United States Ex Rel. Westinghouse Electric Supply Co. v. National Surety Corp.

179 F. Supp. 598, 1959 U.S. Dist. LEXIS 2425
CourtDistrict Court, E.D. Pennsylvania
DecidedDecember 11, 1959
DocketCiv. A. 23965, 23966
StatusPublished
Cited by4 cases

This text of 179 F. Supp. 598 (United States Ex Rel. Westinghouse Electric Supply Co. v. National Surety Corp.) is published on Counsel Stack Legal Research, covering District Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Ex Rel. Westinghouse Electric Supply Co. v. National Surety Corp., 179 F. Supp. 598, 1959 U.S. Dist. LEXIS 2425 (E.D. Pa. 1959).

Opinion

VAN DUSEN, District Judge.

Findings of Fact

The trial judge makes the following Findings of Fact:

1. The United States Army Corps of Engineers entered into a written agreement, No. DA-36-109-Eng-6193, with Joseph W. Montgomery, trading as Montgomery Construction Co., dated March 26, 1956, for construction by Montgomery of Nike Site 78 at Edge-mont, Pennsylvania, for the contract price of $543,915.

2. The United States Army Corps of Engineers entered into a written agreement, No. DA — 36—109—Eng—6194, with Joseph W. Montgomery, trading as Montgomery Construction Co., dated March 26, 1956, for construction by Montgomery of Nike Site 97 at Eureka, Pennsylvania, for the contract price of $544,709.

3. The defendant, The National Surety Corporation, as surety, and Joseph W. Montgomery, trading as Montgomery Construction Co., as principal, pursuant to the provisions of the Miller Act executed and delivered to the United States of America their two separate joint and *600 several bonds, both dated March 26, 1956, conditioned for the prompt payment to all persons supplying labor and material in the prosecution of the construction of the said two Nike Sites, 78 and 97. The amount of the bond with reference to Nike Site 78 was $271,957.50 and the amount of the bond with reference to Nike Site 97 was $272,354.50.

4. Nike sites consist primarily of storage facilities, launching equipment and guidance equipment for Nike missiles, which are an integral part of our country’s national defense.

5. Nike Site 78, located at Edgemont, Pa., and Nike Site 97, located at Eureka, Pa., are both within the territorial jurisdiction of this court.

6. These suits were commenced on January 17, 1958, by the use plaintiff.

7. The date of final settlement of both contracts involved was sometime after January 17, 1957.

8. At the time these suits were commenced, more than 90 days had elapsed since the last material was furnished by the use plaintiff for which a claim is made.

9. Joseph Montgomery, trading as Montgomery Construction Co., entered into a written contract with Maguire Engineering Co., Inc., on May 29, 1956 (plaintiff’s Exhibit 1), which provided that Maguire Engineering Co., Inc., was to supervise the installation of the electrical work comprehended for Nike Sites 78 and 97 and to prepare material lists and obtain prices from electrical suppliers. The lists were to be presented to Montgomery Construction Co. for approval before orders were placed, excepting when, in the opinion of the Maguire Engineering Co., Inc., such delay might cause undue hardship or expense to the Montgomery Construction Co., in v/hich case orders were to be placed by the Ma-guire Engineering Co., Inc., with verbal approval.

10. Subsequent to the execution of the contract of May 29, 1956, between Montgomery Construction Co. and Ma-guire Engineering Co., Inc., it was agreed by the parties to the contract that the requirement that all orders be approved by the Montgomery Construction Co. be ignored and that Maguire Engineering Co., Inc. should order any necessary materials directly from the suppliers.

11. An account was opened with the use plaintiff by the Montgomery Construction Co.

12. Joseph W. Montgomery, trading as Montgomery Construction Co., by Joseph W. Montgomery and Edmund J. Maguire acting for Joseph W. Montgomery, requested the use plaintiff to supply and deliver substantial electrical materials, itemized in Exhibit A attached to the use plaintiff’s Complaint in Civil Action No. 23965 and Exhibit A attached to the plaintiff’s Complaint in Civil Action No. 23966, which materials are also itemized in plaintiff’s Exhibits 6 to 144, inclusive.

