National Union Indemnity Company v. R. O. Davis, Inc., R. O. Davis, Inc. And General Insurance Company of America v. General Electric Company

393 F.2d 897, 1968 U.S. App. LEXIS 7072
CourtCourt of Appeals for the Fifth Circuit
DecidedMay 6, 1968
Docket22121
StatusPublished
Cited by17 cases

This text of 393 F.2d 897 (National Union Indemnity Company v. R. O. Davis, Inc., R. O. Davis, Inc. And General Insurance Company of America v. General Electric Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National Union Indemnity Company v. R. O. Davis, Inc., R. O. Davis, Inc. And General Insurance Company of America v. General Electric Company, 393 F.2d 897, 1968 U.S. App. LEXIS 7072 (5th Cir. 1968).

Opinion

JOHN R. BROWN, Chief Judge:

This case adds one more pebble to the avalanche of litigation resulting from the financial collapse of Mojave Electric Company in I960. 1 Contractor 2 sued National, 3 surety for Subcontractor, 4 for losses sustained when Subcontractor failed to complete work on two contracts. There are three issues presented. The first and main one is whether the Trial Judge erred in refusing to hold that Contractor had made premature or improper payments to Subcontractor under the contract. The remaining subsidiary issues are, second, whether the Trial Judge properly held that Interstate, 5 the Supplier to Subcontractor, is entitled to recover from Contractor and General, 6 its Miller Act surety, amounts due Supplier from Subcontractor, and, third, whether it was proper to deny attorney’s fees and other incidental expenses of the litigation to Contractor. As to the first and third issues, we affirm. As to the second, we reverse.

The facts are not unduly complicated. The Federal Government and Contractor entered into contracts for the construction of jet fuel storage and wharf facilities for the Navy. As part of these contracts, Contractor, gave the Government the required statutory payment and performance bonds with Genera], its Miller Act surety. 7 Contractor then executed two contracts with Subcontractor for the electrical work on the jobs. Although not statutorily required to do so, Subcontractor gave Contractor a performance bond with National, the appellant here. 8 The initial amount of these two original contracts was $41,-618.69. When Subcontractor defaulted in March, 1960, Contractor in periodic monthly payments had already paid Subcontractor $8,689.06 of the total amount, but Subcontractor left outstanding bills *899 unpaid in the sum of about $8,650.00. A second subcontractor was brought in and completed the job for only $750.00 more than the total cost under the original contract.

Contractor demanded that National, as surety for Subcontractor, satisfy the claims of the unpaid materialmen that were being asserted against Contractor. Contending that it was not required to do so because of premature periodic payments from Contractor to Subcontractor, National asserted that it had been released from liability. Thereafter, the suppliers of Subcontractor brought suit against Contractor under the Miller Act bonds, but Contractor impleaded National, seeking full reimbursement and also asserting the right to recover the completion loss of $750.00, incidental costs of litigation, and attorney’s fees. The claims were consolidated and after a trial before the District Judge, he found that the two remaining unpaid suppliers 9 were entitled to recover their claims from Contractor and General, its surety, but that Contractor was entitled to recover from National, Subcontractor’s surety, all losses sustained through the claims of the suppliers and by having to relet the contract. Contractor’s claim for expenses and attorney’s fees were disallowed. From this judgment National appeals and Contractor cross-appeals.

The main thrust of National’s appeal is that under the contract between Contractor and Subcontractor premature payments were made by Contractor to Subcontractor. Since this action constituted a material variation from the contract without the consent of the surety, National was thereby released from any liability.

The critical language in the contract stated that Contractor agreed to pay Subcontractor for the work specified in the contract and that “this payment will be on the basis of a monthly amount equal to the value of the materials and labor installed the previous month * * The crucial words here are “material and labor installed.” National contends that on the basis of job completion records all the credible evidence showed that Contractor made an initial monthly payment to Subcontractor of $3,262.87 when Subcontractor had done nothing more than move materials to the jobsite. On this National urges that the payment was premature because the contract calls for the installation of the materials. If, as National asserts, this were indeed the only credible evidence in the record to show exactly what work by the Subcontractor preceded the payment, we may assume, without deciding, that we might be persuaded by the argument. Cf. National Union Indem. Co. v. G. E. Bass & Co., 5 Cir., 1966, 369 F.2d 75.

But the testimony of two witnesses, one an ex-employee of Contractor and one an ex-employee of Subcontractor, must also be considered. Without going too extensively into the testimony of these two witnesses, the gist of it was that the initial payment was made for materials on which labor had been expended for the purpose of incorporating those materials into the job. Further testimony allowed the Judge to conclude that the payments would certainly not have been made by the Contractor unless a significant amount of initial installation had actually been done. On the basis of this testimony, which helps to put the recorded payment on which National bases its defense into proper context, the determination that the material and labor had been installed passes muster under F.R.Civ.P. 52(a). Cf. National Union Indem. Co. v. Smith, 5 Cir., 1968, 389 F.2d 152 [Feb. 9, 1968].

The second issue, pressed jointly by National and Contractor, is that one of Subcontractor’s suppliers, Inter *900 state, did not comply with the notice requirements of the Miller Act, 40 U.S. C.A. § 270b(a). If this was so then as a matter of law it was unable to recover from Contractor and its Miller Act surety, who in turn demanded and obtained a judgment for reimbursement from National, as the surety of Subcontractor. Although National, half-heart-edly supported by the Contractor, makes a very persuasive argument that a claim in proper form was never made, 10 we need not reach this question for whatever its sufficiency in form and content, we must hold that it was not timely.

The only communication from Interstate to Contractor which could possibly be construed as a claim against Contractor to satisfy the Miller Act was a letter of March 18, 1960. The only materials involved here had an invoice date of July 25, but no year was specified. Taking 1959 as the year of delivery, a letter in March of 1960 is not timely since more than 90 days had elapsed since the last material was furnished. Taking 1960 as the proper year of delivery, then the letter of March 18, 1960, becomes premature and would not be a proper claim. Thus we hold that Interstate cannot recover from Contractor and its Miller Act surety since the notice was untimely.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cracker Barrel Old Country Store, Inc. v. Epperson
284 S.W.3d 303 (Tennessee Supreme Court, 2009)
J D Fields & Co, Inc v. Gottfried Corp
272 F.3d 692 (Fifth Circuit, 2001)
US FOR USE OF LABORERS'PEN. TR. v. Safeco Ins.
707 F. Supp. 286 (E.D. Michigan, 1988)
Dravo Corporation v. Kerris
655 F.2d 503 (Third Circuit, 1981)
Dravo Corp. v. Robert B. Kerris, Inc.
655 F.2d 503 (Third Circuit, 1981)
Stauffer Construction Co. v. Tate Engineering, Inc.
27 Cont. Cas. Fed. 80,200 (Court of Special Appeals of Maryland, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
393 F.2d 897, 1968 U.S. App. LEXIS 7072, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-union-indemnity-company-v-r-o-davis-inc-r-o-davis-inc-ca5-1968.