PER CURIAM:
Fidelity and Deposit Company of Maryland (“Fidelity”) and Zurich American Insurance Company (“Zurich,” and collectively with Fidelity, the “Sureties”) appeal the district court’s entry of a final judgment in favor of JEMS Fabrication, Inc. (“JEMS”) on its claim under the Miller Act, 40 U.S.C. §§ 3131-3134. We AFFIRM.
I. Background
The United States Army Corps of Engineers (the “Corps”) contracted with Bene-tech, LLC (“Benetech”), a construction contractor, to renovate and/or redevelop pumping stations at various sites located on the Mississippi River (the “JSP-05 Project”). Thereafter, the Sureties issued a payment bond (the “Payment Bond”) pursuant to the Miller Act on behalf of Bene-tech to protect subcontractors on the JSP-05 Project against the risk of non-payment by Benetech. Benetech then entered into a subcontract (the “Contract”) with JEMS in which JEMS agreed to provide certain custom-fabricated structural steel for the JSP-05 Project in exchange for a payment of $2,350,000. This figure included $202,432 for shop drawings, $1,316,584 for materials, and $830,984 for labor. Bene-tech and JEMS subsequently approved a change order for additional materials, increasing the total contract amount to $2,379,739.60. Later, JEMS and Benetech agreed to a modification of the Contract to
permit Benetech to provide the on-site labor going forward in order to satisfy certain self-performance requirements of the Corps. Although this modification was not memorialized in writing, JEMS thereafter terminated its on-site labor force although it continued to incur certain labor-related expenses.
JEMS delivered all of the drawings required by the Contract. JEMS also delivered many of the materials required by the Contract. However, JEMS did not deliver one building required by the Contract (the “Hero Building”); instead, Bene-tech and JEMS agreed that Benetech would purchase the Hero Building directly from a subcontractor for $54,000. During its performance under the Contract, JEMS did not submit periodic invoices to Bene-tech. Rather, JEMS delivered shipping tickets to Benetech of materials provided and Benetech provided periodic payments to JEMS over the course of the Contract. However, the shipping tickets did not indicate the price of the materials delivered and Benetech’s periodic payments did not detail which shipping tickets were being paid. In total, Benetech paid JEMS $996,882.14 for its work on the Contract.
However, Benetech claimed that JEMS was not entitled to the remainder of the payment due under the Contract, because JEMS had failed to deliver all of the materials required by the Contract.
Thereafter, JEMS filed the instant federal action, alleging Miller Act claims against Benetech, Fidelity, and Zurich, as well as a breach of contract claim and a Louisiana state law claim against Bene-tech. After a two-day trial, the district court entered a final judgment in favor of JEMS, ordering that Benetech, Fidelity, and Zurich were jointly and severally liable to JEMS in the amount of $497,873.46, plus interest. The Sureties timely appealed.
II. Standard of Review
We review a district court’s conclusions of law
de novo. See J.D. Fields & Co., Inc. v. Gottfried Corp.,
272 F.3d 692, 696 (5th Cir.2001). However, we review a district court’s findings of fact for clear error.
See id.; see also
Fed.R.Civ.P. 52(a)(6). A finding of fact is clearly erroneous when “although there is evidence to support it, the reviewing court on the entire evidence is left with the definite and firm conviction that a mistake has been committed.”
Anderson v. City of Bessemer City, N.C.,
470 U.S. 564, 573, 105 S.Ct. 1504, 84 L.Ed.2d 518 (1985) (quotations omitted). Therefore, “[wjhere there are two permissible views of the evidence, the factfinder’s choice between them cannot be clearly erroneous.”
Id.
at 574, 105 S.Ct. 1504.
III. Discussion
The Miller Act requires that a general contractor on a federal project post a bond for the purpose of protecting the suppliers of materials for the project.
See Arena v. Graybar Elec. Co., Inc.,
669 F.3d 214, 220 (5th Cir.2012). It provides suppliers and subcontractors with the right to sue a prime contractor to recover on the bond for the amounts owed to them.
