Scoggins Construction Co. v. Dealers Electrical Supply Co.

292 S.W.3d 685, 2007 WL 4442544
CourtCourt of Appeals of Texas
DecidedFebruary 28, 2008
Docket13-06-368-CV
StatusPublished
Cited by2 cases

This text of 292 S.W.3d 685 (Scoggins Construction Co. v. Dealers Electrical Supply Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Scoggins Construction Co. v. Dealers Electrical Supply Co., 292 S.W.3d 685, 2007 WL 4442544 (Tex. Ct. App. 2008).

Opinion

MEMORANDUM OPINION

Memorandum Opinion by

Justice GARZA.

This appeal is taken from a judgment entered in favor of appellee, Dealers Electrical Supply Company (“Dealers”), against appellants, Scoggins Construction Company, Inc. and Bill R. Scoggins, President of Scoggins Construction Company, Inc. (jointly “SCC”). By four issues, SCC contends that the judgment rendered by the trial court should be reversed because: (1) pursuant to section 2253.073 of the Texas Government Code, the McGregor Act was Dealers’s mandatory and exclusive remedy against appellants; thus, because appellee failed to sue under the McGregor Act, the trial court’s judgment should be reversed; 1 (2) there was no evidence, or alternatively insufficient evidence, to support a judgment that appellants violated the “joint check” agreement; (3) there was no evi *687 dence, or alternatively insufficient evidence, to find Bill R. Scoggins personally liable for the debt in question; and (4) there was no evidence, or alternatively insufficient evidence, to support a Texas Construction Trust Fund Act (“Trust Fund Act”) violation, and Dealers failed to refute the affirmative defenses afforded by the Trust Fund Act. 2 See Tex. Gov’t Code Ann. § 2253.073 (Vernon 2000); Tex. Prop. Code Ann. § 162.001-.004, § 162.031-.033 (Vernon 2007). We reverse the judgment of the trial court and render judgment in favor of appellants.

1. Factual and Procedural Background

SCC was hired as the general contractor under a public work contract with the Mercedes Independent School District (“M.I.S.D.”) to build the Ruben Hinojosa Elementary School in Mercedes, Texas. In accordance with the McGregor Act, SCC executed performance and payment bonds with Colonial American Casualty and Surety Company (“Colonial”) and Fidelity and Deposit Company of Maryland (“Fidelity”) for the full contract amount of $5,751,000. See Tex. Gov’t Code Ann. § 2253.021(a)(1), (2) (Vernon Supp. 2006). SCC hired Arturo Bujanos d/b/a Diamond Industries (“Diamond”) as the electrical subcontractor for the project. Dealers served as the supplier of the electrical component parts used in the project.

Subsequently, SCC, Diamond, and Dealers entered into a “joint check” agreement in an effort to arrange for Dealers to extend credit to Diamond. The record reflects that the “joint check” agreement required SCC to issue joint checks to Diamond for labor supplied and to Dealers for materials supplied when Diamond completed its work and submitted a draw. 3 The underlying dispute arose in May 2002, when Diamond failed to complete its electrical subcontract with SCC.

SCC claims that Diamond walked off the elementary school project and absconded with materials that were to be incorporated in the elementary school project. According to SCC, Diamond failed to install numerous electrical materials which had been paid for through Diamond’s construction draw requests, and M.I.S.D. did not accept much of Diamond’s electrical work. SCC claims that it paid $107,440.27 to Borchers Electric to complete the electrical work on the elementary school project, $34,640.00 to Ace Fire and Sound to complete the alarm system — both tasks were part of Diamond’s subcontract with SCC, and $8,500 for legal fees in the suit against Diamond for the materials not installed in *688 the elementary school project. In March 2003, Dealers sent notice to SCC demanding payment for $78,123.59 in supplies provided to Diamond for the elementary school project. Stacey Scoggins, an employee of SCC, testified that it refused to pay because the items were never incorporated into the school project and because Diamond did not complete the project to the satisfaction of M.I.S.D.

On June 10, 2003, Dealers filed suit against SCC and its officers, directors, and principals, Diamond, Colonial, and Fidelity, alleging violations of the McGregor Act, the Trust Fund Act, and chapter 53 of the Texas Property Code. On May 25, 2005, the trial court entered an agreed interlocutory judgment in favor of Dealers against Diamond for the principal amount due of $78,123.59. Diamond is not a party to this appeal. 4 On September 20, 2005, the trial court signed an order of partial nonsuit with respect to the sureties, Colonial and Fidelity. Immediately thereafter, Dealers dropped its McGregor Act claims and its claims associated with chapter 53 of the Texas Property Code. Dealers subsequently amended its original petition to allege solely violations of the Trust Fund Act and the “joint check” agreement as grounds for recovery. Dealers sought to recover the principal amount owed of $78,123.59 from appellants for materials furnished in the construction of the elementary school.

On November 16, 2005, the trial court conducted a bench trial on Dealers’s claims against appellants. SCC filed a special exception with the trial court requesting the court to strike Dealers’s Trust Fund Act claim and declare that the McGregor Act was Dealers’s exclusive remedy. In support of its special exception, SCC argued that case law supported its contention that the McGregor Act was Dealers’s exclusive remedy. SCC further argued that Dealers failed to comply with the notice requirements of the McGregor Act, which required Dealers to provide SCC, Colonial, and Fidelity with notice of a suit upon the payment bond by the “fifteenth day of the third month after each month in which any of the claimed labor was performed or any of the claimed material was delivered.” See id. § 2253.041(a), (b) (Vernon 2000). However, the trial court denied SCC’s special exception without explanation.

The trial court entered findings of fact and conclusions of law on April 3, 2006. On April 4, 2006, the trial court signed a final judgment in favor of Dealers against SCC. The trial court awarded Dealers $135,910.08 in damages. The damage award consisted of the principal amount due of $78,123.59, plus six percent (6%) prejudgment interest set to accrue from 31 days after the last unpaid invoice, specifically from May 16, 2002 until March 1, 2006, in the amount of $17,786.49. The trial court also awarded reasonable and necessary attorney’s fees in the amount of $40,000 and court costs. SCC filed a motion for new trial on April 19, 2006. The trial court set a hearing date of May 31, 2006, for the motion for new trial. However, the record does not reflect that the *689 hearing was ever held. Further, the record does not show that the trial court ruled on SCO’s motion for a new trial. The motion, therefore, was overruled by operation of law. Tex.R.App. P. 33.1(b). This appeal ensued.

II. Analysis

In its first issue, SCC contends that the McGregor Act was Dealers’s exclusive remedy for this action and because Dealers failed to sue under the McGregor Act, Dealers should take nothing.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
292 S.W.3d 685, 2007 WL 4442544, Counsel Stack Legal Research, https://law.counselstack.com/opinion/scoggins-construction-co-v-dealers-electrical-supply-co-texapp-2008.