Bunch Electric Company v. Tex-Craft Builders, Inc.

480 S.W.2d 42, 1972 Tex. App. LEXIS 2505
CourtCourt of Appeals of Texas
DecidedApril 27, 1972
Docket596
StatusPublished
Cited by31 cases

This text of 480 S.W.2d 42 (Bunch Electric Company v. Tex-Craft Builders, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bunch Electric Company v. Tex-Craft Builders, Inc., 480 S.W.2d 42, 1972 Tex. App. LEXIS 2505 (Tex. Ct. App. 1972).

Opinion

MOORE, Justice.

This is a suit by a subcontractor against a prime contractor arising out of the construction of a public housing project in Crockett, Houston County, Texas. Appellant, Bunch Electric Company (hereinafter referred to as Bunch), an electrical subcontractor on said project, brought suit for labor and materials furnished as well as for unpaid retainage against the prime contractor, Tex-Craft Builders, Inc. (hereinafter referred to as Tex-Craft), and Continental Casualty Company of Illinois (hereinafter referred to as Continental), the surety on Tex-Craft’s payment bond. Also named as a defendant was the housing authority commissioning the construction, Housing Authority of the City of Crockett (hereinafter referred to as the Housing Authority). The suit was brought under the provisions of Article 5160, Vernon’s Annotated Civil Statutes. Defendants answered with a special denial and also with an unverified special denial, denying that they had received notice of the claim.

Trial was had before the court sitting without a jury. The trial court rendered judgment in favor of appellant, Bunch, against the prime contractor, Tex-Craft, for $13,815.91, the balance due under the contract, but denied a recovery against Continental and the Housing Authority. Appellant, Bunch, duly perfected this appeal complaining of the trial court’s action in refusing to render a joint and several judgment against the bonding company, Continental, for the $13,815.91 upon its payment bond, and also appealed from the judgment denying a recovery against the Housing Authority. Defendant, Tex-Craft, did not appeal.

We affirm the judgment of the trial court.

The primary question, raised by appellant’s fourth point, is whether or 'not Bunch discharged its burden of proving that it gave Continental notice of the claim within the ninety-day period allowed by the Statute.

*44 In response to appellant’s request, the trial court filed the following findings of fact and conclusions of law: Under findings of fact the trial court found: “1. (a) Tex-Craft Builders, Inc., as general contractor, entered into a construction contract with the Housing Authority of the City of Crockett, Texas, dated September 28, 1964, as owner, to construct a project known as the Crockett Housing Project. (b) The contract between Tex-Craft and the Housing Authority was subject to modification and change by the parties, and the suggested time for completion was April 1, 1966. But such contract could by mutual agreement be extended and, in fact, was. (c) Continental Casualty Company executed a performance bond or payment bond in the amount of $1,644,000.00, pursuant to the requirements of Article 5160, Vernon’s Annotated Civil Statutes, (d) On or about December 14, 1964, Tex-Craft Builders, Inc. and Bunch Electric Company entered into a contract calling for the performance of the electrical work on the housing project. (e) Bunch Electric Company completed its contract for the electrical work. 2. The Court finds that $13,815.91 is the remaining unpaid balance of the contract amount. 3. The Court finds that of the sum of $13,815.91, $8,896.64 was retainage. 4. By letter dated April 18, 1967, Bunch Electric Company gave a form of written notice to ‘Tex-Craft Builders, Inc. concerning the remaining unpaid balance of their contract in the amount of $13,815.91. 5. The plaintiff sent a notice on July 10, 1967, but said notice was not for materials or labor performed, but was in the way of alleged special damages. 6. Bunch Electric Company last performed labor or supplied materials to the housing project on November 25, 1966. The Crockett Housing Authority accepted the project on December 13, 1966, and this was the final completion date and the date when all the work had^been successfully completed to the satisfaction of the Housing Authority, and they did on that date accept the project as completed. 7. There is no showing that Continental Casualty Company ever received notice of the plaintiff’s claim. The Court does find that it received notice as of July 13, 1967, the date that plaintiff filed suit. 8. The original answer of Continental Casualty Company filed in the above entitled matter raises the defense of timeliness as to the notice required. A part of the plaintiff’s case is to prove that notice was given pursuant to Article 5160, Vernon’s Annotated Civil Statutes, and the answer filed by the defendant raises the issue of timeliness of notice. 9. A detailed analysis of the causes of delay was submitted to the Housing Authority by Tex-Craft Builders, Inc. A portion of it was due to weather; a portion of it was due to the default of some of the sub-contractors, and Tex-Craft is not responsible for the delay of the project. 10. Tex-Craft Builders, Inc. did not fail to properly coordinate and supervise the project.” Under Conclusions of Law, the trial court found: “1. The responsibility of Continental Casualty Company is controlled by Article 5160, Vernon’s Annotated Civil Statutes. The notice dated April 18, 1967, if it had been received by the defendants, would in part have satisfied the requirements of Article 5160, but not in whole. A detailed description of the labor performed or the material furnished is lacking in the entire notice. 2. Tex-Craft Builders, Inc. had a duty to supervise and coordinate the project in regard to the erection of the housing project as to all of the sub-contractors. 3. Tex-Craft Builders, Inc. did not breach any duty it owed to the plaintiff. 4. Continental Casualty Company is not liable to the plaintiff in any particular. The bonding company is responsible for material and labor furnished and not paid for, and then only when proper, sufficient and timely notice has been given. The plaintiff herein failed to give proper and timely notice to the bonding company, and the ‘special damages’ are not for material and labor, but are merely speculative on the part of the plaintiff, for which there is no responsibility.”

