Fisk Electric Company v. DQSI, L.L.C.

894 F.3d 645
CourtCourt of Appeals for the Fifth Circuit
DecidedJune 29, 2018
Docket17-30091
StatusPublished
Cited by11 cases

This text of 894 F.3d 645 (Fisk Electric Company v. DQSI, L.L.C.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fisk Electric Company v. DQSI, L.L.C., 894 F.3d 645 (5th Cir. 2018).

Opinion

JENNIFER WALKER ELROD, Circuit Judge:

*647 A subcontractor performed electrical work for a general contractor on a post-Hurricane Katrina federal construction project. The subcontractor alleges that the general contractor fraudulently induced it into entering a settlement agreement that released the general contractor from any claims for liability under the Miller Act-a federal statute that requires general contractors to secure payment to subcontractors on most federal construction projects. The district court granted summary judgment to the general contractor. We determine that there is a genuine issue of material fact on justifiable reliance-an element of the subcontractor's fraudulent-inducement claim-and therefore REVERSE the district court's judgment and REMAND for further proceedings.

I.

DQSI, L.L.C., the general contractor here, contracted with the United States Army Corps of Engineers to perform work on a post-Hurricane Katrina pump station construction project. Western Surety Company issued a Miller Act payment bond on the project on DQSI's behalf. DQSI subcontracted with Fisk Electric Company; Fisk was to perform electrical work on the project. The contract allowed Fisk to assert claims for money damages for unforeseen delays not caused by Fisk. Due to delays apparently caused at least in part by adverse weather conditions, the completion of the project was delayed 464 days. Fisk asserted that it experienced significant additional expenses because of the delay, amounting to more than $400,000. Fisk invoiced DQSI for this amount but apparently was never paid. Months before filing a lawsuit, Fisk also submitted to DQSI a Request for Equitable Adjustment seeking damages for the 464 days of delay.

In 2013, Fisk sued DQSI and DQSI's surety, Western, pursuant to the Miller Act, 40 U.S.C. § 3131 , et seq. , 1 and for breach of contract after attempts to resolve the dispute without litigation. 2 Before Fisk filed this 2013 lawsuit, Norman G. "Pat" Clyne, Fisk's supervisor of operations, met twice with DQSI representatives following Fisk's demand letter for delay damages pursuant to the Miller Act. In his affidavit, Clyne states that Stanley Lee and Scott McCumsey, representatives of DQSI, expressed that they were uncomfortable submitting a Request for Equitable Adjustment for delay damages on Fisk's behalf. Clyne states: "I specifically asked if DQSI had already waived Fisk's rights to submit the [Request for Equitable Adjustment]. Stanley Lee and Scott McCumsey responded that it had not." In a later meeting, Lee and McCumsey apparently reiterated that DQSI had not waived Fisk's rights to submit the Request for Equitable Adjustment.

*648 In December 2013, Clyne sent a letter to DQSI. According to the letter, Fisk had previously requested from DQSI a copy of the bilateral modifications issued to DQSI by the Corps granting the 464-day extension. When DQSI had not readily complied with the request, Fisk had obtained copies of the bilateral modifications directly from the Corps through a Freedom of Information Act (FOIA) request. The contract modification to which Clyne's December 2013 letter refers contains a "closing statement" declaring the following: "It is further understood and agreed that this adjustment constitutes compensation in full on behalf of the Contractor, its subcontractors and suppliers for all costs and markups directly or indirectly attributable to the change, for all delays...." However, none of the bilateral modifications obtained through the FOIA request were signed by DQSI. According to Clyne in the December 2013 letter, "It appears from the documents that we received [through the FOIA request], that Fisk was foreclosed from seeking compensation from the Corps before Fisk and DQSI even began negotiations."

Fisk and DQSI mediated the case in April 2014. Clyne states in an affidavit that "based on the representations made at mediation by DQSI, my concerns about the [Request for Equitable Adjustment] expressed in my December 10, 2013 letter were laid to rest." Clyne states that "[b]ased on the prior representations by Mr. Lee and Mr. McCumsey and the fact that DQSI was agreeing to submit Fisk's claims to the Corps, I believed that Fisk's claims were still viable with the Corps and there had been no prior waiver of any rights to seek equitable adjustment."

The "memorandum of agreement" signed at mediation states that "Fisk agrees to provide DQSI with a fully supported [R]equest for Equitable Adjustment that is certifiable by DQSI to [the Corps]." In the memorandum of agreement, DQSI also agreed "to submit to [the Corps] the Request for Equitable Adjustment presented by Fisk provided that DQSI will only be responsible to submit the Request for Equitable Adjustment if it is certifiable to [the Corps] and is fully supported by Fisk." 3 Fisk also agreed "to defend, indemnify[,] and hold DQSI harmless in connection with, arising from, or related to DQSI's submission of Fisk's Request for Equitable Adjustment to [the Corps]." Following mediation, Fisk submitted a Request for Equitable Adjustment nearly identical to the previous one, again seeking damages for the 464-day delay. DQSI objected that the Request for Equitable Adjustment was "not properly supported as required" by the memorandum of agreement. Following mediation, Fisk filed a motion to enforce settlement. The motion was granted, requiring DQSI to submit Fisk's Request for Equitable Adjustment within seven days of the court order. DQSI submitted a Request for Equitable Adjustment to the Corps.

In December 2014, Fisk and DQSI entered into a settlement agreement intended "to formalize the terms" of the memorandum of agreement. 4 As part of the settlement, Fisk and DQSI agreed to a mutual release in which Fisk would release DQSI from any claims for the consideration of approximately $55,000. In consideration of the releases of claims, DQSI agreed "to submit a Request for *649 Equitable Adjustment ('REA') presented by Fisk to [the Corps]." In the event that the Corps awarded funds in response to the Request for Equitable Adjustment, the settlement agreement provided that if the amount exceeded $175,000, DQSI would retain the excess funds, provided that it would not retain more than $25,000. 5 According to Clyne, "[w]ithout the representations made by Mr. Lee and Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
894 F.3d 645, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fisk-electric-company-v-dqsi-llc-ca5-2018.