United Benefit Fire Insurance Co. v. Metropolitan Plumbing Co.

363 S.W.2d 843, 1962 Tex. App. LEXIS 2076
CourtCourt of Appeals of Texas
DecidedDecember 19, 1962
Docket5563
StatusPublished
Cited by31 cases

This text of 363 S.W.2d 843 (United Benefit Fire Insurance Co. v. Metropolitan Plumbing Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United Benefit Fire Insurance Co. v. Metropolitan Plumbing Co., 363 S.W.2d 843, 1962 Tex. App. LEXIS 2076 (Tex. Ct. App. 1962).

Opinion

LANGDON, Chief Justice.

Appellee, Metropolitan Plumbing Company, was a subcontractor in the construction of an addition to the Cooley Elementary School for the El Paso Independent School District, El Paso County, Texas. The prime contractor in such work, D. W. Austin, d/b/a Austin Construction Company, became bankrupt while owing appel-lee a balance of $3,579.40 for labor and materials furnished the school job under the terms of a lump-sum contract. Appel-lee sued the contractor’s surety, United Benefit Fire Insurance Company, upon a payment bond executed by it as surety for D. W. Austin in compliance with the provisions of the McGregor Act (Article 5160, Vernon’s Annotated Texas Civil Statutes, as amended April 27, 1959). In a trial to the court without the interven *845 tion of a jury, judgment was awarded ap-pellee for the sum of $3,579.40, as prayed for, and appellant has appealed.

Appellant rests its appeal upon only three points of error, and contends that this case presents but a single question of law for the court to decide, that being whether or not the appellee fully complied with the “Notice” requirements of the statute when appellee undertook to inform appellant of the claim; or, to state the question another way — is substantial compliance with the statute sufficient?

On the other hand, appellee contends that he fully complied with the requirements of the statute; but if he did not, that appellant waived strict compliance therewith so as to preclude it from asserting discharge from liability under the bond.

For the purpose of clarity the appellant will hereafter be referred to as the defendant or surety, and the appellee as plaintiff.

It is the surety’s contention that the notice or notices of claim furnished it by plaintiff were insufficient, as a matter of law, to satisfy the strict requirements of the statute, and that plaintiff is thereby precluded from any recovery against defendant, as surety, on the payment bond executed by it in compliance with the statute.

The contract upon which the claim here is based was in writing and was for a lump-sum. It was a direct contract between plaintiff and the prime contractor and called for plaintiff to furnish the plumbing and mechanical work on the Cooley school. There is no dispute concerning the performance of the contract, nor of the amount thereon that remained unpaid. It is admitted that plaintiff, under date of February 28, 1961, did notify the surety by registered mail that the sum of $3,579.40 remained unpaid on the sub-contract; also, that at the instance of the surety plaintiff, under date of March 13, 1961, furnished the surety with a sworn notice of its claim. It is further admitted that a third notice of the claim was sent to the surety by plaintiff’s attorney under date of April 28, 1961, and that such notice was received by appellant about May 1, 1961.

Defendant-surety contends that each of the three notices was in some manner defective ; that the first notice was not sworn to; that the second notice did not contain the information requested by defendant and that none of the notices, including the third notice, contained a statement in the language of the statute to the effect that all just and lawful offsets known to plaintiff had been allowed; and further, that none of such notices contained any information showing how much labor or material was furnished by plaintiff month by month during the contract period.

We have been unable to find a case, in which the statute (Article 5160), as amended April 27, 1959, has been construed, and believe this case to be one of first impression. In view of such fact, we deem a more detailed analysis of the statute is required than might otherwise be necessary.

