Terry Matthews, Inc. v. C & L CONTRACTING, INC.

959 F. Supp. 1434, 1997 U.S. Dist. LEXIS 3075, 1997 WL 117702
CourtDistrict Court, W.D. Oklahoma
DecidedMarch 6, 1997
DocketCIV-95-1879-R
StatusPublished

This text of 959 F. Supp. 1434 (Terry Matthews, Inc. v. C & L CONTRACTING, INC.) is published on Counsel Stack Legal Research, covering District Court, W.D. Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Terry Matthews, Inc. v. C & L CONTRACTING, INC., 959 F. Supp. 1434, 1997 U.S. Dist. LEXIS 3075, 1997 WL 117702 (W.D. Okla. 1997).

Opinion

ORDER

CAUTHRON, District Judge.

Before the Court is the motion of Plaintiff Terry Matthews, Inc. (“TMI”) for summary judgment on its claims against Defendant Amwest Surety Insurance Co. (“Amwest”) and Defendant Amwest’s motion for partial summary judgment on Plaintiff’s Complaint. The issues raised by these motions and the responses thereto are as follows:

1. Whether TMI can recover against Am-west, the surety for C & L Contracting, Inc. (“C & L”), on bonds issued in accordance with Okla. Stat. tit. 42, § 147.1 for amounts owed under or for breach of subcontracts between TMI and C & L or whether TMI’s claim is a “lien claim” only, pursuant to which TMI may only recover the reasonable value of material and labor furnished.

2. Whether TMI can establish that the written subcontracts with C & L were modi *1435 fied by executed oral agreements, and whether TMI can show fully executed oral agreements by clear and convincing evidence,

a.Whether TMI’s knowledge of on-site superintendents’ lack of authority to approve change orders or extras precludes enforcement of any fully executed oral agreements against C & L, precluding the surety’s liability for charges for extra work performed by TMI.

3. Whether C & L received payment from General Mills for the extra work performed by TMI and, if not, whether TMI is by that fact precluded under the terms of the subcontracts from recovering payment for extra work.

a. Has Amwest shown that its or C & L’s right to submit a claim to General Mills for payment of TMI’s extra work has been prejudiced by TMI’s failure to obtain written change orders and/or to submit timely claims to C & L?
b. Has Amwest waived or should it be precluded from asserting the defense that TMI failed to timely submit claims to C & L for payment of extra work to C & L’s prejudice because it failed to assert this defense until it filed its motion for partial summary judgment on February 3, 1997?

4. Assuming that TMI is not precluded from recovering payment for extra work it performed and that TMI is limited to recovering the reasonable value of that work, whether genuine issues of material fact exist as the reasonable value of that extra work.

5. Whether TMI released all liénable claims for original and extra work against Red Lobster # 237 by the final release and lien waiver it executed on January 27, 1995.

a. Does the final release and lien waiver apply to labor and materials furnished by TMI after the date of the release and waiver?
b. Does the parol evidence rule bar TMI’s evidence that neither C & L nor TMI intended that the final release and lien waiver operate to prevent TMI from being paid for extra work already performed or for work, including extra work, that TMI performed in the future?
c. . Did C & L and/or Amwest either abandon or waive its rights under the Final Release and Lien Waiver by allowing TMI to continue to work on Red Lobster # 237 after TMI executed the Final Release and Lien Waiver and/or by failing to plead the defense of release and failing to assert this defense until Amwest filed its motion for partial summary judgment on February 3, 1987?

6.Whether TMI has shown that it performed or substantially performed all of its obligations under the subcontracts with C & L (with or without modification), the amounts due under the subcontracts (with or without modification), and that C & L has failed to pay those amounts and/or whether C & L and therefore Amwest is entitled to offset(s) for expenses incurred by C & L to remedy defects in or to complete TMI’s work under the subcontracts.