See
40 U.S.C. § 3133(b)(1). This statutory scheme “was created to protect parties such as subcontractors or suppliers who work on federal projects as state-law liens cannot be applied against federally-owned property and traditional state-law reme
dies are unavailable.”
Arena,
669 F.3d at 220. The Miller Act is “highly remedial in nature” and “is entitled to a liberal construction and application in order properly to effectuate the Congressional intent to protect those whose labor and materials go into public projects.”
Clifford F. MacEvoy Co. v. U.S. for Use & Benefit of Calvin Tomkins Co., 322
U.S. 102, 107, 64 S.Ct. 890, 88 L.Ed. 1163 (1944).
The elements of a Miller Act claim are: (1) the plaintiff supplied materials in prosecution of the work provided for in the contract; (2) the plaintiff has not been paid; (3) the plaintiff had a good faith belief that the materials were intended for the specified work; and (4) the plaintiff meets the jurisdictional requisites of timely notice and filing.
See U.S. for Use & Benefit of Carlson v. Cont’l Cas. Co.,
414 F.2d 431, 433 (5th Cir.1969);
U.S. for Use & Benefit of Martin Steel Constructors, Inc. v. Avanti Constructors, Inc.,
750 F.2d 759, 761 (9th Cir.1984).
First, the Sureties argue that the district court erred in entering judgment in favor of JEMS because JEMS failed to demonstrate at trial either: (1) that it supplied materials to Benetech in prosecution of the JSP-05 Project; or (2) that it had a good faith belief that the materials supplied to Benetech were intended for the JSP-05 Project.
See Carlson,
414 F.2d at 433;
see also United States v. C.J. Elec. Contractors, Inc.,
535 F.2d 1326, 1328-29 (1st Cir.1976). Specifically, the Sureties assert that JEMS supplied materials to Benetech for other unrelated projects that were not covered by the Payment Bond at the same time as it supplied materials to Benetech for the JSP-05 Project.
Free access — add to your briefcase to read the full text and ask questions with AI
PER CURIAM:
Fidelity and Deposit Company of Maryland (“Fidelity”) and Zurich American Insurance Company (“Zurich,” and collectively with Fidelity, the “Sureties”) appeal the district court’s entry of a final judgment in favor of JEMS Fabrication, Inc. (“JEMS”) on its claim under the Miller Act, 40 U.S.C. §§ 3131-3134. We AFFIRM.
I. Background
The United States Army Corps of Engineers (the “Corps”) contracted with Bene-tech, LLC (“Benetech”), a construction contractor, to renovate and/or redevelop pumping stations at various sites located on the Mississippi River (the “JSP-05 Project”). Thereafter, the Sureties issued a payment bond (the “Payment Bond”) pursuant to the Miller Act on behalf of Bene-tech to protect subcontractors on the JSP-05 Project against the risk of non-payment by Benetech. Benetech then entered into a subcontract (the “Contract”) with JEMS in which JEMS agreed to provide certain custom-fabricated structural steel for the JSP-05 Project in exchange for a payment of $2,350,000. This figure included $202,432 for shop drawings, $1,316,584 for materials, and $830,984 for labor. Bene-tech and JEMS subsequently approved a change order for additional materials, increasing the total contract amount to $2,379,739.60. Later, JEMS and Benetech agreed to a modification of the Contract to
permit Benetech to provide the on-site labor going forward in order to satisfy certain self-performance requirements of the Corps. Although this modification was not memorialized in writing, JEMS thereafter terminated its on-site labor force although it continued to incur certain labor-related expenses.
JEMS delivered all of the drawings required by the Contract. JEMS also delivered many of the materials required by the Contract. However, JEMS did not deliver one building required by the Contract (the “Hero Building”); instead, Bene-tech and JEMS agreed that Benetech would purchase the Hero Building directly from a subcontractor for $54,000. During its performance under the Contract, JEMS did not submit periodic invoices to Bene-tech. Rather, JEMS delivered shipping tickets to Benetech of materials provided and Benetech provided periodic payments to JEMS over the course of the Contract. However, the shipping tickets did not indicate the price of the materials delivered and Benetech’s periodic payments did not detail which shipping tickets were being paid. In total, Benetech paid JEMS $996,882.14 for its work on the Contract.
