C. Green Scaping, L.P. v. Westfield Insurance Co.

248 S.W.3d 779, 2008 Tex. App. LEXIS 1334, 2008 WL 467334
CourtCourt of Appeals of Texas
DecidedFebruary 21, 2008
Docket2-06-460-CV
StatusPublished
Cited by4 cases

This text of 248 S.W.3d 779 (C. Green Scaping, L.P. v. Westfield Insurance Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
C. Green Scaping, L.P. v. Westfield Insurance Co., 248 S.W.3d 779, 2008 Tex. App. LEXIS 1334, 2008 WL 467334 (Tex. Ct. App. 2008).

Opinion

OPINION

DIXON W. HOLMAN, Justice.

I. Introduction

Appellant and Cross-Appellee C. Green Scaping, L.P. (“CGS”) sued Appellee and Cross-Appellant Westfield Insurance Company (“Westfield”) on a payment bond issued by Westfield under section 2253 of the Texas Government Code. Following a bench trial, the trial court entered judgment for CGS. In two issues, CGS challenges the sufficiency of the evidence supporting the trial court’s finding that CGS was liable for liquidated damages in the amount of $15,000 and argues that the trial court abused its discretion by not awarding CGS attorney’s fees. Westfield argues that the trial court erred by failing to offset CGS’s award in an amount equal to the trial court’s award to Greenscape Pump Services, Inc. (“Greescape Pump”), another party involved in the lawsuit, and that the evidence is legally and factually insufficient to show that CGS gave timely notice of one of its payment bond claims. We will affirm in part and reverse and render in part.

II. Factual and Procedural Background

SRO General Contracting, Inc. (“SRO”) entered into a public works contract with the City of Fort Worth (“the City”) to reconstruct a portion of Evans Avenue. SRO subcontracted part of the work to CGS, which was responsible for everything “back of the curb” — bricks, brick pavers, sidewalks, decorative concrete sidewalks, columns, monuments, irrigation, landscaping, and a fountain. CGS subcontracted the equipment, material, and labor for the *782 fixed architectural fountain equipment to Greenscape Pump.

As required by the City’s and SRO’s contract and section 2253 of the government code, SRO secured a payment bond issued by Westfield in the amount of the contract. Payments to SRO’s subcontractors were ultimately made through a disbursement control account managed by AACON, Inc.

SRO began work on the project after some initial delays. Thirteen or fourteen change orders were made to the project’s plans, and the City increased the number of days given SRO to complete the project at least once. CGS experienced difficulty beginning work on its portion of the construction after receiving notice to proceed in April 2003 because SRO had not completed part of its work, such as grading and installing steel columns, but CGS eventually completed the work under its contract with SRO. Greenscape Pump also completed its work under the subcontract with CGS.

CGS filed payment bond claims with Westfield on July 14, 2003, October 14, 2003, December 12, 2003, March 10, 2004, and June 1, 2004, for unpaid amounts allegedly due for labor performed, materials furnished, and retainage. CGS also filed a payment bond claim on September 28, 2004, after the City’s final inspection in June 2004 but before the City “clos[ed] out the project” in August 2005. When West-field ultimately withheld $87,424.31 of CGS’s claimed amounts, CGS sued West-field, alleging damages in the amount of $87,424.31, which represented approximately $48,138.68 for retainage, $7,867.74 for work performed during July and August 2004, and approximately $33,000 for work performed under line item twenty-three of the SRO — CGS subcontract agreement. CGS also sued SRO and the City.

Greenscape Pump filed one or more payment bond claims with Westfield for unpaid labor and materials, too. Westfield paid all but $5,561.25. Greenscape Pump sued Westfield for this remaining balance and sought attorneys’ fees.

CGS obtained a default judgment against SRO in the amount of $87,424.31 and nonsuited its claims against the City before trial, leaving Westfield as the sole defendant. At trial in March 2006, witnesses testified that the City assessed liquidated damages against SRO for delays in timely completing the project. Westfield attempted to elicit testimony from Bill Hurst, an inspector for the City who worked on the Evans Avenue project, about construction delays and liquidated damages attributable to CGS, but the trial court sustained CGS’s objection to the testimony because Westfield did not assert delay or liquidated damages as affirmative defenses to CGS’s payment bond claim. The trial court did, however, allow West-field to make an offer of proof setting forth the excluded evidence.

The trial court signed its findings of fact and conclusions of law on May 29, 2006. The trial court found in part that Westfield was liable to Greenscape Pump in the amount of $5,561.25 plus attorneys’ fees and that Westfield was hable to CGS in the amount of $56,006.42, representing $48,138.68 for retainage and $7,867.74 for work performed “in the summer of 2004.” The trial court found that CGS was liable for liquidated damages in the amount of $15,000.00, which reduced CGS’s award to $41,006.42, because CGS “did not timely perform its work under the subcontract and the City of Fort Worth assessed liquidated damages against SRO for delayed completion caused by CGS.” The trial court also found that CGS was not entitled to recover the approximately $33,000.00 that it had requested pursuant to line item *783 twenty-three of SRO’s contract with the City, that Westfield was not entitled to offset the amount awarded to Greenscape Pump from the amount awarded to CGS, and that CGS was not entitled to attorney’s fees.

In November 2006, the trial court signed an order granting Westfield’s motion for leave to amend its pleadings. Westfield included for the first time an assertion in its second amended petition that “SRO was assessed liquidated damages by the City of Fort Worth for failure of the work to be completed on time” and that “CGS was the direct or indirect cause of the delay and that any liquidated damages assessed against SRO and caused directly or indirectly by CGS should be offset against any amounts recovered by CGS from Westfield.” The trial court also signed its final judgment in November 2006 awarding CGS $41,006.42. Westfield “resolved” “all matters between” it and Greenscape Pump. Both CGS and Westfield appeal.

III. Sufficiency Arguments

In its first issue, CGS argues that the evidence is insufficient to support the trial court’s twenty-eighth and twenty-ninth findings of fact that CGS failed to timely perform its work, that the City assessed liquidated damages against SRO for the delayed completion of the project because of CGS, and that CGS is hable for liquidated damages caused by the delays in the amount of $15,000.00. In its second issue, Westfield argues that the evidence is insufficient to support the trial court’s twenty-seventh, thirtieth, thirty-first, thirty-fourth, and part of the thirty-ninth findings of fact that CGS timely filed its September 28, 2004 payment bond claim and that CGS is entitled to recover $7,867.74.

A. Standards of Review

Findings of fact entered in a case tried to the court have the same force and dignity as a jury’s answers to jury questions. Anderson v. City of Seven Points, 806 S.W.2d 791, 794 (Tex.1991). The trial court’s findings of fact are reviewable for legal and factual sufficiency of the evidence to support them by the same standards that are applied in reviewing evidence supporting a jury’s answer. Ortiz v. Jones,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Martinez v. Dallas Central Appraisal District
339 S.W.3d 184 (Court of Appeals of Texas, 2011)
La Ash, Inc. v. Texas A&M University
Court of Appeals of Texas, 2008

Cite This Page — Counsel Stack

Bluebook (online)
248 S.W.3d 779, 2008 Tex. App. LEXIS 1334, 2008 WL 467334, Counsel Stack Legal Research, https://law.counselstack.com/opinion/c-green-scaping-lp-v-westfield-insurance-co-texapp-2008.