Bond Restoration, Inc. v. Ready Cable, Inc.

462 S.W.3d 597, 2015 Tex. App. LEXIS 3904, 2015 WL 1743605
CourtCourt of Appeals of Texas
DecidedApril 16, 2015
Docket07-14-00056-CV
StatusPublished
Cited by2 cases

This text of 462 S.W.3d 597 (Bond Restoration, Inc. v. Ready Cable, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bond Restoration, Inc. v. Ready Cable, Inc., 462 S.W.3d 597, 2015 Tex. App. LEXIS 3904, 2015 WL 1743605 (Tex. Ct. App. 2015).

Opinion

OPINION

Brian Quinn, Chief Justice

Bond Restoration, Inc. (Bond) appeals from a final judgment awarding Ready Cable, Inc. (Ready) damages related to the cost of materials purportedly used in a public works project. The two issues before us involve whether Ready proved that the materials were delivered to or used by Bond and whether the trial court’s award of consequential damages comported with Chapter 2253 of the Government Code (that is, the McGregor Act). We reverse.

Background

In 2012 and 2013, E.P. Reyes & Sons purchased supplies from Ready purportedly for use in a street improvement project undertaken by the City of Houston. Bond allegedly was the prime contractor for the project. Reyes did not pay for the materials. This resulted in Ready requesting from Bond information regarding the payment bond securing payment for the project. Bond did not respond. Thereafter, Ready sought similar information from the City of Houston. The latter answered by informing Ready that it was “unable to identify the City of Houston project or vendor” and to furnish “more information, including the complete City of Houston project name and project number.” (Emphasis in original). Ready had no project name or number.

Eventually, the deadline to submit a claim against the bond, if any, lapsed. So, Ready sued Reyes for breach of contract and Bond under § 2253.024 of the Texas Government Code “for failure to provide bond information as required by” that statute. A default judgment was entered against Reyes for the sum due Ready. After conducting a bench trial, the trial court entered judgment against Bond for consequential damages or an amount equal to the unpaid invoices that would have been paid had Bond timely provided the requisite bond information.

The McGregor Act or Texas Government Code § 2253.001 et seq.

Before addressing the issues before us, we briefly mention the provisions of the McGregor Act (the Act) relevant here. The first is § 2253.024. It states:

(a) A prime contractor, on the written request of a person who provides public work labor or material ... shall provide to the person
(1) the name and last known address of the governmental entity with whom the prime contractor contracted for the public work;
(2) a copy of the payment and performance bonds for the public work, including bonds furnished by or to the prime contractor; and
(3) the name of the surety issuing the payment bond and the performance bond and the toll-free telephone number maintained by the Texas Department of Insurance under Sub-chapter B, Chapter 521, Insurance Code, for obtaining information concerning licensed insurance companies.

Tex. Gov’t Code Ann. § 2253.024(a)(1), (2), & (3) (West 2008). “Public work material” is defined as “material used, or ordered and delivered for use, directly to carry out a public work; [or] ... specially fabricated material; [or] ... reasonable rental and actual running repair costs for construction equipment used, or reasonably required and delivered for use, directly to carry out work at the project site; or ... *600 power, water, fuel, and lubricants used, or ordered and delivered for use, directly to carry out a public work.” Id. § 2253.001(6). In turn, “public work labor” is “labor used directly to carry out a public work.” Id. § 2253.001(5).

Next, the statutory obligation imposed on a prime contractor under the Act to secure a payment bond arises when the contract between the prime contractor and municipality exceeds $50,000. Id. § 2253.021(a)(2)(B) (West Supp.2014). Per statute, the payment bond is “solely for the protection and use of payment bond beneficiaries who have a direct contractual relationship with the prime contractor or a subcontractor to supply public work labor or material....” Id. § 2253.021(c)(1). Finally, a subcontractor is “a person, firm, or corporation that provides public work labor or material to fulfill an obligation to a prime contractor or to a subcontractor for the performance and installation of any of the work required by a public work contract.” Id. § 2253.001(9).

Application of § 2253.001 etseq.

We address Bond’s initial contention. Through it, the company posits that “actual proof of delivery at the project site or consumption of the materials in the work is required for a material supplier to be entitled to establish a valid bond claim on a public works project,” and that “proof of neither exists.” In other words, Bond argues that the evidence is legally insufficient to satisfy an element of Ready’s claim, that element being the provision of material used or ordered and delivered for use in a public work.

As explained in Ford Motor Co. v. Castillo, 444 S.W.3d 616 (Tex.2014), a legal insufficiency challenge will be upheld if the record illustrates either 1) a complete absence of a vital fact, 2) the court is barred by rules of law or of evidence from giving weight to the only evidence offered to prove a vital fact, 3) the evidence offered to prove a vital fact is no more than a mere scintilla, or 4) the evidence conclusively establishes the opposite of the vital fact. Id. at 620. Furthermore, we view the evidence in the light most favorable to the verdict and assume that the fact finder made all inferences in favor of its decision if reasonable minds could. Id. at 620-21. In viewing circumstantial evidence favoring the decision, we must “ ‘view each piece of circumstantial evidence, not in isolation, but in light of all the known circumstances,’ ” id. quoting City of Keller v. Wilson, 168 S.W.3d 802 (Tex.2005), and when that evidence “is equally consistent with either of two facts, then neither fact may be inferred.” Id. However, if not so “equally consistent with either of two facts, and the inference drawn by the jury is within the ‘zone of reasonable disagreement,’ a reviewing court cannot substitute its judgment for that of the trier-of-fact.” Id. at 621, quoting City of Keller v. Wilson, 168 S.W.3d 802 (Tex.2005). With this said, we turn to the record before us.

Bond cites us to authority holding that the claimant in a public works project must show that “the materials furnished were actually used on the job ... and that same were consumed or wholly depreciated in the process of the construction work.” John F. Buckner & Sons v. Arkansas Fuel Oil Corp., 301 S.W.2d 325, 327 (Tex.Civ.App.-Waco 1957, no writ); accord Sheldon Pollack Corp v. Pioneer Concrete of Texas. Inc., 765 S.W.2d 843, 846 (Tex.App.-Dallas 1989, writ denied) (noting the same); National Surety Corp. v. Dabney,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
462 S.W.3d 597, 2015 Tex. App. LEXIS 3904, 2015 WL 1743605, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bond-restoration-inc-v-ready-cable-inc-texapp-2015.