However, Benetech claimed that JEMS was not entitled to the remainder of the payment due under the Contract, because JEMS had failed to deliver all of the materials required by the Contract.
Thereafter, JEMS filed the instant federal action, alleging Miller Act claims against Benetech, Fidelity, and Zurich, as well as a breach of contract claim and a Louisiana state law claim against Bene-tech. After a two-day trial, the district court entered a final judgment in favor of JEMS, ordering that Benetech, Fidelity, and Zurich were jointly and severally liable to JEMS in the amount of $497,873.46, plus interest. The Sureties timely appealed.
II. Standard of Review
We review a district court’s conclusions of law
de novo. See J.D. Fields & Co., Inc. v. Gottfried Corp.,
272 F.3d 692, 696 (5th Cir.2001). However, we review a district court’s findings of fact for clear error.
See id.; see also
Fed.R.Civ.P. 52(a)(6). A finding of fact is clearly erroneous when “although there is evidence to support it, the reviewing court on the entire evidence is left with the definite and firm conviction that a mistake has been committed.”
Anderson v. City of Bessemer City, N.C.,
470 U.S. 564, 573, 105 S.Ct. 1504, 84 L.Ed.2d 518 (1985) (quotations omitted). Therefore, “[wjhere there are two permissible views of the evidence, the factfinder’s choice between them cannot be clearly erroneous.”
Id.
at 574, 105 S.Ct. 1504.
III. Discussion
The Miller Act requires that a general contractor on a federal project post a bond for the purpose of protecting the suppliers of materials for the project.
See Arena v. Graybar Elec. Co., Inc.,
669 F.3d 214, 220 (5th Cir.2012). It provides suppliers and subcontractors with the right to sue a prime contractor to recover on the bond for the amounts owed to them.
See
40 U.S.C. § 3133(b)(1). This statutory scheme “was created to protect parties such as subcontractors or suppliers who work on federal projects as state-law liens cannot be applied against federally-owned property and traditional state-law reme
dies are unavailable.”
Arena,
669 F.3d at 220. The Miller Act is “highly remedial in nature” and “is entitled to a liberal construction and application in order properly to effectuate the Congressional intent to protect those whose labor and materials go into public projects.”
Clifford F. MacEvoy Co. v. U.S. for Use & Benefit of Calvin Tomkins Co., 322
U.S. 102, 107, 64 S.Ct. 890, 88 L.Ed. 1163 (1944).
The elements of a Miller Act claim are: (1) the plaintiff supplied materials in prosecution of the work provided for in the contract; (2) the plaintiff has not been paid; (3) the plaintiff had a good faith belief that the materials were intended for the specified work; and (4) the plaintiff meets the jurisdictional requisites of timely notice and filing.
See U.S. for Use & Benefit of Carlson v. Cont’l Cas. Co.,
414 F.2d 431, 433 (5th Cir.1969);
U.S. for Use & Benefit of Martin Steel Constructors, Inc. v. Avanti Constructors, Inc.,
750 F.2d 759, 761 (9th Cir.1984).
First, the Sureties argue that the district court erred in entering judgment in favor of JEMS because JEMS failed to demonstrate at trial either: (1) that it supplied materials to Benetech in prosecution of the JSP-05 Project; or (2) that it had a good faith belief that the materials supplied to Benetech were intended for the JSP-05 Project.
See Carlson,
414 F.2d at 433;
see also United States v. C.J. Elec. Contractors, Inc.,
535 F.2d 1326, 1328-29 (1st Cir.1976). Specifically, the Sureties assert that JEMS supplied materials to Benetech for other unrelated projects that were not covered by the Payment Bond at the same time as it supplied materials to Benetech for the JSP-05 Project. The Sureties argue that JEMS failed to demonstrate that the materials it supplied were intended for the JSP-05 Project, not other projects, or that it had a good faith belief that the supplied materials were intended for the JSP-05 Project, not other projects.
