Ætna Casualty & Surety Co. v. Russell

24 S.W.2d 385
CourtTexas Commission of Appeals
DecidedFebruary 19, 1930
DocketNo. 1150—5448
StatusPublished
Cited by9 cases

This text of 24 S.W.2d 385 (Ætna Casualty & Surety Co. v. Russell) is published on Counsel Stack Legal Research, covering Texas Commission of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ætna Casualty & Surety Co. v. Russell, 24 S.W.2d 385 (Tex. Super. Ct. 1930).

Opinion

SHORT, P. J.

The defendant in error employed Fred C. Herbst, a contractor, to erect a brick building and to move and repair another building for a price of $18,317.80, the contractor to pay out of this sum for all the labor and all the material used in the construction of the brick building and the repair of the other. The contract between these two parties was reduced to writing, and, among other things, this language was used:

“One Herbst and the Defendant in error, Russell, entered into a builder’s contract whereby said Herbst agreed to furnish all material and labor and to perform the work specified in the contract for a consideration of $18,000.00, increased to $18,317.80 by additions and changes provided for in the contract. To secure the performance of the contract, Herbst entered into a bond with Plaintiff in Error, as surety, in the sum of $9,000.-00. As to the manner of payment, the contract provided that payments for labor were to be made in full every week; the payments for the material were to be made every two weeks, the provision being * * * payment of 15% of the value of all material furnished in the construction of said building will be made every two weeks. * * * Payment of the other 25% of the balance covering all materials up to the full amount of said contract price will be made after final approval and acceptance by the first party of ail other material and work embraced in this contract.”

The defendant in error required Herbst to procure the execution of a $9,000 bond, which he did, by securing as his surety the plaintiff in error. The contractor having failed to comply with his part of the contract, and the surety company having failed to comply with the demands of the defendant in error, to pay what the latter had assumed he had been compelled to pay, in order to release his property from alleged liens against it, by reason of Herbst’s failure to fully pay for labor and material, this suit was brought by the defendant in error, and, upon a trial to a jury with the submission of special issues, based upon the answers thereto, judgment was rendered against the plaintiff in error for $3,969, plus $600 attorney’s fees. Upon appeal to the Court of Civil Appeals, the judgment of the trial court was affirmed [14 S.W.(2d) 78], and writ of error was granted upon the error assigned, committed by the Court of Civil Appeals, in construing the following language, among other things, upon which the bond was conditioned: “ * * * To indemnify Russell against loss or expense resulting from the failure of Herbst to pay all labor and material bills in connection with the contract” The Court of Civil Appeals held that defendant in error bound himself to pay all of the labor bills as and when presented to him, and 76 per cent, of all of the material bills as and when presented to him, and that the plaintiff in error obligated itself to guarantee the compliance by Herbst with the obligations imposed by the terms of the contract. It is the contention of the plaintiff in error that, under the quoted provisions of the contract, the company’s obligation was to indemnify defendant in error against any legal liability by reason of the failure of Herbst to pay any labor or material bills.

At the conclusion of the testimony, the plaintiff in error requested the court to deliver to the jury a summary instruction in its favor. This, was refused, and the alleged error,- committed by the trial court, has been duly preserved in the record. We have read the statement of facts and the findings of fact by the Court of Civil Appeals, and have •reached the conclusion that the plaintiff in error was entitled to have this instruction given.

The Court of Civil Appeals, in its opinion, correctly says: “The parties agree that tbe facts were without dispute, and on the substantive law of the case regulating their relations to each other, as announced by the Supreme Court in Bullard v. Norton, 107 Tex. 671, 182 S. W. 668, that any material alteration in the terms of the contract without appellant’s consent would release it from liability, and that whether the change in the [387]*387contract was injurious to appellant or favorable.”

Tbe testimony of tbe parties, as well as that of tbe other evidence in tbe case, being without dispute to tbe effect that tbe defendant in error, in bis contract with tbe contractor, reserved “tbe right to require each week a pay roll receipt from all men employed showing full payment to all laborers as said amount is advanced by first party,” and further that tbe owner feserved “tbe right to require a receipt from tbe concerns furnishing said materials showing payments made to said concerns and tbe payment of tbe other 25%, or tbe balance covering all material up to tbe full amount of said contract price, will be made after final approval and acceptance by first party of all of tbe material and work embraced in tbe contract,” and tbe testimony being further without dispute that, after tbe .owner bad paid tbe contractor tbe full amount of tbe contract price, be then discovered for tbe first time that the contractor had failed to pay laborers’ bills, amounting to more than $1,000, and material-men, amounting to nearly $3,000, and it being apparent that tbe provisions in tbe contract above quoted were material parts of it, in which tbe plaintiff in error bad a substantial interest as surety, it clearly appears that these quoted provisions of tbe contract were not complied with by the defendant in error.

While tbe defendant in error bad tbe right to waive these provisions so far as requiring tbe contractor to comply with them bad he not required tbe contractor to give a bond guaranteeing tbe faithful performance by him of those things mentioned in tbe contract, yet, when the plaintiff in error became interested, by virtue of tbe obligations evidenced by the bond, it then became tbe duty of the defendant in error, which be owed to the plaintiff in error, to demand of tbe contractor a . substantial compliance of these terms of tbe contract, for tbe reason that such compliances furnished to tbe.plaintiff in error a security in tbe bands of tbe defendant in error to reimburse tbe latter for any sums of money it would owe to the defendant in error, by reason of the failure of the contractor to comply with the terms of bis contract.

This contract of tbe parties, evidenced by tbe two instruments, tbe one executed by Herbst and tbe defendant in error and tbe other executed by tbe plaintiff in error, are unambiguous in their terms, and need no construction. Upon tbe one band, tbe contractor agreed with tbe defendant in error to build a brick bouse and repair another building, according to the specifications, furnishing all tbe labor and all of tbe material, payments for tbe labor to be made weekly, tbe amount of which was to toe evidenced by a receipt from all of the men employed, showing full payment to all laborers, and every two weeks payment for tbe material, to tbe extent of 75 per cent, of material furnished, based upon tbe receipts from the concerns furnishing tbe materials, showing full payments made to said concerns by Herbst.

Tbe testimony shows that tbe amounts paid for labor by tbe defendant in error aggregated some $10,000, and tbe balance of tbe contract price representing materials furnished, paid by tbe defendant in error during the course of tbe construction, amounted to the remainder of tbe contract price, aggregating something less than $8,000.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Allied Bank of Texas v. Plaza Deville Associates
733 S.W.2d 566 (Court of Appeals of Texas, 1987)
ALLIED BANK OF TX v. Plaza DeVille Assoc.
733 S.W.2d 566 (Court of Appeals of Texas, 1987)
New Amsterdam Casualty Co. v. Bettes
407 S.W.2d 307 (Court of Appeals of Texas, 1966)
Knutson v. Metallic Slab Form Co.
130 F.2d 200 (Fifth Circuit, 1942)
New Amsterdam Casualty Co. v. F. Renondo & Co.
158 S.W.2d 334 (Court of Appeals of Texas, 1942)
United States Fidelity & Guaranty Co. v. Daniels
107 S.W.2d 400 (Court of Appeals of Texas, 1937)
Fidelity Union Casualty Co. v. State
54 S.W.2d 1079 (Court of Appeals of Texas, 1932)

Cite This Page — Counsel Stack

Bluebook (online)
24 S.W.2d 385, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tna-casualty-surety-co-v-russell-texcommnapp-1930.