Sims v. William S. Baker, Inc.

568 S.W.2d 725, 1978 Tex. App. LEXIS 3551
CourtCourt of Appeals of Texas
DecidedJuly 5, 1978
Docket8549
StatusPublished
Cited by12 cases

This text of 568 S.W.2d 725 (Sims v. William S. Baker, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sims v. William S. Baker, Inc., 568 S.W.2d 725, 1978 Tex. App. LEXIS 3551 (Tex. Ct. App. 1978).

Opinion

ODEN, Justice.

The primary question to be resolved on appeal is whether or not the notice of claim served by James D. Sims, d/b/a Simtex Industries, appellant, on William S. Baker, Inc., and Transamerica Insurance Company, appellees, is sufficient to comply with the notice requirements of the McGregor Act. Tex.Rev.Civ.Stat.Ann. art. 5160. Appellant and appellees will be respectively referred to as Sims, Baker and Transamerica.

Sims is a sheet metal and duct subcontractor. Baker is a general contractor and on August 18, 1975, it entered into a contract with the City of Carrollton to remodel and make certain additions to the Carroll-ton Library and Recreational Center. The consideration to be paid under the construction contract was in excess of $25,000.00, and Baker was therefore required by the McGregor Act to execute performance and payment bonds. Transamerica was the surety on the statutory performance and payment bonds executed by Baker. On September 23, 1975, Baker subcontracted the plumbing, heating, ventilation and air conditioning portions of the construction contract to Dallas North Mechanical, Inc., who in turn entered into an agreement with Sims to perform the sheet metal and duct work required thereunder for $10,070.00. Sims substantially performed his obligations under the subcontract during the *728 months of January, February, March and April of 1976; however, Dallas North Mechanical, Inc., though often requested, failed to remit payment, whereupon Sims served written notices of his claim by certified mail on Baker and Transamerica. The claim remained unpaid for at least 60 days at which time Sims instituted suit for the amount alleged due on the subcontract, plus reasonable attorney’s fees, against Baker and Transamerica on the payment bond and Dallas North Mechanical, Inc., on the subcontract. The case was tried before the court without a jury. Judgment was entered that Sims take nothing on his claims against Baker and Transamerica. Sims was awarded judgment against Dallas North Mechanical, Inc., for $9,209.26 plus interest, and reasonable attorney’s fees in the amount of $3,000.00. The parties to the appeal agree that the notice of claim was timely served for labor performed and materials furnished during the months of February, March and April, 1976. They likewise agree that the notice is not timely to perfect a claim for monies due during January, 1976. The primary disputed issue will be resolved by our determination of whether or not the notice of claim was sufficient to comply with the notice requirements contained in part B of the McGregor Act.

The provisions of the McGregor Act which are pertinent to the appeal are, with emphasis added:

“B. Every claimant who has furnished labor or material in the prosecution of the work provided for in such contract in which a Payment Bond is furnished as required hereinabove, and who has not been paid in full therefor, shall have the right, if his claim remains unpaid after the expiration of sixty (60) days after the filing of the claim as herein required, to sue the principal and the surety or sureties on the Payment Bond jointly or severally for the amount due on the balance thereof unpaid at the time of filing the claim or of the institution of the suit plus reasonable attorneys’ fees; provided:
“(a) Notices Required for Unpaid Bills, other than notices solely for Retainages as hereinafter described.
“Such claimant shall have given within ninety (90) days after the 10th day of the month next following each month in which the labor was done or performed, in whole or in part, or material was delivered, in whole or in part, for which such claim ⅛ made, written notices of the claim i)y certified or registered mail, addressed to the prime contractor at his last known business address, or at his residence, and to the surety or sureties. Such notices shall be accompanied by a sworn statement of account stating in substance that the amount claimed is just and correct and that all just and lawful offsets, payments, and credits known to the affiant have been allowed. Such statement of account shall include therein the amount of any retainage or retainag-es applicable to the account that have not become due by virtue of terms of the contract between the claimant and the prime contractor or between the claimant and a subcontractor. When the claim is based on a written agreement, the claimant shall have the option to enclose, with the sworn statement of account, as such notice a true copy of such agreement and advising completion or value of partial completion of same.
“(1) When no written contract or written agreement exists between the claimant and the prime contractor or between the claimant and a subcontractor, except as provided in subparagraph B(a)(2) hereof, such notices shall state the name of the party for whom the labor was done or performed or to whom the material was delivered, and the approximate dates of performance and delivery, and describing the labor or materials or both in such a manner so as to reasonably identify the said labor or materials or both and amount due therefor. The claimant shall generally itemize his claim and shall accompany same with true copies of documents, invoices or orders sufficient to reasonably identify the labor performed or material delivered for which claim is being made. Such documents and copies thereof shall have thereon a reasonable *729 identification or description of the job and destination of delivery.
“(2) When the claim is for multiple items of labor or material or both to be paid for on a lump sum basis such notice shall state the name of the party for whom the labor was done or performed or to whom the material was delivered, the amount of the contract and whether written or oral, the amount claimed and the approximate date or dates of performance or delivery or both and describing the labor or materials or both in such a manner as to reasonably identify the said labor or materials.”

The parties to the appeal briefed the case on the assumption that the information to be contained in the notice to be served is that prescribed by subparagraph B(a)(l) of the McGregor Act. We do not agree. Subparagraph B(a)(l) relates specifically to content of the notices required of claimants where no written contract exists, and which does not involve a claim for multiple items to be paid for on a lump sum basis. United Benefit F. Ins. Co. v. Metropolitan Plumbing Co., 363 S.W.2d 843 (Tex.Civ.App. El Paso 1962, no writ). This Court disagrees with the statement contained in the United Benefit F. Ins. Co. v. Metropolitan Plumbing Co., supra, that, “Subpara-graph (2), subd. (a) of part B relates specifically to the content of notices required of claimants in direct contractual relation with the prime contractor . . .”. In our opinion subparagraph B(a)(2) of the McGre-gor Act prescribes the information to be contained in all notices given which involve a claim for multiple items of labor or material or both to be paid for on a lump sum basis irrespective of whether the claimant has a direct contractual relationship with the prime contractor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

SureTec Insurance Company v. Myrex Industries
Court of Appeals of Texas, 2007
Suretec Insurance Co. v. Myrex Industries
232 S.W.3d 811 (Court of Appeals of Texas, 2007)
Redland Insurance Co. v. Southwest Stainless, L.P.
181 S.W.3d 509 (Court of Appeals of Texas, 2005)
Ramex Construction Co. v. Tamcon Services Inc.
29 S.W.3d 135 (Court of Appeals of Texas, 2000)
Chilton Insurance Co. v. Pate & Pate Enterprises, Inc.
930 S.W.2d 877 (Court of Appeals of Texas, 1996)
Argee Corp. v. Solis
932 S.W.2d 39 (Court of Appeals of Texas, 1995)
S.A. Maxwell Co. v. R.C. Small & Associates, Inc.
873 S.W.2d 447 (Court of Appeals of Texas, 1994)
Featherlite Building Products Corp. v. Constructors Unlimited, Inc.
714 S.W.2d 68 (Court of Appeals of Texas, 1986)
Wm. S. Baker, Inc. v. Sims
589 S.W.2d 492 (Court of Appeals of Texas, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
568 S.W.2d 725, 1978 Tex. App. LEXIS 3551, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sims-v-william-s-baker-inc-texapp-1978.