This text of 274 P.2d 1002 (State Ex Rel. Modern Motor Co. v. H & K Construction Co.) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State Ex Rel. Modern Motor Co. v. H & K Construction Co., 274 P.2d 1002, 75 Idaho 492, 1954 Ida. LEXIS 253 (Idaho 1954).

Opinion

*494 GIVENS, Justice.

The H & K Construction Company, an Idaho corporation, contracted with the State of Idaho, through its Highway Commissioners, to construct 11.172 miles of the Lost River Highway between Arco and Big Lost River in Butte County, being Federal Aid Project No. F — 1381 (1), Contract No. 1489, and as principal, executed with the Fidelity and Casualty Company of New York as surety, a bond for $368,464.90 securing payments for labor, materials and supplies for such work, in compliance with Section 45-502, Idaho Code.

The H & K Construction Company subcontracted to the Mountain States Construction Company, Inc., an Idaho corporation, the furnishing of, and spreading, watering and rolling specified amounts of crushed gravel. The latter Company in turn, with the knowledge and consent of the H & K Company, entered into a working agreement with R. A. Craig to perform such work, which in part he did between July 10, 1951 and September 12, 1951, when his financial difficulties ended his participation.

The entire project was completed and accepted by the State of Idaho October 19, 1951.

Respondent claims to have furnished supplies, material and labor to Craig for such work, with a balance therefor unpaid by Craig of $5,139.96. It complied with the necessary concomitant statutory requirements and joining, as required, other claimants as defendants, April 17, 1952 sued the H & K Construction Company and its above named surety for such amount and $500 attorney’s fees, listing in its amended complaint February 24, 1953, some 277 odd separate charges covering gas, oil, tires, tubes, repairs to and servicing of equipment, labor, parts and hardware.

Appellants H & K Construction Company and Fidelity & Casualty Company admitted the contracts, etc., but denied the materials and services claimed to have been furnished to Craig by respondent Company, except for a few items, were used in or went into the work performed by Craig in his contract with the Mountain States Construction Company and denied that it has not been paid in full or that it is entitled to attorney’s fees.

By agreement the case was tried to the court without a jury. The court, with meticulous scrutiny of the evidence, rejected certain claimed items, but found otherwise in favor of respondent in the sum of $4,-704.53 and $500 attorney’s fees and so entered judgment.

In appellants’ appeal, the assignments of error all focus on the insufficiency of the evidence to prove that the items, as found by the court, were actually delivered to the *495 project or were used, necessary, incidental, and consumed in whole or in part in the prosecution of the work by Craig.

The burden of proof was, of course, on respondent, 40 C.J.S., Highways, § 210(8), p. 188, but the coverage of the bond is to be liberally construed and not limited to labor and materials that are lien-able under the mechanics’ lien law in its relation to private structures, but all labor or materials that directly or indirectly contribute to the construction of the work, are covered; thus including repairs, parts, (furniture) hardware, gas, oil, servicing and labor and other similar items, but not tools or new equipment, except as actually consumed on the job. People v. Storm, 49 Idaho 246, 287 P. 689; Franzen v. Southern Surety Co., 35 Wyo. 15, 246 P. 30, 46 A.L.R. 496, 503; State for Use of Wadsworth v. Southern Surety Co., 221 Ala. 113, 127 So. 805, 70 A.L.R. 296; H. Earl Clack Co. v. Staunton, 105 Mont. 735, 72 P.2d 1022.

