Aetna Casualty & Surety Co. v. Robertson Lumber Co.

3 S.W.2d 895
CourtCourt of Appeals of Texas
DecidedFebruary 16, 1928
DocketNo. 615.
StatusPublished
Cited by13 cases

This text of 3 S.W.2d 895 (Aetna Casualty & Surety Co. v. Robertson Lumber Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Aetna Casualty & Surety Co. v. Robertson Lumber Co., 3 S.W.2d 895 (Tex. Ct. App. 1928).

Opinion

STANFORD, J.

Suit by appellee Robertson Lumber Company against appellant ¿Etna Casualty & Surety Company, and Gregory & Hope, for material furnished to Gregory & Hope as contractors, and by them used in the construction of a city hall for the city of Groesbeck under a contract between said city and said contractors, upon whose bond for the faithful performance of said contract appellant ¿Etna Casualty & Surety Company became a surety. Numerous other parties who furnished labor and material intervened and sought judgment against said surety company and said contractors. The surety company made the city of Groesbeck a party, and by appropriate pleadings asked in case the parties who furnished labor and material recovered against it, that it have judgment for a like amount over against the city of Groesbeck. The case was tried before the court withodt a jury, and judgment rendered against the surety company and said contractors and in favor of the parties who furnished labor and material, amounting in the aggregate to $3,682.17, and judgment in favor of said surety company over against the city of Groesbeck for $3,280.92. The city of Groesbeck and the surety company have appealed, and present the record for review.

Under its first proposition, appellant city of Groesbeck, which will hereafter be referred to as the city, contends that it and its contractors had the right under the provisions of said contract to change, without the knowledge or consent of the surety company, the provisions of the contract providing the method and manner of the payments by the city to the contractor of the contract price. The contract obligated the contractors to build said city hall according to plans and specifications, and obligated the city to pay the contractors the sum of $32,253, payable as the work progressed, as follows:

“The- superintendent selected by the city shall each week make an estimate of the amount of work done and material placed on the ground during said week, and furnish a copy of same *897 to the contractor, and the city shall pay 80 per cent, of said estimate, retaining 20 per cent, of same, which retainage shall be held by the city until the final completion and acceptance of said building,” etc.

The city failed to comply with the contract in respect to paying only 80 per cent, of the weekly estimates and retaining 20 per cent, until the work was completed and accepted, and seeks to justify its course in so doing under the following clause of the contract, which it claims authorized it and the contractors to change the provision of the contract providing for the 20 per cent, retainage:

“The owner reserves the right, by conferring with the superintending architect, to alter or modify the plans and this specification in any particular, and the architect shall be at liberty to make any deviation in the construction, detail or execution without in either case invalidating or rendering void .the contract, and in case any such alteration shall increase or diminish the cost of doing the work, the amount to be allowed to the contractor or owner shall be such as may be equitable and just.”

We think it is clear that the above provision has reference only to changes in the plans and specifications, and has no application to the provisions of the contract prescribing the mode and manner of the payment of the consideration. This assignment is overruled.

Under its second and third propositions, the city contends, in effect, that, having paid the full contract price, except $1,224.26, to the contractors or upon their order, without any notice of unpaid claims, and without any notice that the retainage provided for by the contract had been assigned to other parties, its only liability was for said $1,224.26. The appellant surety company also contends that, by reason of the city and contractors changing the method of payment without its knowledge or consent, it was released from its bond, not only as to tbe city, but also as to appel-lees, and that no judgment should have been rendered against it in favor of appellees for labor performed and material furnished. We will consider these contentions of both appellants together. The trial court filed findings of fact and conclusions of law, which are in no way challenged by either side. The material parts of such findings are, in substance, as follows: On November 16,1926, Gregory & Hope and the city of Groesbeck entered into a contract for the erection of a city hall for the consideration, as recited in said contract, of $32,253. A bond was given to the city by said contractors, bearing the same date, in the sum of $32,253, guaranteeing the performance of said contract, upon which the .¡Etna Casualty & Surety Company was a surety. One of the conditions of said bond was that said contractors would pay all indebtedness that might be incurred by the contractors in carrying out said contract, as well as all costs, including 15 per cent, attorney’s fees, in enforcing the payment of all sucli indebtedness.

The bond provided, further, that the same was made for the use and benefit of all persons who might become entitled to liens under said contract according to the provisions of law in such eases made and provided, and might be sued upon by them as if executed to them in proper person. Extras agreed to by the city and the contractors under the provisions of the contract amounted to $1,579.07; thus increasing the contract price to $33,-832.07. Payments were to be made as the work progresses as follows:

“The superintendent selected by the city shall each week make an estimate of the amount of work and material placed on the ground during said week and furnish a copy ■ of the same to the contractor, and the city shall pay 80 per cent, of said estimates, retaining 20 per cent, of the same, which said retainage shall be held by the city until the final completion and acceptance of said building as hereinafter provided, at which time all retainage then so held by the city and not otherwise disposed of under the terms and conditions of this contract shall be paid to the contractors.”

The last of May, 1926, the contractors abandoned the contract; the building then being virtually completed. C. H. Foote, engineer for the city, finished the job at a cost of $264.49. During the progress of the work, and up to the time of the abandonment of the contract'by the contractors, the city had paid to them, upon estimates furnished by its superintendent, the sum of $29,318.51. The city had also paid the Citizens’ National Bank, upon an order of the contractors, the sum of $2,006.66, same being money which the bank had loaned the contractors, making a total amount paid to the contractors and' on their order of $31,325.17. After the abandonment of the contract by the contractors, in addition to the sum of $264.49 paid out by the city in completion of the work, said city also paid $278 for a vault door, and also two small judgments against the city for material furnished for said work, one for $406.80 and the other for $235.60, or a total thus paid by the city of $1,184.89. Eighty per cent, of the contract price of $33,882.07 was $27,065.60, so all sums paid by the city to the contractors or on their order in excess of said $27,065.60 were paid out of the 20 per cent, retainage, which, under the provisions of the contract, was to be held by the city until the final completion and acceptance of the work by the city.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Michael Ignasiak v. State
Court of Appeals of Texas, 1997
Commercial Union Ins. Co. v. Spaw-Glass Corp., Inc.
877 S.W.2d 538 (Court of Appeals of Texas, 1994)
Threlkeld-Covington, Inc. v. Baker Drywall Co.
837 S.W.2d 840 (Court of Appeals of Texas, 1992)
Corpus Christi Bank and Trust v. Smith
525 S.W.2d 501 (Texas Supreme Court, 1975)
Friendswood Independent School District v. National Surety Corp.
423 S.W.2d 95 (Court of Appeals of Texas, 1967)
Old Colony Insurance Company v. City of Quitman
352 S.W.2d 452 (Texas Supreme Court, 1961)
Graybar Electric Co. v. Manufacturers Casualty Co.
122 A.2d 624 (Supreme Court of New Jersey, 1956)
Knutson v. Metallic Slab Form Co.
130 F.2d 200 (Fifth Circuit, 1942)
Fidelity Union Casualty Co. v. State
54 S.W.2d 1079 (Court of Appeals of Texas, 1932)
Ætna Casualty & Surety Co. v. Russell
24 S.W.2d 385 (Texas Commission of Appeals, 1930)

Cite This Page — Counsel Stack

Bluebook (online)
3 S.W.2d 895, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aetna-casualty-surety-co-v-robertson-lumber-co-texapp-1928.