1995)
United States v. Tway, Inc.
938 F.2d 583 (Federal Circuit, 1991)
R.J. Russo Trucking & Excavating, Inc. v. Pennsylvania Resource Systems, Inc.
169 A.D.2d 239 (Appellate Division of the Supreme Court of New York, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
689 F. Supp. 1092, 41 Cont. Cas. Fed. 77,067, 1988 U.S. Dist. LEXIS 5969, 1988 WL 64289, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-carlisle-construction-co-v-coastal-structures-inc-flmd-1988.