City of Weippe v. Yarno

528 P.2d 201, 96 Idaho 319, 1974 Ida. LEXIS 440
CourtIdaho Supreme Court
DecidedNovember 15, 1974
Docket11391
StatusPublished
Cited by39 cases

This text of 528 P.2d 201 (City of Weippe v. Yarno) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Weippe v. Yarno, 528 P.2d 201, 96 Idaho 319, 1974 Ida. LEXIS 440 (Idaho 1974).

Opinion

DONALDSON, Justice.

This is an action brought by use-plaintiff-appellant Les Schwab Tire Centers of Idaho, Inc. against defendant-respondent United States Fidelity and Guaranty Company, on a public works payment bond executed in behalf of defendant-respondent J. R. Yarno, d/b/a Yarno and Associates, in connection with a contract to have been performed for plaintiff-appellant City of Weippe, Idaho.

In June, 1967, J. R. Yarno, d/b/a Yarno and Associates, hereafter “Yarno,” entered into a public works contract with the City of Weippe. Subsequent thereto, respondent United States Fidelity and Guaranty Company, hereafter “U.S.F. & G,” issued and furnished a labor and material bond in the penal sum of $190,174.21.

In September and October, 1968, appellant Les Schwab Tire Centers of Idaho, Inc., hereafter “Les Schwab,” furnished certain tires, anti-freeze and labor valued in the amount of $1,494.57 at the insistence and request of respondent Yarno.

During the first or second week of November, 1968, Yarno moved off the job site and did not, personally, by agent or otherwise, deliver any materials or personal property to the operation at Weippe, or render any personal services in connection with the public works contract. The City of Weippe, by letter dated July 1, 1969, declared that Yarno was in default in the performance of said public works contract and therefore terminated the contractual relationship.

Appellant Les Schwab instituted action 1 for payment February 11, 1970 for the above listed materials and labor. Yarno allowed judgment to be entered against him April 8, 1970 in the amount of $1,522.-67 (materials plus costs). Respondent, U. S.F. & G. answered, counterclaimed and filed motion for summary judgment. Subsequent to hearing, briefs were submitted by both parties and the trial court granted respondent’s motion. Judgment was entered and appeal was taken therefrom to this Court as case number 10828, Weippe v. Yarno, 94 Idaho 257, 486 P.2d 268 (1971), wherein the trial court’s granting of summary judgment was reversed. Trial on the merits was held without jury October 24, 1972 and the district court dismissed appellant’s complaint with prejudice and awarded respondent attorney’s fees and costs in the amount of $810.00. Error is assigned to that finding.

Two principle issues of controversy are presented in this case: Whether goods and labor furnished by use-plaintiff are “materials” within the definition of that term under the Idaho Public Contracts Bond Act or the payment bond in question? Whether the applicable period of limitations had run thereby barring the action?

The trial court found that the personal services furnished and the personal property sold to Yarno by use plaintiff were not “labor and materials” within the provisions of the Idaho Public Contracts Bond Act. The trial court rationale was that the goods and services were not, in the reasonable contemplation of all parties, to be consumed ; and were not consumed in the completion of the project. We disagree.

*321 The labor and material bond contains the following definition:

“A. A claimant is defined as one having a direct contract with the Principal [Yarno] or with a subcontractor of the Principal for labor, material, or both, used or reasonably required for use in the performance of the Contract, labor and material being construed to include that part of water, gas, power, light, heat, oil, gasoline, telephone service or rental of equipment directly applicable to the Contract.”

I.C. § 54-1926 states in applicable part that before certain public works contracts are awarded, bonds shall become binding upon the award:

“(1) A performance bond in any amount to be fixed by the contracting body, but in no event less than 50 per cent of the contract amount conditioned upon the faithful performance of the contract in accordance with the plans, specifications and conditions thereof. Said bond shall be solely for the protection of the public body awarding the contract.
(2) A payment bond in an amount to be fixed by the contracting body but in no event less than 50 per cent of the contract amount, solely for the protection of persons supplying labor or materials to the contractor or his subcontractors in the prosecution of the work provided for in such contract." (emphasis added)

I.C. § 54-1927 states in applicable part that every claimant who has furnished labor or material in the prosecution of a public works contract, and who has not been paid, can sue on the payment bond. The statutory period for bringing such action is one year from the date the last labor or materials were supplied, or in no event greater than one year from the date final payment under the subcontract was due.

