United States ex rel. Roig v. Castro

71 F. Supp. 36, 1947 U.S. Dist. LEXIS 2662
CourtDistrict Court, D. Puerto Rico
DecidedApril 11, 1947
DocketCiv. No. 4321
StatusPublished
Cited by6 cases

This text of 71 F. Supp. 36 (United States ex rel. Roig v. Castro) is published on Counsel Stack Legal Research, covering District Court, D. Puerto Rico primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States ex rel. Roig v. Castro, 71 F. Supp. 36, 1947 U.S. Dist. LEXIS 2662 (prd 1947).

Opinion

COOPER, District Judge.

By this proceeding Ramon M. Roig, use-plaintiff, seeks to recover from the defendants Celestino Castro as Principal and Glens Falls Indemnity Company as Surety, the amounts set forth in plaintiff’s complaint. The defendant Castro admits in his answer that Roig was to receive a salary which is stated in the complaint but alleges that salary was paid to Roig as and when it [37]*37became due. He denies liability for other claims made by Roig. He alleges substantially that the work in question was performed jointly by Castro and Roig under an agreement to the effect that Roig was to contribute his work and his engineering equipment as a partner or joint venturer with a 25% interest in the contract, while Castro contributed his work and engineering equipment and further financed the whole undertaking as a partner with a 75% interest.

Defendant Castro also states a counterclaim alleging substantially that the demand made by Roig for hired equipment and repairs thereto is in excess of the rates permitted by the Office of Price Administration and on that account he claims from Roig treble damages in the total sum of $10,349.64.

The defendant Glens Falls Indemnity Company in its answer admits paragraphs 1, 2 and 3 of the complaint with reference to the capacity of the parties, the public works contract between Castro and the United States Government, and the payment bond furnished in connection therewith by Glens Falls Indemnity Company. All allegations of the complaint other than the three paragraphs are denied. The Glens Falls Indemnity Company also alleges as a special defense that the rental of construction equipment, cost of repair parts and repairs to such equipment are not included in the phrase “labor and material” for which the surety answers under the provisions of law and the terms of the bond given by it.

After a careful consideration of the pleadings and the evidence, and briefs submitted by counsel for all parties, I make the following findings of fact and conclusions of law.

Findings of Fact.

I. Defendant Celestino Castro on or about November 29, 1943, entered into a contract with the United States of America, Engineer Office, known as Contract No. W-1099-Eng.-1524, for the construction of a “Pipe Line ‘A’ of Waterwork Facilities for San Juan, Puerto Rico” in the sum of $188,025.

II. As required by Section 270a of Title 40 U.S.C.A. in collection with said public works contract, defendant Celestino Castro as principal, and codefendant Glens Falls Indemnity Company as surety, executed a payment bond on or about December 13, 1943 acknowledging themselves to be held jointly and severally bound in the sum of $94,012.50, the condition thereof being as follows: “Now Therefore, if the principal shall promptly make payment to all persons supplying labor and materials in the prosecution of the work provided for in said contract, and any and all duly authorized modifications of said contract that may hereafter be made, notice of which modifications to the surety being hereby waived, then this obligation to be void; otherwise to remain in full force and virtue.”

III. Defendant Celestino Castro employed plaintiff Ramon M. Roig as engineer to supervise work to be done in the field under said contract.

IV. Castro agreed that Roig should have a salary of $200 per week to be paid upon termination of the work, irrespective of whether or not a profit on the contract was realized.

V. Castro agreed that Roig would receive 25% of any net profits, salary to be deducted therefrom; that is to say, if the 25% of profits realized was more than the total amount of the salary, Roig would receive the difference but if the 25% was less than the total amount of the salary, then Roig would receive only the salary. Roig was not responsible for any loss which might result.

VI. Work under said public works corn-tract started December 17, 1943 and terminated August 31, 1944.

VII. The total amount of Roig’s salary, Victory Tax deducted is $7,201 which amount has not been paid to him by Castro.

VIII. Castro hired from Roig the following equipment which was used in the work during the time stated in respect to each item:

Angledozer Allis Chalmers HD7, Model 1941, for 6Yz months
Air compressor Ingersoll Rand 1941, 160 cu. ft., for 4 months, 21 days.
[38]*38Concrete Mixer Jaegger 75, 1941, for 8 months
3 Jack Hammers for two (2) months Tools, tire and steel wheel barrows, etc. from December 17, 1943 to August 31, 1944.
IX. Castro agreed to pay for the repairs and replacements of Roig’s equipment.
X. I find that the fair rental for the Angledozer is $665 per month which for 5.3 months, totals the sum of $3524, which amount is now due Roig.
XI. Castro owes Roig as follows:
4 months, 21 days, use of air compressor Ingersol — Rand 1941,
160 cu. ft. at $180.00.......... $ 846.00
8 months use concrete mixer Jaegger 75, 1941, at $77.00 ......... 616.00
2 months use of jack hammers at $60.00 ....................... 120.00
5 months use 300 1-ft. 3/4" air
hose at $20.00................. 100.00
Rental of tools, tire and steel wheel barrows, etc. from December 17, 1943 to August 31,
1944 ........................ 325.00
$2007.00
Also money paid by Roig to P.R.
Iron Works, Sobrinos de Portilla, Ulpiano Casals and others, for repairs to equipment and parts therefor ............... 819.10
$2826.10
Conclusions of Law.

1. The Court has jurisdiction of this case under Section 270b, Title 40 U.S.C.A.

2. The relation between defendant Celestino Castro and plaintiff Ramon M. Roig was not that of partners, but that of employer and employee.

3. Castro having admitted that Roig was to receive a salary and having pleaded payment thereof, the burden is on Castro to prove such payment by a preponderance of the evidence. This he has failed to do. ■

4. Defendant Glens Falls Indemnity Company answers under its bond for payment of Roig’s salary.

5. The defendant Glens Falls Indemnity Company is not required to pay for repairs to Roig’s equipment and repair parts therefor amount to $819.11. This was for repairs made after the completion of the project. However, Glens Falls Indemnity Company must answer under its bond for the rental of Roig’s equipment and for necessary repairs in the prosecution of the work.

6. Plaintiff Roig is entitled to interest at 6% per annum from the date of the filing of the complaint on the total amount found due him.

7. Defendant Castro has failed to sustain his counterclaim.

Opinion.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cecil I. Walker MacHinery Co. v. Stauben, Inc.
230 S.E.2d 818 (West Virginia Supreme Court, 1976)
United States Ex Rel. Altman v. Young Lumber Company
376 F. Supp. 1290 (D. South Carolina, 1974)
Goss v. Structural Concrete Products & Maryland Casualty Co.
92 P.R. 378 (Supreme Court of Puerto Rico, 1965)
Goss v. Structural Concrete Products
92 P.R. Dec. 391 (Supreme Court of Puerto Rico, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
71 F. Supp. 36, 1947 U.S. Dist. LEXIS 2662, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-roig-v-castro-prd-1947.