“All materials and supplies purchased, sold, and delivered for use on the project of the nature we have described, and reasonably useful and consumable in the performance of the contract, and in contemplation when it is executed, and fairly within its terms, the court or jury trying the facts may infer are secured by the bond conditioned as provided by law, unless the evidence rebuts the inference. We do not think that the burden is upon the claimant in thé first instance to prove by direct evidence that the supplies were used for the job, but that this may be inferred from the circumstances. (Cases).” United Statas Fidelity & Guaranty Co. v. Benson Hardware Co., 222 Ala. 429, 132 So. 622, at page 627.
“Mr. Caddell, an employee of appellee, testified fully as to the shipment of asphalt by appellee consigned to Ted B. Smith in care of the Highway Department, Merkel, Texas. There is evidence that Ted B. Smith was not doing any construction work at any place near Merkel except on the farm to market road in question. There is no evidence that any of the asphalt delivered to Ted B. Smith at Merkel was diverted and not used on the construction of the project involved. The evidence is such that the trial court could, and presumably did find, that all of the asphalt was used by Smith in the prosecution of the Taylor County project.
“ ‘It is not necessary for a material-man to prove by direct evidence that his supplies sold for the construction of the highway, being reasonably suitable and appropriate to it, were in fact so used, if this may be inferred from the circumstances.’ 40 C.J.S., Highways, § 210, p. 188.
“We believe the fact of the use of the material upon the highway may be reasonably inferred from all the facts *496 and circumstances in this case. * *” Houston Fire & Casualty Ins. Co. v. Col-Tex Refining Co., Tex.Civ.App., 231 S.W.2d 468, at page 470.

Craig was not at the trial.

Alfred L. Hahn, President of respondent Company, testified charge slips covering all items were given to Craig or his employees, and as to many items, he personally knew the parts were furnished for and repairs made on, and gas and oil placed in, Craig’s equipment; that he had sold several of Craig’s trucks to him; that he, Hahn, was often out at the job some 55 miles west of Blackfoot, site of respondent’s place of business; that he there saw this equipment being used by Craig’s employees, whom he knew and recognized and who were in the Company’s garage in Blackfoot having the equipment serviced and repaired and there also secured gas and oil.

That the charge slips were made in the regular course of the Company’s way of doing business and delivered to Craig or his employees; that Craig was not engaged in any other highway construction work of this kind in that locality or vicinity on which the equipment was used; except for some two days’ excavating and hauling for a house in Blackfoot.

Earl H. Gough, Craig’s foreman on the job, substantiated in considerable detail Hahn’s testimony covering repairs, servicing and securing of parts and materials for Craig’s equipment from respondent Company, how and where used and the need therefor. Both Hahn and Gough described in detail the effect of the hard rough usage and terrain traversed to and from the rock crusher, on the equipment; the wear and tear, breakdowns of the rock crusher, and the consequent necessary repair work. Such arduous work conditions were, in part, recognized by appellants’ witnesses.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Great Plains Equipment, Inc. v. Northwest Pipeline Corp.
979 P.2d 627 (Idaho Supreme Court, 1999)
Municipality of Anchorage v. Tatco, Inc.
774 P.2d 207 (Alaska Supreme Court, 1989)
Buckalew v. City of Grangeville
600 P.2d 136 (Idaho Supreme Court, 1979)
Comish v. Smith
540 P.2d 274 (Idaho Supreme Court, 1975)
City of Weippe v. Yarno
528 P.2d 201 (Idaho Supreme Court, 1974)
Colorado Builders' Supply Co. v. National Fire Insurance Co.
423 P.2d 79 (Wyoming Supreme Court, 1967)
Minidoka County Ex Rel. Detweiler Bros. v. Krieger
399 P.2d 962 (Idaho Supreme Court, 1965)
International Harvester Co. v. L. G. DeFelice & Son, Inc.
197 A.2d 638 (Supreme Court of Connecticut, 1964)
Rogers v. County of Nez Perce
364 P.2d 1049 (Idaho Supreme Court, 1961)
Crouch v. Bischoff
280 P.2d 419 (Idaho Supreme Court, 1955)

Cite This Page — Counsel Stack

Bluebook (online)
274 P.2d 1002, 75 Idaho 492, 1954 Ida. LEXIS 253, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-ex-rel-modern-motor-co-v-h-k-construction-co-idaho-1954.