Suretec Insurance Co. v. Myrex Industries

232 S.W.3d 811, 2007 Tex. App. LEXIS 6460, 2007 WL 2324330
Court of Appeals of Texas·Decided August 16, 2007·No. 09-06-433 CV·Published·Cited by 12 cases

Opinion

OPINION

CHARLES KREGER, Justice.

SureTec Insurance Company (“Sure-Tec”) appeals the trial court’s order denying SureTec’s cross-motion for summary judgment and granting summary judgment in favor of appellee Myrex Industries (“Myrex”) in a suit to recover on a payment bond. See Tex. Gov’t Code Ann. § 2253.073 (Vernon 2000). We reverse and render.

We review a summary judgment de novo. Valence Operating Co. v. Dorsett, 164 S.W.3d 656, 661 (Tex.2005); Provident Life & Accident Ins. Co. v. Knott, 128 S.W.3d 211, 215 (Tex.2003). When, as here, both parties move for summary judgment and the trial court grants one motion and denies the other, we review the summary judgment evidence presented by both sides, determine all questions presented, and render the judgment the trial court should have rendered. Tex. Workers’ Comp. Comm’n v. Patient Advocates of Tex., 136 S.W.3d 643, 648 (Tex.2004).

Myrex, a subcontractor, contracted with Proficient Construction Services, Ltd. (“Proficient”), the general contractor for the construction of the Ben Rogers Regional Visitors Information Center in Beaumont, Texas. Myrex agreed to manufacture and deliver specially fabricated “structural, joist and deck and miscellaneous steel” for the project. Myrex contends it performed its obligations under the contract, but that Proficient still owed Myrex money under the contract. Myrex brought a claim against SureTec, as surety on the payment bond, for failure to pay on the bond, and filed a suit on a sworn account and breach of contract action against Proficient. Myrex’s notice of claim letter to SureTec was dated May 15, 2005, and mailed on May 16, 2005. Myrex moved for summary judgment against both SureTec and Proficient. SureTec filed a cross-motion for summary judgment against Myrex. The trial court granted Myrex’s motion for summary judgment and denied SureTec’s cross-motion for summary judgment. The trial court held Proficient and SureTec jointly and severally liable, and awarded Myrex damages.

In its sole issue on appeal, SureTec contends the trial court erred in denying SureTec’s motion for summary judgment and granting Myrex’s motion for summary *813 judgment because Myrex failed to provide timely notice of its claim pursuant to Chapter 2253 of the Texas Government Code (the “McGregor Act”).

The legislature enacted the McGre-gor Act, which requires contractors to secure a bond to ensure payment, because a subcontractor or supplier may not place a lien against a public budding. See Featherlite Bldg. Prods. Corp. v. Constructors Unlimited, Inc., 714 S.W.2d 68, 69 (Tex.App.-Houston [14th Dist.] 1986, writ ref d n.r.e.). The McGregor Act allows for the subcontractor or supplier to sue the contractor and its surety for any unpaid balance for work or materials provided and reasonable attorney fees. See Tex. Gov’t Code § 2253.073. Pursuant to section 2253.041 of the McGregor Act, a subcontractor or supplier must provide the contractor and its surety notice of its claim:

(a) To recover in a suit under Section 2253.073 on a payment bond for a claim for payment for public work labor performed or public work material delivered, a payment bond beneficiary must mail to the prime contractor and the surety written notice of the claim.
(b) The notice must be mailed on or before the 15th day of the third month after each month in which any of the claimed labor was performed or any of the claimed material was delivered.

Id. § 2253.041(a),(b) (Vernon 2000).

We must decide whether the Code Construction Act applies to section 2253.041(b) of the Texas Government Code. SureTec argues that section 2253.041(b) required Myrex to mail its notice on or before Sunday, May 15, 2005, which was the 15th day of the third month after the month in which the claimed labor was performed or material delivered. My-rex contends section 311.014 of the Code Construction Act applies and extends section 2253.041’s deadline for filing a notice of claim. Section 311.014 provides the following:

§ 311.014. Computation of Time

(a) In computing a period of days, the first day is excluded and the last day is included.
(b) If the last day of any period is a Saturday, Sunday, or legal holiday, the period is extended to include the next day that is not a Saturday, Sunday, or legal holiday.
(c) If a number of months is to be computed by counting the months from a particular day, the period ends on the same numerical day in the concluding month as the day of the month from which the computation is begun, unless there are not that many days in the concluding month, in which case the period ends on the last day of that month.

Tex. Gov’t Code Ann. § 311.014 (Vernon 2005). Myrex maintains that because May 15, 2005, fell on a Sunday, section 311.014(b) allowed Myrex to mail the notice on Monday, May 16, 2005. SureTec asserts the Code Construction Act does not apply to section 2253.041(b) of the Texas Government Code.

Free access — add to your briefcase to read the full text and ask questions with AI

Suretec Insurance Co. v. Myrex Industries, 232 S.W.3d 811, 2007 Tex. App. LEXIS 6460, 2007 WL 2324330 (Tex. Ct. App. 2007).

232 S.W.3d 811 (Suretec Insurance Co. v. Myrex Industries) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related