Article 5160, supra, as amended by Acts 1969, 61st Leg., p. 1390, ch. 422, requires a *45 claimant to give notice of claims for unpaid bills as well as notice of claims for retainage. The statute reads, in part, as follows:

“B. (a) Notices Required for Unpaid Bills, other than notices solely for Re-tainages as hereinafter described.
“Such claimant shall have given within ninety (90) days after the 10th day of the month next following each month in which the labor was done or performed, in whole or in part, or material was delivered, in whole or in part, for which such claim is made, written notices of the claim by certified or registered mail, addressed to the prime contractor at his last known business address, or at his residence, and to the surety or sureties. ⅜ ⅜ ⅜ t*
“B. (c) Notices of Unpaid Retain-ages Required. Retainage Defined.
“Retainage as referred to in this Act is defined as any amount representing any part of the contract payments which are not required to be paid to the claimant within the month next following the month in which the labor was done or material furnished or both.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dealers Electrical Supply Co. v. Scoggins Construction Co.
292 S.W.3d 650 (Texas Supreme Court, 2009)
Truss World, Inc. v. ERJS, INC.
284 S.W.3d 393 (Court of Appeals of Texas, 2009)
Scoggins Construction Co. v. Dealers Electrical Supply Co.
292 S.W.3d 685 (Court of Appeals of Texas, 2008)
C. Green Scaping, L.P. v. Westfield Insurance Co.
248 S.W.3d 779 (Court of Appeals of Texas, 2008)
Redland Insurance Co. v. Southwest Stainless, L.P.
181 S.W.3d 509 (Court of Appeals of Texas, 2005)
Argee Corp. v. Solis
932 S.W.2d 39 (Court of Appeals of Texas, 1995)
Commercial Union Ins. Co. v. Spaw-Glass Corp., Inc.
877 S.W.2d 538 (Court of Appeals of Texas, 1994)
S.A. Maxwell Co. v. R.C. Small & Associates, Inc.
873 S.W.2d 447 (Court of Appeals of Texas, 1994)
City of LaPorte v. Taylor
836 S.W.2d 829 (Court of Appeals of Texas, 1992)
Gill Sav. Ass'n v. International Supply Co. Inc.
759 S.W.2d 697 (Court of Appeals of Texas, 1988)
Baxter Construction Co. v. Hou-Tex Products, Inc.
718 S.W.2d 355 (Court of Appeals of Texas, 1986)
Trevino v. Allstate Insurance Co.
651 S.W.2d 8 (Court of Appeals of Texas, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
480 S.W.2d 42, 1972 Tex. App. LEXIS 2505, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bunch-electric-company-v-tex-craft-builders-inc-texapp-1972.