Jems Fabrication, Incorporated v. Benetech, L.L.C.

566 F. App'x 298
CourtCourt of Appeals for the Fifth Circuit
DecidedApril 30, 2014
Docket13-30934
StatusUnpublished

This text of 566 F. App'x 298 (Jems Fabrication, Incorporated v. Benetech, L.L.C.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jems Fabrication, Incorporated v. Benetech, L.L.C., 566 F. App'x 298 (5th Cir. 2014).

Opinion

PER CURIAM: *

Fidelity and Deposit Company of Maryland (“Fidelity”) and Zurich American Insurance Company (“Zurich,” and collectively with Fidelity, the “Sureties”) appeal the district court’s entry of a final judgment in favor of JEMS Fabrication, Inc. (“JEMS”) on its claim under the Miller Act, 40 U.S.C. §§ 3131-3134. We AFFIRM.

I. Background

The United States Army Corps of Engineers (the “Corps”) contracted with Bene-tech, LLC (“Benetech”), a construction contractor, to renovate and/or redevelop pumping stations at various sites located on the Mississippi River (the “JSP-05 Project”). Thereafter, the Sureties issued a payment bond (the “Payment Bond”) pursuant to the Miller Act on behalf of Bene-tech to protect subcontractors on the JSP-05 Project against the risk of non-payment by Benetech. Benetech then entered into a subcontract (the “Contract”) with JEMS in which JEMS agreed to provide certain custom-fabricated structural steel for the JSP-05 Project in exchange for a payment of $2,350,000. This figure included $202,432 for shop drawings, $1,316,584 for materials, and $830,984 for labor. Bene-tech and JEMS subsequently approved a change order for additional materials, increasing the total contract amount to $2,379,739.60. Later, JEMS and Benetech agreed to a modification of the Contract to *300 permit Benetech to provide the on-site labor going forward in order to satisfy certain self-performance requirements of the Corps. Although this modification was not memorialized in writing, JEMS thereafter terminated its on-site labor force although it continued to incur certain labor-related expenses.

JEMS delivered all of the drawings required by the Contract. JEMS also delivered many of the materials required by the Contract. However, JEMS did not deliver one building required by the Contract (the “Hero Building”); instead, Bene-tech and JEMS agreed that Benetech would purchase the Hero Building directly from a subcontractor for $54,000. During its performance under the Contract, JEMS did not submit periodic invoices to Bene-tech. Rather, JEMS delivered shipping tickets to Benetech of materials provided and Benetech provided periodic payments to JEMS over the course of the Contract. However, the shipping tickets did not indicate the price of the materials delivered and Benetech’s periodic payments did not detail which shipping tickets were being paid. In total, Benetech paid JEMS $996,882.14 for its work on the Contract. 1 However, Benetech claimed that JEMS was not entitled to the remainder of the payment due under the Contract, because JEMS had failed to deliver all of the materials required by the Contract.

Thereafter, JEMS filed the instant federal action, alleging Miller Act claims against Benetech, Fidelity, and Zurich, as well as a breach of contract claim and a Louisiana state law claim against Bene-tech. After a two-day trial, the district court entered a final judgment in favor of JEMS, ordering that Benetech, Fidelity, and Zurich were jointly and severally liable to JEMS in the amount of $497,873.46, plus interest. The Sureties timely appealed. 2

II. Standard of Review

We review a district court’s conclusions of law de novo. See J.D. Fields & Co., Inc. v. Gottfried Corp., 272 F.3d 692, 696 (5th Cir.2001). However, we review a district court’s findings of fact for clear error. See id.; see also Fed.R.Civ.P. 52(a)(6). A finding of fact is clearly erroneous when “although there is evidence to support it, the reviewing court on the entire evidence is left with the definite and firm conviction that a mistake has been committed.” Anderson v. City of Bessemer City, N.C., 470 U.S. 564, 573, 105 S.Ct. 1504, 84 L.Ed.2d 518 (1985) (quotations omitted). Therefore, “[wjhere there are two permissible views of the evidence, the factfinder’s choice between them cannot be clearly erroneous.” Id. at 574, 105 S.Ct. 1504.

III. Discussion

The Miller Act requires that a general contractor on a federal project post a bond for the purpose of protecting the suppliers of materials for the project. See Arena v. Graybar Elec. Co., Inc., 669 F.3d 214, 220 (5th Cir.2012). It provides suppliers and subcontractors with the right to sue a prime contractor to recover on the bond for the amounts owed to them. See 40 U.S.C. § 3133(b)(1). This statutory scheme “was created to protect parties such as subcontractors or suppliers who work on federal projects as state-law liens cannot be applied against federally-owned property and traditional state-law reme *301 dies are unavailable.” Arena, 669 F.3d at 220. The Miller Act is “highly remedial in nature” and “is entitled to a liberal construction and application in order properly to effectuate the Congressional intent to protect those whose labor and materials go into public projects.” Clifford F. MacEvoy Co. v. U.S. for Use & Benefit of Calvin Tomkins Co., 322 U.S. 102, 107, 64 S.Ct. 890, 88 L.Ed. 1163 (1944).

The elements of a Miller Act claim are: (1) the plaintiff supplied materials in prosecution of the work provided for in the contract; (2) the plaintiff has not been paid; (3) the plaintiff had a good faith belief that the materials were intended for the specified work; and (4) the plaintiff meets the jurisdictional requisites of timely notice and filing. See U.S. for Use & Benefit of Carlson v. Cont’l Cas. Co., 414 F.2d 431, 433 (5th Cir.1969); U.S. for Use & Benefit of Martin Steel Constructors, Inc. v. Avanti Constructors, Inc., 750 F.2d 759, 761 (9th Cir.1984).

First, the Sureties argue that the district court erred in entering judgment in favor of JEMS because JEMS failed to demonstrate at trial either: (1) that it supplied materials to Benetech in prosecution of the JSP-05 Project; or (2) that it had a good faith belief that the materials supplied to Benetech were intended for the JSP-05 Project. See Carlson, 414 F.2d at 433; see also United States v. C.J. Elec. Contractors, Inc., 535 F.2d 1326, 1328-29 (1st Cir.1976). Specifically, the Sureties assert that JEMS supplied materials to Benetech for other unrelated projects that were not covered by the Payment Bond at the same time as it supplied materials to Benetech for the JSP-05 Project.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
566 F. App'x 298, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jems-fabrication-incorporated-v-benetech-llc-ca5-2014.