However, the Sureties never argued to the district court that JEMS’ claim included materials supplied to Benetech for other projects. Absent extraordinary circumstances not present here, we do not consider arguments not previously raised before the district court.
See Vogel v. Veneman,
276 F.3d 729, 733 (5th Cir.2002).
Second, the Sureties assert that the district court erred in entering final judgment in favor of JEMS because the shop drawings prepared by JEMS for Benetech are not compensable labor under the Miller Act. The district court concluded that “Benetech already paid for the [shop] drawings ... because Benetech’s payments of $996,882.14 covered the amount JEMS was owed for the [shop] drawings.” The Sureties contend that the district court erred in concluding that Benetech’s payment of $996,882.14 covered the cost of the shop drawings. Specifically, the Sureties assert that, under Louisiana’s law of imputation, the district court should have imputed Benetech’s payment of $996,882.14 to the cost of the materials, not the cost of the shop drawings.
See
La. Civ.Code Ann. art. 1868 (providing that payments must be imputed to secured debts in preference to unsecured debts where the debts are simultaneously incurred).
The Sureties failed to raise this
argument before the district court. In fact, the district court noted that “the Sureties provide no justification as to why the amount due for the drawings should be deducted from the top of the remainder of the Contract Price owed to JEMS, rather than attributed to the amounts already paid by Benetech.” We thus decline to consider this argument.
See Vogel,
276 F.3d at 733.
Third, the Sureties argue that the district court erred in entering final judgment in favor of JEMS because the Sureties were entitled to a setoff in the amount of $408,759.13. Specifically, the Sureties assert that JEMS failed to deliver all of the materials required by the Contract and that, as a result, Benetech was forced to procure additional materials for the JSP-05 Project from other suppliers at a cost of' $408, 759.13. The district court concluded both that “JEMS delivered the material required by the Contract” and that Benetech was not entitled to deduct any expenditures in excess of the $54,000 attributable to the Hero Building because “Benetech failed to provide JEMS with notice of any deficiency and an opportunity to cure [pursuant to the Contract] before incurring the[se] additional expenses.”
The Sureties maintain that, unlike Benetech, it is not bound by the “notice and cure” provisions of the Contract and that it should not be precluded from obtaining a setoff on that basis. However, while a Miller Act surety is not a party to a contract between a subcontractor and a contractor,
see U.S. for & on behalf of Portland Constr. Co. v. Weiss Pollution Control Corp.,
532 F.2d 1009, 1012 (5th Cir.1976), it nonetheless stands in the shoes of the contractor and is. bound by its dealings for these purposes,
see U.S. for Benefit & on Behalf of Sherman v. Carter,
353 U.S. 210, 217-18, 77 S.Ct. 793, 1 L.Ed.2d 776 (1957);
see also Hous. Fire & Cas. Ins. Co. v. E.E. Cloer Gen. Contractor,
217 F.2d 906, 910 (5th Cir.1954). Therefore, the Sureties, like Benetech, are bound by the terms of the Contract, including its “notice and cure” provisions. The Sureties do not dispute that Benetech failed to comply with these provisions. As a result, we conclude that the district court did not err in concluding that neither Benetech nor the Sureties were entitled to a setoff for
these additional expenses.
Moreover, JEMS introduced substantial evidence at trial indicating that it had supplied all of the materials, with the exception of the Hero Building, required by the Contract, including testimony from several witnesses, shipping tickets, and bills of lading. Although Benetech introduced evidence indicating that it purchased materials for the JSP-05 Project, it did not introduce evidence directly linking the invoices for its purchases with specific materials that should have been delivered by JEMS under the Contract. As a result, we conclude that the district court did not clearly err in concluding that “JEMS delivered the material required by the Contract.”
See
Fed.R.Civ.P. 52(a)(6);
Anderson,
470 U.S. at 573-74, 105 S.Ct. 1504.
AFFIRMED.