Ætna Casualty & Surety Co. v. Russell

14 S.W.2d 78
CourtCourt of Appeals of Texas
DecidedJanuary 3, 1929
DocketNo. 1744. [fn*]
StatusPublished
Cited by1 cases

This text of 14 S.W.2d 78 (Ætna Casualty & Surety Co. v. Russell) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ætna Casualty & Surety Co. v. Russell, 14 S.W.2d 78 (Tex. Ct. App. 1929).

Opinions

On the 8th day of March, 1926, T. A. Russell contracted in writing with F. C. Herbst for Herbst to build him one brick building and to remove and repair a wooden building for an agreed consideration of $18,000, which, by additions and changes provided for in the contract, was increased to $18,317.80. Appellant, as surety, joined with Herbst in executing a bond to appellee in the sum of $9,000 to secure the faithful performance of the contract. The wooden building was moved and repaired, but Herbst abandoned his contract without finishing the brick building. Appellee gave due notice to appellant of Herbst's default, as required by the bond, whereupon appellant denied all liability on its bond on the ground that appellee and Herbst had breached the following condition of the contract:

"Payments of the value of all work executed satisfactorily based upon the estimated value thereof as determined by the owner will be made every week, said amounts covering payment for labor only, and said first party reserves the right to require each week a payroll receipt from all men employed showing full payment to all laborers as said amount is advanced by first party; and payment of 75% of the value of all material furnished in the construction of said building will be made every two weeks, the owner reserving the right to require a receipt from the concerns furnishing said material showing payments made to said concerns and the payment of the other 25% of the balance covering all materials up to the full amount of said contract price will be made after final approval and acceptance by first party of all other material and work embraced in this contract. Before or at the time final payment is made second party agrees to furnish receipt of all bills of whatsoever character paid and make an acceptable contractor's affidavit to that effect."

Appellee then brought this suit, pleading the contract and bond, Herbst's default, due demand upon appellant, and prayed for his damages in the sum of $4,853.11. Among other defenses, appellant pleaded breach of the above-quoted clause of the contract. The trial was to a jury, and on its verdict judgment was entered in favor of appellee against appellant and Herbst for the sum of $3,960.03, together with an attorney's fee of $500, under the conditions of the bond, and an additional judgment against Herbst for $180.

The parties agree that the facts were without dispute, and on the substantive law of the case regulating their relations to each other, as announced by the Supreme Court in Bullard v. Norton, 107 Tex. 571,182 S.W. 668, that any material alteration in the terms of the contract without appellant's consent would release it from liability, and that whether the change in the contract was injurious to appellant or favorable to it. The facts may be summarized as follows:

(1) Appellant and Herbst entered into a contract in writing containing the above-quoted clause, whereby Herbst was to build for appellee one brick building and move and repair one wooden building for $18,000, which, by additions and changes allowed by the contract, was increased to $18,317.80. Appellant entered into a bond with Herbst in *Page 79 the sum of $9,000, payable to appellee, to secure the faithful performance of the contract.

(2) The wooden building was moved and repaired in accordance with the contract, and for this work, under the contract, Herbst was allowed $2,000 of the contract price.

(3) Herbst abandoned the brick building before it was completed. The expense of finishing the building as per the contract was small, and the amount involved thereby was not a controverted item.

(4) During the progress of the work, Herbst presented all his labor bills to appellee, in accordance with the express conditions of the contract, as quoted above, and appellee duly paid the labor bills when presented to him.

(5) "Every two weeks" Herbst presented to appellee bills for the "value of material furnished in the construction of said building" as the material was furnished, and appellee duly paid to Herbst 75 per cent. of all the bills thus presented to him.

(6) Herbst continued on the Job, presenting labor bills "every week" and material bills "every two weeks," and appellee continued paying all the labor bills in full and 75 per cent. of the material bills thus presented to him until he had paid to Herbst the full contract price of $18,317.80.

(7) When appellee notified Herbst that all the contract price had been exhausted, Herbst abandoned the contract on the ground that he was without funds to finish it.

(8) All the money paid by appellee to Herbst on the contract was used by Herbst in payment of labor and material bills incurred by him in executing the contract.

(9) At the time Herbst defaulted, there were unpaid material bills in the sum of $4,123.91 for material used under the terms of the building contract in the construction of the brick building.

(10) The total cost of the material used in both buildings was $11,485.39. The total cost of labor under the contract was $10,956.32.

Appellee paid to Herbst on material bills $7,361.48. The amount unpaid was in excess of 25 per cent. of the total cost of material. The jury found that appellee retained in his hands "at all times, until after the defendant the Ætna Casualty Surety Company had refused to complete said building and pay the balance of the bills then due for material used * * * at least twenty-five per cent. of the total amount due for said material under the terms of the contract introduced in evidence." Appellants excepted to the submission of this issue, on the ground that it involved a conclusion of law to be drawn by the court from the undisputed facts, and that, on the undisputed facts, verdict should have been instructed in its favor. Appellee agrees with appellant that the issue is one of law and not of fact, but insists that on the undisputed evidence verdict should have been instructed in his favor. The parties then being in agreement on the facts and on the substantive law of the case regulating their respective rights, we have before us only one question: Upon the agreed facts, did the appellee and Herbst make material alterations in the building contract? If they did, appellant was released. If they did not, judgment was properly entered against it.

Surety contracts are strictly construed in favor of the surety. The rule is thus stated by 32 Cyc. 73: "Sureties are said to be favorites of the law, and a contract of suretyship must be strictly construed to impose upon the surety only those burdens clearly within its terms, and must not be extended by implication or presumption. This rule is followed both at law and in equity. Construction in favor of the surety should not, however, be carried to the length of giving the contract a forced and unreasonable construction with the view of relieving him."

The surety assumes no burden not clearly within the terms of the contract. If there is an ambiguity, the contract must be given the construction most favorable to the surety. But the rules for construing surety contracts, as with all other contracts, have been devised to assist in ascertaining the intent of the parties. This intent, when ascertained, is the contract, and must be enforced. Though sureties are favorites of the law and must be given the benefit of all ambiguities, yet it must be borne in mind that the parties to such contracts are trying to assume reciprocal duties towards each other, and therefore a surety contract must not be given "a forced and unreasonable construction," with a view of relieving the surety; that is to say, the contract should not be so construed as to make it null and void unless such a construction is absolutely imperative.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ætna Casualty & Surety Co. v. Russell
24 S.W.2d 385 (Texas Commission of Appeals, 1930)

Cite This Page — Counsel Stack

Bluebook (online)
14 S.W.2d 78, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tna-casualty-surety-co-v-russell-texapp-1929.