United States v. Mechanical Contractors, Incorporated

677 F.2d 383, 69 A.L.R. Fed. 592, 29 Cont. Cas. Fed. 82,471, 1982 U.S. App. LEXIS 19880
CourtCourt of Appeals for the Fourth Circuit
DecidedApril 22, 1982
Docket81-1754
StatusPublished
Cited by4 cases

This text of 677 F.2d 383 (United States v. Mechanical Contractors, Incorporated) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Mechanical Contractors, Incorporated, 677 F.2d 383, 69 A.L.R. Fed. 592, 29 Cont. Cas. Fed. 82,471, 1982 U.S. App. LEXIS 19880 (4th Cir. 1982).

Opinion

677 F.2d 383

69 A.L.R.Fed. 592, 29 Cont.Cas.Fed. (CCH) 82,471

The UNITED STATES of America for the Use of Honeywell,
Incorporated, Appellant,
v.
A & L MECHANICAL CONTRACTORS, INCORPORATED, Defendant,
and
LeBlanc Construction Company, National Surety Corporation, Appellees.

No. 81-1754.

United States Court of Appeals,
Fourth Circuit.

Argued Jan. 6, 1982.
Decided April 22, 1982.

Bradfute W. Davenport, Jr., Richmond, Va. (James C. Roberts, David G. Shuford, Mays, Valentine, Davenport & Moore, Richmond, Va., Cecil P. Merritt, Merritt & Gaylor, Goldsboro, N. C., on brief), for appellant.

Leonard T. Jernigan, Jr., Raleigh, N. C. (Michaels & Jernigan, Raleigh, N. C., on brief), for appellees.

Before WINTER, Chief Judge, HAYNSWORTH, Senior Circuit Judge, and HALL, Circuit Judge.

HAYNSWORTH, Senior Circuit Judge:

This is a suit under the Miller Act1 against a general construction contractor and its surety to collect unpaid debts owed by a subcontractor to Honeywell. Judgment was entered for the defendants on the grounds that all of the notices of the indebtedness were untimely, that, in any event, the amount of the claim was not stated with sufficient accuracy and, moreover, that Honeywell was estopped to assert the claim.2 We conclude that, with respect to work already done, the notice was not untimely though further work remained to be done. We also conclude that there was no estoppel and that the claim was stated with reasonable accuracy.

I.

The United States Air Force entered into a contract with LeBlanc Construction Company for the renovation of five dormitories at the Seymour Johnson Air Force Base. LeBlanc subcontracted the heating and cooling work to A & L Mechanical Contractors, Inc., which entered into a sub-subcontract with Honeywell, Inc. to provide the automatic temperature control systems, and to calibrate and adjust the controls after installation of the systems by A & L Mechanical.

Honeywell supplied the components of all five systems, but approximately three months before completion of all of the calibration and adjustment work, Honeywell informed LeBlanc by registered mail that A & L Mechanical was indebted to it by an unpaid balance of $31,083.96. Several weeks later LeBlanc wrote to Honeywell to inform it that A & L Mechanical denied that its account was due. Thereafter, on November 30, 1979, Honeywell sent another letter to LeBlanc by registered mail stating that there was still an unpaid balance of $27,161.56.3

Honeywell completed its work on January 22, 1980, and on May 7, 1980, it sent a third letter to LeBlanc saying that A & L Mechanical's indebtedness to Honeywell on the job was $28,522.54. A fourth notice was sent on June 20, 1980.

II.

Honeywell does not contend that either the May or June 1980 notice is effective. The ninety days from the January 22, 1980 completion date had run before the May 7 notice. It does contend that the October and November 1979 notices were effective with respect to materials furnished and work done before the dates of those notices. With that we agree.

Under § 270b(a), Honeywell is given a right of action upon a payment bond "upon giving written notice to said contractor within ninety days from the date on which such person did or performed the last of the labor or furnished or supplied the last of the material for which such claim is made, stating with substantial accuracy the amount claimed ...."

The statute does not require that the notice be given only after final completion of the project. The notice is timely if given within ninety days after performance of the last labor or supply of the last material "for which such claim is made." The statutory distinction is both necessary and reasonable. If a subcontractor is delinquent in making progress payments, its subcontractor, the claimant, should not be required to continue work on a prolonged project without progress payments. It should be entitled to assert its rights under the Miller Act so that its rights are protected and a defaulting subcontractor is either required to discharge its obligations or get off the job. The November 1979 notice did not claim anything with respect to work to be done or materials supplied thereafter; it was within ninety days after the labor or material "for which such claim is made" had been furnished.

In United States ex rel. Kinlau Sheet Metal Works, Inc. v. Great American Insurance Co., 537 F.2d 222 (5th Cir. 1976), it was said, in effect, that a notice given before completion of a construction job was premature and could not be considered as a qualifying notice. The notice was also held to have been substantively deficient, however, and the statement about prematurity is inconsistent with other cases construing the Miller Act and similar state statutes.4

The district court also thought its position was supported by our cases5 in which we held ineffective notices given more than ninety days after completion of a project. Strict enforcement of that requirement is necessary, however. The design of the statute is to give contractors, such as Honeywell, ninety days after completion of their work within which to assert a claim against the general contractor and its surety. If it does not do so within that period, the contractor may make final payment to the subcontractor with impunity. It would be quite unfair to the general contractor to expose it to stale claims of which it had no notice during the ninety day period. See Noland Company v. Allied Contractors, Inc., 273 F.2d 917, 920-21 (4th Cir. 1959). But those questions have no bearing upon the question of the validity of the November 1979 notice claiming payment for work already done. The claim was in no sense stale. Indeed, the defendant seeks to invalidate it for prematurity. However, it clearly sufficed to give notice of the claim in the maximum amount of $27,161.56. Nevertheless, in February LeBlanc made final payments to A & L Mechanical without assuring itself that Honeywell had been paid.6

The principal purpose of the Miller Act is the protection of persons supplying labor and materials to subcontractors on federal construction projects. To that end, the Supreme Court has held that the Miller Act should receive a liberal construction. United States ex rel Sherman v. Carter, 353 U.S. 210, 216, 77 S.Ct. 793, 796, 1 L.Ed.2d 776 (1957). We do not regard our construction as being "liberal," but surely the defendant's construction that would invalidate the November 1979 notice would be niggardly.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
677 F.2d 383, 69 A.L.R. Fed. 592, 29 Cont. Cas. Fed. 82,471, 1982 U.S. App. LEXIS 19880, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-mechanical-contractors-incorporated-ca4-1982.