J D Fields & Co, Inc v. Gottfried Corp

272 F.3d 692, 2001 WL 1381194
CourtCourt of Appeals for the Fifth Circuit
DecidedNovember 27, 2001
Docket00-60668
StatusPublished
Cited by9 cases

This text of 272 F.3d 692 (J D Fields & Co, Inc v. Gottfried Corp) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J D Fields & Co, Inc v. Gottfried Corp, 272 F.3d 692, 2001 WL 1381194 (5th Cir. 2001).

Opinion

DeMOSS, Circuit Judge:

Plaintiff-Appellant, J.D. Fields & Company, Inc. (J.D. Fields), appeals the district court’s final judgment following a bench trial dismissing Fields’ claims under the Miller Act, 40 U.S.C. §§ 270a-270d, against Defendants-Appellees, The Gott-fried Corporation (Gottfried) and Continental Casualty Company (Continental Casualty), because of Fields’ failure to give adequate notice within the 90-day period prescribed by section 270b(a). The district court’s decision is vacated and remanded for further proceedings.

I. BACKGROUND

In 1997, Gottfried, as general contractor, contracted with the United States Government, Department of Veterans Affairs (VA), to perform construction work at the VA Hospital in Biloxi, Mississippi. Continental Casualty supplied a payment bond guaranteeing Gottfried’s payment of labor and materials supplied to the job. Cherokee Towing & Construction Co., Inc. (Cherokee) entered into a subcontract with Gottfried wherein it agreed to provide the labor, material, equipment, and supervision required to complete two steel sheet-pile cofferdams on the project in conjunction with the construction of an elevator shaft and stairwell.

Cherokee executed a rental agreement with J.D. Fields for the pilings it used in making the cofferdams, which it began driving on May 19, 1997. The rental agreement required the payment of monthly rental by Cherokee to J.D. Fields. The rental agreement was to terminate when Cherokee notified J.D. Fields that the pilings were ready for inspection and return shipment, after which J.D. Fields would be given the opportunity to inspect the pilings at the job site. Pursuant to the rental agreement, Cherokee was to pay final liquidation and reconditioning charges and pay attorneys’ fees in the event of its default.

Brian McHale, Sales Manager for J.D. Fields, testified that Cherokee’s rental payments were untimely throughout the rental period immediately prior to halting altogether in October 1997. McHale also testified that in late December 1997, or early January 1998, he called Karl Gott-fried, of The Gottfried Corporation, regarding the failure of Cherokee to meet its obligation to pay the rental payments for the months of October, November, and December 1997. McHale further testified during his telephone conversation that he informed Gottfried that his corporation would be responsible for any lien required to secure payment, as well as any attorneys’ fees, if the rental payments remained outstanding.

According to McHale, Gottfried told him that he would investigate the matter and get back in touch with McHale. Gottfried’s testimony did not conflict with McHale’s testimony on this fact. However, the district court found that both documentary evidence and witness testimony revealed that on December 22, 1997, Gottfried required Cherokee to execute a release certifying that all invoices for materials, payrolls, and other obligations in *695 curred by Cherokee in connection with the VA project had been paid in full and that there were no outstanding obligations against Cherokee applicable to the project. Nevertheless, the district court concluded that it was unclear from the testimony whether Gottfried was aware of Cherokee’s outstanding obligations at the time it required Cherokee to sign the release.

The district court found that Gottfried issued a check on January 7, 1998, made payable jointly to Cherokee and J.D. Fields for rental payments due in October, November, and December 1997, bringing Cherokee’s account current through January 9, 1998. Gottfried testified that at the time the check was issued, Cherokee had completed driving the pilings and he believed the pilings had been returned to J.D. Fields. Gottfried expected that no further rental fees would be owed and was unaware that the pilings had not been returned to J.D. Fields.

The district court noted that there was conflicting testimony regarding when the pilings left the job site. Louis Evans, a truck driver for Cherokee, testified that he observed the pilings in the lay-down yard on the VA premises approximately one month after the pilings were removed from the ground. Notably, Doug Ladner, President of Cherokee, testified that the pilings were stored for at least two weeks, and perhaps until late January or early February, on the VA premises in an area where daily logs and reports were not required. Jane Page, a Cherokee employee, testified that the pilings remained in the “lay down” area for about one week after they were removed from the ground. George Malcolm Brooks, Jr., Project Supervisor for Gottfried, testified that the pilings were removed and taken from the site on December 18, 1997, and that he did not see them on the “lay down” site after that date. James Levens, President of Levins Builders, Inc., another subcontractor, stated that his firm began constructing stairs for the VA project on December 19, 1997, and that the pilings would have had to have been removed from the site by that date in order for his company to begin work. Levin also testified that he never saw the pilings at the lay-down yard. David Boggs, Project Manager for the VA, recalled that the pilings remained for a few days near the loading dock after being removed from the ground, but he did not recall seeing them in the “lay down” yard. On redirect, Boggs testified that the pilings may have remained on site for two to three days after having been removed from the ground.

In view of the conflicting testimony, the district court concluded that the written records before it were the most reliable evidence. Those documents included Cherokee’s Daily Manpower Reports and Gottfried’s Daily Logs. The court noted that the Daily Logs showed that as of December 15, 1997, Cherokee had “finished pulling piling.” On December 17, Cherokee was “hauling sheet piling from job site.” On December 18, Cherokee had “finished removing piling.” The court found that there was no further mention of the pilings and no Daily Log was admitted into evidence on or after December 19. Although there was a Daily Manpower Report completed by Cherokee on December 19, indicating its presence on the site, there was no description of the work completed for the day. As a result, the court concluded that the last day the pilings were supplied to the job site was December 18, 1997. Based on this factual finding, the court found that the statutory period for notice under the Miller Act began to run on December 19, 1997, and expired 90 days later on March 18, 1998.

There is no dispute that the material rented by Cherokee was returned to J.D. *696 Fields on February 27, 1998. On March 2, 10, and 12, J.D. Fields sent letters to Cherokee regarding the charges for reconditioning and liquidation of the pilings used in the VA project. The letters do not indicate that they were copied to Gottfried; however, Gottfried does not deny that it received copies. On March 20, 1998, J.D. Fields mailed written notice to Cherokee and Gottfried of its Miller Act claim. The notice was not received by Gottfried until March 23,1998.

The court found that prior to the notice of claim mailed on March 20, 1998, and received on March 23, 1998, Gottfried received no notice of a demand upon it for payment of Cherokee’s account.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jems Fabrication, Incorporated v. Benetech, L.L.C.
566 F. App'x 298 (Fifth Circuit, 2014)
Younge Mechanical, Inc. v. Max Foote Construction Co.
869 So. 2d 1079 (Court of Appeals of Mississippi, 2004)
Southern Electrical Health Fund v. Kelley
308 F. Supp. 2d 847 (M.D. Tennessee, 2003)
Cableguard Sytems, Inc. v. Mid-Continent Casualty Co.
73 F. App'x 28 (Fifth Circuit, 2003)
Prator v. Paw Paw's Camper
Fifth Circuit, 2002

Cite This Page — Counsel Stack

Bluebook (online)
272 F.3d 692, 2001 WL 1381194, Counsel Stack Legal Research, https://law.counselstack.com/opinion/j-d-fields-co-inc-v-gottfried-corp-ca5-2001.