The record clearly shows that the defendant was supplied with two new tires, a retread, a section repair for a third tire and four gallons of anti-freeze. The record further shows that such supply was essential to keep a Trojan front end loader in operation. It is undisputed that the tires furnished, under the operating conditions at bar, had a life expectancy of approximately three months. Testimony shows that the loader was used from eight to ten hours a day, five days a week on the Weippe project, for seven to eight weeks after their installation. The loader had been used over sharp four inch rocks and when the equipment left the project, notches and big chunks of rubber had been cut out and spun off the tread.

The supplies in question, coupled with their testified use, clearly qualified as materials under the act. Analysis of I.C. §§ 54-1926 and 54-1927, and 40 U.S.C. § 270a (the Federal Statute — Miller Act) indicates both are substantially identical.

In People v. Storm, 49 Idaho 246, 254, 287 P. 689 (1930), this Court stated:

“The Federal statute, from which our own is taken, has been held to be highly remedial, and should, therefore, be liberally construed to cover all persons who supply labor or material in a public work, to give all creditors a remedy on the bond of the contractor to be enforced within the time stated, etc., and that the strict letter of the act must ‘yield to its evident spirit and purpose, when this is necessary to give effect to the intent of Congress.’ ” 2

A statute which is adopted from another jurisdiction, including federal statutes adopted by a state, will be presumed to be adopted with the prior construction placed upon it by the courts of the other *322 jurisdictions. 3 As such, we find the following cases persuasive.

Montgomery v. Unity Electric Co., 155 F.Supp. 179 (D.C.P.R.1957) was an action under the Miller Act for materials sold to a subcontractor. The court held:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Geringer Capital v. Taunton Properties, LLC
529 P.3d 760 (Idaho Supreme Court, 2023)
Evco Sound & Electronics, Inc. v. Seaboard Surety Co.
223 P.3d 740 (Idaho Supreme Court, 2009)
Oldcastle Precast, Inc. v. Parktowne Construction, Inc.
128 P.3d 913 (Idaho Supreme Court, 2005)
Mason v. Tucker and Associates
871 P.2d 846 (Idaho Court of Appeals, 1994)
Seubert Excavators, Inc. v. Eucon Corp.
871 P.2d 826 (Idaho Supreme Court, 1994)
Sun Valley Ranches, Inc. v. Prairie Power Cooperative, Inc.
856 P.2d 1292 (Idaho Court of Appeals, 1993)
Idaho Schools for Equal Educational Opportunity v. Evans
850 P.2d 724 (Idaho Supreme Court, 1993)
Beco Corp. v. Roberts & Sons Construction Co.
760 P.2d 1120 (Idaho Supreme Court, 1988)
Walker v. Shoshone County
739 P.2d 290 (Idaho Supreme Court, 1987)
Hibbler v. Fisher
712 P.2d 708 (Idaho Court of Appeals, 1985)
Richard B. Smith Real Estate, Inc. v. Knudson
691 P.2d 1212 (Idaho Supreme Court, 1984)
Sheppard v. Sheppard
655 P.2d 895 (Idaho Supreme Court, 1982)
Pope v. Intermountain Gas Co.
646 P.2d 988 (Idaho Supreme Court, 1982)
G & H Land & Cattle Co. v. Heitzman & Nelson, Inc.
628 P.2d 1038 (Idaho Supreme Court, 1981)
Gavica v. Hanson
608 P.2d 861 (Idaho Supreme Court, 1980)
Revello v. Revello
606 P.2d 933 (Idaho Supreme Court, 1979)
Kifer v. School District No. 394
599 P.2d 302 (Idaho Supreme Court, 1979)
Kifer v. School Dist. No. 394
599 P.2d 302 (Idaho Supreme Court, 1979)
Consolidated Concrete Co. v. Empire West Construction Co.
596 P.2d 106 (Idaho Supreme Court, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
528 P.2d 201, 96 Idaho 319, 1974 Ida. LEXIS 440, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-weippe-v-yarno-idaho-1974.