13. All orders placed with the use plaintiff for the materials itemized in plaintiff’s Exhibit 6 to 144, inclusive, were placed in accordance with the agreement between Montgomery Construction Co. and Maguire Engineering Co., Inc. in effect at the time they were placed.

14. There was a direct contractual relationship between Montgomery Construction Co. and the use plaintiff with respect to the purchase and sale of the materials itemized in plaintiff’s Exhibits 6 to 144, inclusive.

15. The use plaintiff furnished and delivered to Joseph W. Montgomery, trading as Montgomery Construction Co., all of the material itemized in plaintiff’s Exhibits 6 to 144, inclusive.

16. All of the materials itemized in plaintiff’s Exhibits 6 to 144, inclusive, were required for the electrical construction of Nike Sites 78 and 97.

17. All of the materials itemized in plaintiff’s Exhibits 6 to 144, inclusive, were actually incorporated in the electrical installation and construction of Nike Sites 78 and 97.

18. The prices charged by the use plaintiff for all of the materials itemiz *601 ed in plaintiff’s Exhibits 6 to 144, inclusive, were reasonable.

19. No payment has been made to the use plaintiff for or on account of the electrical materials itemized in plaintiff’s Exhibits 6 to 144, inclusive.

20. The aggregate amount of the invoices for the materials itemized in plaintiff’s Exhibits 6 to 144, inclusive, is the sum of $20,643.73, computed as follows: $11,895.14 for Nike Site 78 (Civil Action No. 23965) and $8,748.59 for Nike Site 97 (Civil Action No. 23966). The defendant is entitled to credits as set forth in Exhibit A attached to each of the two Complaints, as follows: Civil Action No. 23965 for Nike Site 78 $37.77, and Civil Action No. 23966 for Nike Site 97, $322.81. In addition, defendant is entitled to a further credit of $138 with respect to plaintiff’s exhibit 105, representing a return of material as against the amount claimed in Civil Action No. 23965, and the further and additional credit of $138 with respect to plaintiff’s Exhibit 105, representing a return of material as against the amount claimed in Civil Action No. 23966.

21. The amount due to the use plaintiff, therefore, is the sum of $20,367.73 for the electrical materials and, in addition thereto, interest upon each invoice (plaintiff’s Exhibits 6 to 144, inclusive) from the due date of the said invoices.

22. Mr. Joseph W. Montgomery, the general contractor and the principal on the surety bond, was present in the courtroom and available as a witness at virtually all times during the trial.

23. All requests for Findings of Fact which are inconsistent with the foregoing are denied.

Discussion

Westinghouse Electric Supply Company brought two actions against the National Surety Company under 40 U. S.C.A. §§ 270a-270e, commonly known as the Miller Act, on two bonds executed by the defendant as surety and Joseph W. Montgomery, trading as Montgomery Construction Co., as principal. These bonds were conditioned for the prompt payment to all persons supplying labor and material in the construction of Nike Sites 78 and 97 which Montgomery had contracted to construct for the United States Army Corps of Engineers. The two actions were consolidated for purposes of trial.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Beckwith MacHinery Co. v. Asset Recovery Group, Inc.
890 A.2d 403 (Superior Court of Pennsylvania, 2005)
Regal Industrial Corp. v. Crum & Forster, Inc.
890 A.2d 395 (Superior Court of Pennsylvania, 2005)
City of Weippe v. Yarno
528 P.2d 201 (Idaho Supreme Court, 1974)
Gypsum Contractors, Inc. v. American Surety Company
181 A.2d 174 (Supreme Court of New Jersey, 1962)

Cite This Page — Counsel Stack

Bluebook (online)
179 F. Supp. 598, 1959 U.S. Dist. LEXIS 2425, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-westinghouse-electric-supply-co-v-national-surety-paed-1959.