United States v. George Hyman

CourtCourt of Appeals for the First Circuit
DecidedDecember 10, 1997
Docket97-1577
StatusPublished

This text of United States v. George Hyman (United States v. George Hyman) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. George Hyman, (1st Cir. 1997).

Opinion

USCA1 Opinion



UNITED STATES COURT OF APPEALS
FOR THE FIRST CIRCUIT

____________________

No. 97-1577

UNITED STATES OF AMERICA FOR THE USE AND,
BENEFIT OF WATER WORKS SUPPLY CORPORATION,

Plaintiff, Appellee,

v.

GEORGE HYMAN CONSTRUCTION COMPANY,
NATIONAL UNION FIRE INSURANCE COMPANY OF
PITTSBURGH, P.A., FEDERAL INSURANCE COMPANY
AND SEABOARD SURETY COMPANY,

Defendants, Appellants.

____________________

APPEAL FROM THE UNITED STATES DISTRICT COURT

FOR THE DISTRICT OF MASSACHUSETTS

[Hon. Patti B. Saris, U.S. District Judge] ___________________

____________________

Before

Torruella, Chief Judge, ___________

Campbell, Senior Circuit Judge, ____________________

and Boudin, Circuit Judge. _____________

____________________

Steven J. Comen, with whom Jeremy M. Sternberg, Dori C. ________________ ____________________ ________
Gouin, Howard J. Hirsch and Goodwin, Procter & Hoar LLP were on _____ ________________ ____________________________
brief for appellant, The George Hyman Construction Company.
Bert J. Capone, with whom CharCretia V. DiBartolo and _______________ _________________________
Cetrulo & Capone were on brief for appellant, National Union Fire ________________
Insurance Company of Pittsburgh, PA; Federal Insurance Company
and Seaboard Surety Company.
Gary H. Kreppel for appellee. _______________
____________________
December 10, 1997
____________________

CAMPBELL, Senior Circuit Judge. Defendant- _______________________

appellant George Hyman Construction Company ("Hyman") appeals

from the district court's judgment awarding recovery to the

Water Works Supply Corporation ("Water Works") under the

Miller Act, 40 U.S.C. 270a-270d (1986) (the "Miller Act"

or the "Act"). Hyman makes a number of arguments as to why

the district court erred in allowing recovery. In this

opinion we concentrate particularly on Hyman's contentions:

(1) that Water Works did not satisfy the Act's ninety-day

notice requirement; and (2) that Water Works did not have a

sufficiently close relationship to Hyman to qualify for

recovery under the Miller Act. Finding no merit in these or

in the other arguments that Hyman advances, we affirm.

I. BACKGROUND.

The facts are largely undisputed. Hyman was the

general contractor on a $70 million federal construction

project to build a mail processing center in Waltham,

Massachusetts (the "Post Office Project" or the "Project").

Pursuant to the requirements of the Miller Act, Hyman

obtained a payment bond from National Union Fire Insurance

Company of Pittsburgh, PA, Federal Insurance Company, and

Seaboard Surety Company (collectively, the "Sureties"). On

or about September 16, 1994, Hyman entered into an oral

agreement with Calvesco, Inc. ("Calvesco"), wherein Calvesco

-2-

promised to serve as demolition, excavation and site work

subcontractor for the Post Office Project.

On September 16, 1994, the same day that Hyman

hired Calvesco, Calvesco submitted an application for credit

to Water Works, a purveyor of pipe and piping materials.

Water Works extended an unlimited line of credit to Calvesco.

Calvesco was working on at least three projects at that time,

and the credit application did not indicate whether it was

for a particular project.

Subsequently, Calvesco informed Hyman that it could

not legally serve as subcontractor on the Post Office Project

because it was a non-union shop. On September 27, 1994,

Hyman and Calvesco agreed to replace Calvesco with Iron

Holdings, Inc. d/b/a Charles A. Jackson Co. ("Jackson"), a

unionized company created by the principals of Calvesco.

On October 11, 1994, Jackson notified Water Works

that it had replaced Calvesco as subcontractor on the Post

Office Project. Jackson requested that it, rather than

Calvesco, receive Water Works's invoices. Because Water

Works had extended credit only to Calvesco and not to

Jackson, Water Works refused to supply Jackson unless

Calvesco executed a corporate guarantee. Until the corporate

guarantee could be signed, Water Works agreed to ship piping

materials to the Post Office Project site at Jackson's

request and to send the invoices to Calvesco. That same day,

-3-

Jackson placed an order for pipe. Water Works shipped the

material to "Charles A. Jackson Co., c/o Calvesco." Water

Works sent the invoice to "Calvesco, Inc. Attn: Jackson

Gateman, Treas." ("Gateman").

From early October through December 29, 1994, Water

Works filled seven purchase orders relating to the Post

Office Project. Water Works continued to ship materials to

the Post Office Project site and to send the invoices to

Gateman at Calvesco. Jackson paid for five of the seven

shipments; the other two invoices remain unpaid and are the

subject of this action. The first unpaid invoice, for

$53,493.83 and dated November 30, 1994, corresponded to an

order placed on November 1, 1994 by Lou Ingegneri, the Post

Office Project manager for Jackson. The second unpaid

Free access — add to your briefcase to read the full text and ask questions with AI

Related

MacCaferri Gabions, Inc. v. Dynateria Inc.
91 F.3d 1431 (Eleventh Circuit, 1996)
United States Ex Rel. Sherman v. Carter Constr. Co.
353 U.S. 210 (Supreme Court, 1957)
Riva v. Commonwealth of MA
61 F.3d 1003 (First Circuit, 1995)
Coffee v. United States
157 F.2d 968 (Fifth Circuit, 1946)
United States v. William L. Crow Construction Co.
826 F. Supp. 647 (E.D. New York, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
United States v. George Hyman, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-george-hyman-ca1-1997.