Houston Fire & Casualty Insurance Company v. E. E. Cloer General Contractor, Inc., and United States Guarantee Company

217 F.2d 906, 1954 U.S. App. LEXIS 4079
CourtCourt of Appeals for the Fifth Circuit
DecidedDecember 22, 1954
Docket15104_1
StatusPublished
Cited by18 cases

This text of 217 F.2d 906 (Houston Fire & Casualty Insurance Company v. E. E. Cloer General Contractor, Inc., and United States Guarantee Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Houston Fire & Casualty Insurance Company v. E. E. Cloer General Contractor, Inc., and United States Guarantee Company, 217 F.2d 906, 1954 U.S. App. LEXIS 4079 (5th Cir. 1954).

Opinion

TUTTLE, Circuit Judge.

We have here for consideration the question whether that type of surety bond that is generally known as a performance bond, which is conditioned on the faithful performance of the principal contract requiring that the principal “furnish all materials and perform all work as described etc.,” but failing to state affirmatively that the contractor will pay for the materials so furnished, requires that such surety stand responsible for the payment of materials admittedly used in furtherance of the contract.

This case is here on appeal from a judgment given by the trial court in favor of Cloer and his surety, United States Guarantee Company, two of the defendants below, over against Houston Fire and Casualty Insurance Company, another defendant below. The action was originally brought by the United States of America for the use of Johns-Manville Sales Corporation, an admitted supplier of materials to Latimer, a subcontractor of Cloer’s in a government construction job. The United States Guarantee Company was surety for Cloer under a Miller Act bond, § 270a, Title 40, U.S.C.A. Latimer had defaulted after incorporating the materials purchased from Johns-Manville in the job, and Houston Fire and Casualty Insurance Company, having the option to “(1) Complete the contract in accordance with its terms and conditions, or (2) Obtain a bid or bids for completing the contract within the penal limits of the bond,” elected to and did, according to written stipulation in the record, enter upon the job and complete it “in accordance with the plans and specifications of the Latimer Roofing Company.” It was clear from the record that this did not mean that Houston paid for *908 materials previously used by its principal Latimer.

In the action below Houston was not obligated directly to Johns-Manville because it did not execute a Miller Act bond giving a direct right to material-men. When, therefore, the materialman sued Cloer, the general contractor and his surety, United States Guarantee Company, as well as Houston jointly, Cloer and United States Guarantee Company prayed judgment over against Houston on the bond given by it to Cloer. This bond was a simple document in a penal sum of $21,500, the amount of Latimer’s contract, referring to the contract between Latimer and Cloer and stating the condition as follows:

“Now, therefore, the condition of this obligation is such that, if the contractor (Latimer) shall promptly and faithfully perform said contract, then this obligation shall be null and void; otherwise it shall remain in full force and effect.”

The provisions of the contract that are germane are:

“Section 1. The subcontractor agrees to furnish all materials and perform -all work as described in Section 2 hereof. * * *
“Section 2. The subcontractor and the contractor agree that the materials to be furnished and the work to be done by the subcontract- or are all roofing (Section 4, Part IV) and all sheet metal pertaining to roofing.”

On the trial below the court entered up judgment for the use plaintiff, Johns-Manville, against Cloer and his surety, United States Guarantee Company, and then entered judgment in their behalf against Houston Fire and Casualty Insurance Company on the performance bond executed by it.

No difficulties arise as to the construction of the bond executed by appellant. Both parties here agree that Houston is liable unless Latimer or Houston, substituting for Latimer, promptly and faithfully performed Latimer’s contract with Cloer. The question that is posed then is what is the proper construction of the contract itself. The trial court stated at one point that the bond should be strictly construed and at another that the bond “should be construed most strongly against the man making it.” Appellant complains of this second statement, contending that the rule in Texas is that suretyship contracts must be construed strictly in the surety’s favor, citing Bill Curphy Co. v. Elliott, 5 Cir., 207 F.2d 103, and Southern Surety Co. v. Klein, Tex.Civ. App., 278 S.W. 527. We think it unimportant to determine whether there was any inconsistency in the court’s comments, 1 because there can be no question *909 here as to what was meant by the surety bond; it simply stood responsible for the performance of the contract between Latimer and Cloer. That contract will be construed under the ordinary rules of construction, the underlying one of which is to ascertain what the parties meant by their engagements.

As we read the contract in the light of the circumstances under which it was executed, we conclude that it required not only that Latimer furnish the materials, but also that it furnish them free of any claims of materialmen; or in other words that all materials furnished be paid for by the subcontractor. All parties to the subcontract and its surety bond were charged with knowledge that Cloer had been required to give surety to the United States Government that he would pay all labor and material costs in connection with the principal contract. This much is required by the statute. 40 U.S.C.A. § 270a. Thus Cloer would be obligated to the extent of his financial responsibility to discharge all unpaid obligations incurred by his subcontractor, whether they be obligations for labor or materials. Since he was thus vulnerable as against all such claimants and as Lati-mer, his subcontractor, knew he was, what did they intend when they signed a contract whereby Latimer agreed to “furnish all materials, and perform all work as described, etc.”? Could it be contended that they did not intend that this was to be done at Latimer’s expense and out of the contract price? Here the contract provided that the subcontractor was entitled to draw up to 90¡% of the “work or materials as far as executed and fixed in place,” and while the record is silent as to the state of the account between Cloer and Latimer, it is stipulated that Houston “entered upon the job and completed it.” It can therefore be assumed that whatever retained per *910 centage was left in Cloer’s hands was paid to Houston, since that would be required under the contract. Houston therefore received some substantial amount of money that represented a 10% retained percentage of the very materials for the payment of which it disclaims responsibility, since 10'% of the value of materials in place was withheld from each month’s estimate. This brings into play the principle that where the surety elects to step into the shoes of the contractor in such a case, it does so cum onere. It becomes entitled to all the benefits and assumes all the liabilities. See W. H. Putegnat Co., Inc. v. Fidelity & Deposit Co. of Maryland, Tex. Com.App., 29 S.W.2d 1004.

Two cases, one a case in the Court of Appeals for the 2nd Circuit, and one in the New York Court of Appeals are persuasive authority for the conclusion we have reached. These are: United States for Use of W. E. Foley & Bro., Inc. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jems Fabrication, Incorporated v. Benetech, L.L.C.
566 F. App'x 298 (Fifth Circuit, 2014)
Colonial American Casualty & Surety Co. v. Scherer
214 S.W.3d 725 (Court of Appeals of Texas, 2007)
Star Contracting Corporation v. Manway Construction
337 A.2d 669 (Connecticut Superior Court, 1973)
Miles v. Fidelity & Casualty Co. of New York
185 So. 2d 613 (Louisiana Court of Appeal, 1966)
Buck v. Reed
381 S.W.2d 490 (Court of Appeals of Texas, 1964)
Crews Well Service v. Texas Company
358 S.W.2d 171 (Court of Appeals of Texas, 1962)
Pennsylvania Fire Insurance v. American Airlines, Inc.
180 F. Supp. 239 (E.D. New York, 1960)
Steelcraft Manufacturing Co. v. Hewkin
148 F. Supp. 872 (E.D. Illinois, 1956)

Cite This Page — Counsel Stack

Bluebook (online)
217 F.2d 906, 1954 U.S. App. LEXIS 4079, Counsel Stack Legal Research, https://law.counselstack.com/opinion/houston-fire-casualty-insurance-company-v-e-e-cloer-general-ca5-1954.