Baxter Construction Co. v. Hou-Tex Products, Inc.

718 S.W.2d 355, 1986 Tex. App. LEXIS 8307
CourtCourt of Appeals of Texas
DecidedAugust 21, 1986
Docket01-85-0757-CV
StatusPublished
Cited by5 cases

This text of 718 S.W.2d 355 (Baxter Construction Co. v. Hou-Tex Products, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Baxter Construction Co. v. Hou-Tex Products, Inc., 718 S.W.2d 355, 1986 Tex. App. LEXIS 8307 (Tex. Ct. App. 1986).

Opinion

OPINION

DUGGAN, Justice.

This is an appeal from a summary judgment on a McGregor Act payment bond claim in favor of the plaintiff, a subcontractor-claimant on a public works project, in a suit against the project’s prime contractor and its surety.

The sole issue on appeal is whether the trial court correctly held the payment bond’s contractual 90-day notice provision for the filing of laborers’ and material-mens’ claims to be applicable, when Tex. Rev.Civ.Stat.Ann. art. 5160 (Vernon 1971) prescribes a lesser notice period. We hold that the trial court was correct, and we affirm the judgment.

Appellant, Baxter Construction Co., Inc. (“Baxter”), as prime contractor, was awarded a contract to construct a General Services Building on the campus of Texas Southern University in Houston. Baxter entered into a subcontract with Cinco Mechanical Systems, Inc. (“Cinco”), to provide mechanical work for the building; Cinco in turn subcontracted with the appellee, Hou-Tex Products, Inc., d/b/a Hou-Tex Sheet Metal (“Hou-Tex”), to provide certain duct work on the project.

As required by the provisions of Tex. Rev.Civ.Stat.Ann. art. 5160 A (Vernon Pamphlet 1986), appellant Baxter, as principal, and appellant Federal Insurance Co. (“Federal Insurance”), as surety, executed a labor and material payment bond which provided, in part, as follows:

[N]o suit or action shall be commenced hereunder by claimant unless claimant, other than one having a direct contract with the principal, shall have given written notice to any two of the following: the principal, the owner, or the surety above named, within ninety (90) days after such claimant did or performed the last of the work or labor, or furnished the last of the material for which said claim is made, stating with substantial accuracy the amount claimed and the name of the party for whom the work or labor was done or performed_ (Emphasis added).

Art. 5160 B(b)(2) requires that a payment bond claimant, other than one having a direct contractual relationship with the prime contractor, must provide written notice by certified or registered mail to the prime contractor within thirty-six (36) days after the tenth (10th) day of the month next following each month in which the labor was done or performed, in whole or in part, or material was delivered, in whole or in part, for which payment has not been received.

In addition to the foregoing notice, art. 5160 B(a) requires written notice and a sworn statement of account to the prime contractor and surety within ninety (90) days after the tenth (10th) day of the month next following each month in which labor was done or performed in whole or in part, or material was delivered, in whole or in part.

On February 10 and 11, 1983, within the 90-day notice period required under the payment bond’s quoted provisions, Hou-Tex notified Baxter and Federal Insurance, respectively, of its unpaid invoices to Cinco, Baxter’s mechanical subcontractor, total-ling $18,860.40, for work completed on the *357 job during the month of November, 1982. Cinco had filed for bankruptcy. However, Hou-Tex’s notifications were not furnished within 36 days after the 10th day of December 1982, the month next following the month when the labor was performed and the services rendered, as required under art. 5160 B(b)(2).

Although several earlier Hou-Tex claims had been paid under the payment bond, Baxter and Federal Insurance refused payment on the November 1982 invoices, stating that they were not submitted timely under the statute.

Hou-Tex sued Baxter and Federal Insurance to recover under the bond on the November invoices, and both sides moved for summary judgment. Baxter and Federal Insurance asserted in both their answer and their own motion for summary judgment that Hou-Tex did not give notice as required under Tex.Rev.Civ.Stat.Ann. art. 5160 (Vernon Supp.1986).

Proof submitted to the trial court by stipulation showed that the bond executed by Baxter, as principal, and Federal Insurance, as its surety, is a payment bond within the purview of art. 5160; that Hou-Tex’s notice to Baxter and Federal Insurance did not comply with the requirement under the statute; but that the notice given did meet the requirements of the bond. All parties agree that if the statutory notice requirement controls over the payment bond’s more expansive contractual notice provisions, Hou-Tex’s failure to give notice within 36 days after December 10, 1984, is a bar to any claim on the bond. The trial court granted claimant Hou-Tex’s motion for summary judgment and denied that of appellants Baxter and Federal Insurance.

In two points of error, Baxter and Federal Insurance assert that the trial court erred: (1) by allowing recovery on the statutory bond when Hou-Tex did not comply with the statutory prerequisite of notice, although it did comply with the bond’s contractual notice requirements; and (2) by allowing contractual notice requirements of the bond to override statutory notice requirements.

It is well-settled that art. 5160 sets out the method by which persons who furnish labor or materials for the construction of public improvements may bring themselves under the protection of the statutory payment bond. Barfield v. Henderson, 471 S.W.2d 633, 637 (Tex.Civ.App.—Corpus Christi 1971, writ ref’d n.r.e.). The statutory provisions governing recovery are mandatory and provide the only procedure and remedy for presenting a claim against the bond. Barfield; Bunch Electric Co. v. Tex-Craft Builders, 480 S.W.2d 42 (Tex.Civ.App.—Tyler 1972, no writ).

To this end, it is well-settled that the terms of art. 5160 are by law incorporated into and become part of any bond executed by a general contractor in connection with the construction of public buildings for the State or its agencies, regardless of whether art. 5160 is mentioned, referred to, or incorporated into the bond. City of San Antonio v. Argonaut Insurance Company, 644 S.W.2d 90 (Tex.Civ.App.—San Antonio 1982, writ ref’d n.r.e.). Incorporation of the terms of the statute is not dependent on the intent of the parties. Id. at 92.

Appellants urge that because the bond is statutory, statutory provisions become a part of the bond by incorporation, and that they control in every instance of conflict between language of the bond and the statute. Apellants urge that such a construction is required to attain a policy of consistent application of the statute.

We disagree. Our examination of the cited case authorities shows that such interpretations are made only to achieve the minimum standards imposed by the applicable statutes.

The legislative purpose of art.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dealers Electrical Supply Co. v. Scoggins Construction Co.
292 S.W.3d 650 (Texas Supreme Court, 2009)
Argee Corp. v. Solis
932 S.W.2d 39 (Court of Appeals of Texas, 1995)
City of LaPorte v. Taylor
836 S.W.2d 829 (Court of Appeals of Texas, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
718 S.W.2d 355, 1986 Tex. App. LEXIS 8307, Counsel Stack Legal Research, https://law.counselstack.com/opinion/baxter-construction-co-v-hou-tex-products-inc-texapp-1986.