Under the McGregor Act prime contractors on contracts exceeding $2,000 for the construction, alteration or repair of any public buildings or the prosecution or completion of any public work for this state, any department, board or agency thereof; or any municipality of this state, department, board or agency thereof; or of any school district of this state; or of any other governmental or quasi-governmental authority authorized by law to enter into such public works contract, shall be required, before commencing work, to execute two statutory bonds to the governmental authority or authorities for whom the work is to be performed. The bonds required to be furnished are a “Performance Bond” in the amount of the contract conditioned upon the performance of the work, and a “Payment Bond”, also in the amount of the contract. The “Performance Bond” shall be solely for the protection of the governmental authority awarding the con *846 tract, and the “Payment Bond” solely for the protection of all claimants supplying labor and material in the prosecution of the work provided for in the contract, for the use of each such claimant.

The statute not only specifies the conditions of the bonds that shall be required of prime contractors on public works, but prescribes the time limits within which “notice” of claims thereon must be given, and specifies the form and content of the “Notice” required of the several classes of claimants for perfecting their respective claims against the contractor’s payment bond, for labor or material supplied by them in the prosecution of the contract work.

Part B, subdivision (a) of the statute pertains generally to all classes of claimants and specifies the time for filing notices of “Unpaid Bills, other than notices solely for Retainages * * *.” It provides that such notice shall be given within 90 days after the 10th day of the month next following each month in which the labor was done or performed or the material was delivered, for which such claim is made. . Notice of such claims shall be in writing and are required to be sent by certified or registered mail, addressed to the prime contractor at his last known business address, or at his residence, and to the surety or sureties. The statute requires that such notices shall be accompanied by the following:

1. Sworn statement of account stating in substance that the amount claimed is just and correct and that all just and lawful offsets, payments and credits known to affiant have been allowed.
2. Amount of any retainages.
3. If claim is based on a written contract, claimant may at his option enclose a true copy of such contract.
. 4. Advising completion or value of ■ partial completion.

Subparagraph (1) subd. (a) of part B relates specifically to content of the notices required of claimants where no written contract exists, and which does not involve a claim for multiple items to be paid for on a lump-sum basis. In such case the notice is required to contain the following'

1. Name of party for whom labor was done or to whom material was delivered.
2. Approximate dates of performance and delivery.
3. Description of labor or materials reasonably identified and generally itemized.
4. Amount due.
5.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

La Ash, Inc. v. Texas A&M University
Court of Appeals of Texas, 2008
Scoggins Construction Co. v. Dealers Electrical Supply Co.
292 S.W.3d 685 (Court of Appeals of Texas, 2008)
Argee Corp. v. Solis
932 S.W.2d 39 (Court of Appeals of Texas, 1995)
J.W.D., Inc. v. Federal Insurance Co.
806 S.W.2d 327 (Court of Appeals of Texas, 1991)
Missouri-Kansas-Texas Railroad v. Heritage Cablevision of Dallas, Inc.
783 S.W.2d 273 (Court of Appeals of Texas, 1989)
Pennzoil Co. v. Texaco Inc.
481 U.S. 1 (Supreme Court, 1987)
Baxter Construction Co. v. Hou-Tex Products, Inc.
718 S.W.2d 355 (Court of Appeals of Texas, 1986)
Featherlite Building Products Corp. v. Constructors Unlimited, Inc.
714 S.W.2d 68 (Court of Appeals of Texas, 1986)
Opinion No.
Texas Attorney General Reports, 1981
Sims v. William S. Baker, Inc.
568 S.W.2d 725 (Court of Appeals of Texas, 1978)
Trucker's, Inc. v. South Texas Construction Co.
561 S.W.2d 855 (Court of Appeals of Texas, 1977)
Yandell v. Tarrant State Bank
538 S.W.2d 684 (Court of Appeals of Texas, 1976)
Lesikar Construction Company v. Acoustex, Inc.
509 S.W.2d 877 (Court of Appeals of Texas, 1974)
Texarkana Construction Co. v. Alpine Construction Specialties, Inc.
489 S.W.2d 941 (Court of Appeals of Texas, 1972)
Bunch Electric Company v. Tex-Craft Builders, Inc.
480 S.W.2d 42 (Court of Appeals of Texas, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
363 S.W.2d 843, 1962 Tex. App. LEXIS 2076, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-benefit-fire-insurance-co-v-metropolitan-plumbing-co-texapp-1962.