This action is, as Amwest seems to suggest, an action against the substituted security, i.e., the payment bond, “in the same manner as is required for foreclosure of a lien claim,” and for the “principal, interest, court costs and attorney’s fees to the extent they could be awarded in a lien foreclosure proceeding.” OHa. Stat. tit. 42, § 147.1. But a lien claimant has a right to and must establish its substantive right to recover for the debt underlying the lien statement. Cf. Cashway Lumber Co. v. Langston, 479 P.2d 582, 585 (Okla.1970) (subcontractor proved proper perfection of its lien and substantive right to recover for the debt underlying the lien statement, thereby establishing the validity of its lien and its right to foreclose the lien, subject to a later proportional reduction in the amount of its judgment to the extent the total amount of all subcontractors’ valid liens, and thereby the property owner’s hen obligations to the subcontractors, exceed the contract price of the general contract); Knapp v. Arko Interstate Electric Co., 448 P.2d 996, 1005-06 (Okla.1968) (subcontractor may obtain and enforce hen for amount due on subcontract plus amount which represents an amount charged to the contractor for work and materials not included in the subcontract). The Court is not persuaded by Defendant Amwest’s unsupported assertion that TMI cannot recover against the bond amounts due pursuant to contracts but is *1436 limited to recovery of the reasonable value of goods and services rendered.

No question exists but that under Oklahoma law, 1 a written contract may. be altered or modified either “by a contract in writing, or by an executed oral agreement, and not otherwise.” Okla. Stat. tit. 15, § 237; Flour Mills of America, Inc. v. American Steel Building Co., 449 P.2d 861, 879-80 (Okla.1968); Kenison v. Baldwin, 351 P.2d 307, 309 (Okla.1960). See United States for the Use and Benefit of Moody v. American Insurance Co., 835 F.2d 745, 748-49 (10th Cir.1987) (Miller Act ease applying Oklahoma law concerning interpretation and modification of a contract to be performed in Oklahoma). This rule has been applied in cases involving construction contracts similar to those herein, requiring that extra work and changes be ordered in writing and that no claims for amounts based upon extra work or changes would be valid unless so ordered, in which the courts concluded that the contracts were modified when the owner or contractor requested additions and modifications to the contract and the contractor or subcontractor complied with those requests, resulting in a fully executed oral agreement modifying the written contract’s term requiring written change orders. See Flour Mills of America, Inc. v. American Steel Building Co., 449 P.2d at 877-78; Kenison v. Baldwin, 351 P.2d at 309; Pfeiffer v. Peppers Refining Co., 197 Okla.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Renfro v. City of Emporia, Kansas
948 F.2d 1529 (Tenth Circuit, 1991)
Exxon Corporation v. Allen Gann
21 F.3d 1002 (Tenth Circuit, 1994)
Bank of Oklahoma, N.A. v. Briscoe
911 P.2d 311 (Court of Civil Appeals of Oklahoma, 1996)
Thompson v. Estate of H. H. Coffield
894 P.2d 1065 (Supreme Court of Oklahoma, 1995)
CASHWAY LUMBER COMPANY v. Langston
479 P.2d 582 (Supreme Court of Oklahoma, 1970)
Knapp v. Arko Interstate Electric Co.
1968 OK 183 (Supreme Court of Oklahoma, 1968)
Fabbro v. Reese
1952 OK 256 (Supreme Court of Oklahoma, 1952)
Crockett v. McKenzie
1994 OK 3 (Supreme Court of Oklahoma, 1994)
Flour Mills of America, Inc. v. American Steel Building Co.
449 P.2d 861 (Supreme Court of Oklahoma, 1969)
Kenison v. Baldwin
1960 OK 93 (Supreme Court of Oklahoma, 1960)
Pfeiffer v. Peppers Refining Co.
1946 OK 280 (Supreme Court of Oklahoma, 1946)
Mertz v. Owen
1942 OK 165 (Supreme Court of Oklahoma, 1942)
Federal Deposit Ins. Corp. v. Grim
1938 OK 540 (Supreme Court of Oklahoma, 1938)
Truscon Steel Co. v. Cooke
98 F.2d 905 (Tenth Circuit, 1938)
Clark v. Brien
59 F.3d 1082 (Tenth Circuit, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
959 F. Supp. 1434, 1997 U.S. Dist. LEXIS 3075, 1997 WL 117702, Counsel Stack Legal Research, https://law.counselstack.com/opinion/terry-matthews-inc-v-c-l-contracting-inc-okwd-1997.