Commercial Union Ins. Co. v. Spaw-Glass Corp., Inc.

877 S.W.2d 538, 1994 WL 245861
CourtCourt of Appeals of Texas
DecidedJuly 6, 1994
Docket3-93-517-CV
StatusPublished
Cited by9 cases

This text of 877 S.W.2d 538 (Commercial Union Ins. Co. v. Spaw-Glass Corp., Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Commercial Union Ins. Co. v. Spaw-Glass Corp., Inc., 877 S.W.2d 538, 1994 WL 245861 (Tex. Ct. App. 1994).

Opinion

BEA ANN SMITH, Justice.

Appellee Spaw-Glass Corporation, Inc. contracted with Judson Independent School District to complete construction of Judson High School in San Antonio. Appellant Commercial Union Insurance Company was the surety for Kleck Plumbing HVAC, a subcontractor on the project whose default left certain suppliers unpaid. To mitigate damages under its performance and payment bonds, Commercial Union funded Kleck’s remaining obligations under its contract. Commercial Union expected to recover these expenditures from the ten percent retainage Spaw-Glass was required to withhold from Kleck under their contract. Spaw-Glass, however, released substantial portions of Kleck’s retention upon completion of the first phase of the project, making the final payment from retention after completion of the second phase approximately $100,000 less than the obligations Commercial Union had funded.

Commercial Union sued Spaw-Glass, claiming to be a third-party beneficiary of the contract between Spaw-Glass and Kleck. Commercial Union claimed that Spaw-Glass’ breach of its contractual obligation to retain ten percent of the total contract price until final completion of the project caused Commercial Union to sustain $100,000 in damages. The ease was submitted to the court on an agreed statement of facts. The trial court held that Commercial Union had no legal or equitable claim against Spaw-Glass. We will affirm the trial court’s judgment.

BACKGROUND

The agreed statement of facts reflects that Spaw-Glass contracted to complete construction of the high school in March 1987; later that month it signed a contract with Kleck, as a subcontractor, for work totalling $1,188,-814. Under the subcontract, Spaw-Glass was required to retain ten percent of the payments due Kleck until completion of the project. A second phase of the project was added in July 1987. Rather than execute a new contract, which would have required the school district to conduct a bidding process, the parties executed a change order to cover the addition. The addition increased the value of Kleck’s work under the contract to $1,843,585. In exchange for executing the change order, the school district agreed to release to Spaw-Glass retainage for the original phase of the project before completion of the second phase. Spaw-Glass in turn released retainage from the first phase to subcontractors who were performing adequately. Kleck received retention payments of $70,-883.90 on October 9, 1987, and $66,833.90 on November 5, 1987. On September 22, 1988, Kleck signed a certification that all suppliers had been paid; on September 29, 1988, it signed a final release and received the final retention payment. At this time Spaw-Glass was unaware that Kleck had unpaid obligations on the project and Commercial Union was unaware of the earlier retention payments. The final retention payment due Kleck was only $43,210.23, approximately $100,000 less than the obligations funded by Commercial Union. Disappointed that it could not recover its expenditures from Kleck’s retention, Commercial Union sued Spaw-Glass in July 1989, seeking to recover its damages as a third-party beneficiary of the subcontract.

*540 DISCUSSION

Standard of Review

When a case is submitted to the trial court on an agreed statement of facts, the judgment will be upheld on appeal if it can be sustained on any legal theory supported by the evidence. WesTech Eng’g, Inc. v. Clearwater Constructors, Inc., 835 S.W.2d 190, 196 (Tex.App.—Austin 1992, no writ).

The McGregor Act

In its third point of error, Commercial Union attacks the trial court’s holding that this action is governed by the McGregor Act. See Act of May 20, 1977, 65th Leg., R.S., ch. 809, § 1, art. 5160(A), 1977 Tex.Gen. Laws 2027, 2027 (Tex.Rev.Civ.Stat.Ann. art. 5160, since amended and repealed) (“Article 5160”). We will address this contention first, as it affects our review of the other points of error. The McGregor Act provides a comprehensive and exclusive statutory scheme requiring prime contractors on public projects exceeding $25,000 in cost to purchase both a performance bond to protect the public entity owning the project and a payment bond to protect suppliers of labor or materials. Article 5160 A. There is no dispute that the Act governs unpaid claims of suppliers brought against the prime contractor and its surety. Commercial Union argues that the McGregor Act does not govern claims of a subcontractor’s surety brought against the contractor, and hence its provisions are irrelevant to this suit on a contract. We note that the trial court did not hold v that the McGregor Act governs Commercial Union’s claim. Rather, the trial court held that Kleck’s suppliers were required to give notice of their unpaid bills to Spaw-Glass and that they failed to do so. We will uphold the trial court’s decision that the notice provisions of the McGregor Act governed the claims of Kleek’s suppliers.

The McGregor Act requires unpaid claimants to give timely notice of their unpaid claims to the prime contractor. Article 5160 B(a). Kleck’s unpaid suppliers did not give Spaw-Glass the statutorily required notice. The provisions of the Act must be strictly complied with if there is to be recovery from a payment bond; furthermore, the Act provides the exclusive remedy for laborers or suppliers on a public project. Bunch Elec. Co. v. Tex-Craft Builders, Inc., 480 S.W.2d 42, 45 (Tex.Civ.App.—Tyler 1972, no writ). If Spaw-Glass had no liability to the unpaid suppliers because they failed to give notice, Commercial Union had no obligation under the payment bond to the unpaid suppliers. Spaw-Glass thus argues that Commercial Union voluntarily paid the suppliers who did not comply with the exclusive statutory scheme for asserting their unpaid claims against, the prime contractor.

The statute refers to “claimants who do not have a direct contractual relationship with the prime contractor.” Article 5160 B(b). The Act defines a claimant as “anyone having direct contractual relationship with the Prime Cdntractor, or with a subcontractor, to perform the work or a part of the work, or to furnish labor or materials or both.” Article 5160 C. The Act requires that a claimant give notice to the contractor; in fact, the Act requires both notice of unpaid claims and notice of any retainage agreement between a subcontractor and a supplier. The purpose of these notices is to protect the prime contractor from incurring double liability. Before the 1959 amendments adding notice provisions to the statute, a contractor might pay a subcontractor in full, “only to find subsequently that a claim had been filed with the County Clerk by a person or persons who had dealt only with the subcontractor. Thus the prime contractor or his surety would have to pay the same debt twice.” Keetch Metal Works of Dallas, Inc. v. Yates, 378 S.W.2d 122, 124 (Tex.Civ.App.—Dallas 1964, no writ). To correct this problem, the legislature amended the statute to remove the contractor’s liability for claims not asserted before retainage is paid in full. Article 5160 B(b), (c).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
877 S.W.2d 538, 1994 WL 245861, Counsel Stack Legal Research, https://law.counselstack.com/opinion/commercial-union-ins-co-v-spaw-glass-corp-inc-texapp-1994.