Tex-Craft Builders, Inc. v. Allied Constructors of Houston, Inc.

465 S.W.2d 786, 1971 Tex. App. LEXIS 2448
CourtCourt of Appeals of Texas
DecidedMarch 25, 1971
Docket536
StatusPublished
Cited by15 cases

This text of 465 S.W.2d 786 (Tex-Craft Builders, Inc. v. Allied Constructors of Houston, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tex-Craft Builders, Inc. v. Allied Constructors of Houston, Inc., 465 S.W.2d 786, 1971 Tex. App. LEXIS 2448 (Tex. Ct. App. 1971).

Opinion

MOORE, Justice.

This is a suit by a subcontractor against a prime contractor and its surety upon a performance bond, wherein prime contractor filed a cross-action against subcontractor and its surety upon a performance bond. Appellant, Tex-Craft Builders, Inc., 1 the prime contractor, contracted to construct a public housing project in the city of Crockett, Texas, with appellant, Continental Casualty Company of Chicago, Illinois, Inc., 2 acting as surety upon Tex-Craft’s performance bond. As prime contractor, Tex-Craft entered into a subcontract with appellee, Allied Constructors of Houston, Inc., 3 for the concrete work, consisting of streets, parking areas, gutters, sidewalks, patio and house slabs, with ap-pellee, National Standard Insurance Company, acting as surety upon Allied’s performance bond. The subcontractor called for a total payment to Allied of the sum of $99,765.00 and was based upon an agreed schedule of unit prices and the amount of concrete furnished. Allied alleged that in addition to the specific unit prices agreed upon, the contract also provided that Tex-Craft had authority to require changes, deviations and additions to the work; that in the event such changes and additions were made, it was agreed that the contract price was to be adjusted accordingly; that Tex-Craft subsequently made certain changes and additions and refused to pay Allied the sum of $65,365.63 due and owing under the terms of the contract. Tex-Craft answered with a general denial, denying that it owed Allied any amount of money upon the contract and also filed a cross-action against Allied alleging that Allied failed and refused to perform its contract according to the schedule of unit prices; that as a result Tex-Craft was required to complete the concrete work called for in the contract at a cost of $53,470.00 for which amount Tex-Craft prayed judgment over against Allied and the surety on its performance bond.

After a trial before the court, sitting without a jury, the trial judge entered judgment in favor of Allied against Tex-Craft and Continental, jointly and severally, for the sum of $25,219.11 and denied Tex-Craft any relief upon its cross-action. *789 From said judgment, Tex-Craft and Continental have perfected this appeal.

Findings of fact and conclusions of law were filed by the trial judge. Among other things, the court found that (a) the contract between Tex-Craft and Allied provided that Tex-Craft could require changes in, deviations from, additions to and omissions from the work therein contracted, and, that in such event, the contract price would be adjusted accordingly; (b) Continental Casualty Company of Chicago, Illinois, executed, as surety, for Tex-Craft, a performance bond which provided that all claimants thereunder would have a direct right of action against the surety; (c) Allied commenced work under the terms of said contract with Tex-Craft shortly after the execution thereof and performed its work under the terms of said contract in accordance with the terms thereof and in good workmanlike manner until Tex-Craft unilaterally undertook to complete certain remaining portions of the work provided for under said contract to be done by Allied; (d) Allied substantially performed its said contract with Tex-Craft and completed numerous, expensive extras and changes to said contract. Additionally, Allied was at all times ready, willing and able to perform its contract with Tex-Craft; (e) the work performed by Allied pursuant to its contract with Tex-Craft was in accordance with the plans and specifications provided for in such contract and in Tex-Craft’s contract with the housing authority with the city of Crockett, except only in those instances where changes, extras, alterations or additions were required of Allied by Tex-Craft; (f) in late August, 1965, W. J. Grierson, Allied’s president, conferred with Mr. Turner in the bonding department of Continental Casualty Company of Chicago, Illinois, concerning his company’s future prospect for payment from Tex-Craft, and was advised that if Continental was the surety on the bond, there would be no problem with payment and that Mr. Grierson should not worry about it; (g) Continental had repeated actual notice and knowledge of Allied’s specific claim by virtue of being furnished with the original, and/or copies of correspondence from either Tex-Craft, Allied or the housing authority of the city of Crockett; (h) Duane Fossler, vice president of Tex-Craft, talked to representatives of Continental and fully advised and notified them of the claim of Allied and the billings received from Allied as they were received; (i) Continental received, prior to Tex-Craft’s assumption of the remaining work under the contract, a full itemization of the work done by Allied, the dates thereof, the amounts thereof and all lawful offsets, credits and payments; and (j) there remains due and owing to Allied by Tex-Craft for work performed under the terms of said contract, after all offsets, payments and credits the sum of $25,219.11. In the conclusions of law, the court found that (1) Allied substantially performed its contract with Tex-Craft; (2) Tex-Craft, without cause, breached its contract with Allied by failure to make payments as agreed upon and by unilaterally undertaking to complete the terms of Allied’s contract with it; (3) because of its conduct, Continental Casualty Company of Chicago, Illinois (Continental) is estopped from claiming a lack of adequate notice of Allied’s claim against Tex-Craft and Continental ; (4) Continental had repeated, actual, timely, substantial and sufficient notice of Allied’s claim against Tex-Craft and Continental; (5) Continental waived any further compliance with the notice provisions of Article 5160, Vernon’s Ann.Civ.St., regarding Allied’s said claim; (6) Allied substantially complied with the notice requirements of Article 5160, V.A.C.S., in making its claim against Tex-Craft and Continental; (7) Allied instituted its suit against Tex-Craft and Continental within the time prescribed by law; (8) after all just and lawful offsets, payments and credits, there remains unpaid to Allied by Tex-Craft under the provisions of their contract, the sum of $25,219.11, for which sum both Tex-Craft and Continental are liable to Allied and Allied is entitled to judgment in such amount together with interest there *790 on and costs of court against both Tex-Craft and Continental; and, (9) neither Allied nor National Standard Insurance Company, Cross-defendants, have any liability to either Tex-Craft or Continental.

Appellants bring forward numerous points of error attacking the trial court’s findings on the ground that such findings were not supported by the evidence. By the first group of points, they contend (a) that there is no evidence to support the trial court’s findings that Allied substantially performed the contract and (b) that there is no evidence that Allied was prevented from completing the contract due to the wrongful acts of Tex-Craft.

In determining the “no evidence” points, we are required to follow the elementary rule that if the record contains any evidence of probative force to support the trial court’s findings, such findings may not be disturbed on appeal. Banks v. Collins, 152 Tex. 265, 257 S.W.2d 97, 99.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

The State of Texas v. Sanitha Lashay Hatter
Court of Appeals of Texas, 2023
United Fire & Casualty Co. v. Boring & Tunneling Co. of America
321 S.W.3d 24 (Court of Appeals of Texas, 2010)
Wentworth v. Meyer
839 S.W.2d 766 (Texas Supreme Court, 1992)
Opinion No.
Arkansas Attorney General Reports, 1989
Skaggs v. Guerra
704 S.W.2d 51 (Court of Appeals of Texas, 1985)
Burton v. National Bank of Commerce of Dallas
679 S.W.2d 115 (Court of Appeals of Texas, 1984)
Austin Elcon Corp. v. Avco Corp.
590 F. Supp. 507 (W.D. Texas, 1984)
Rosestone Properties, Inc. v. Schliemann
662 S.W.2d 49 (Court of Appeals of Texas, 1983)
Graves v. Sommerfeld
618 S.W.2d 952 (Court of Appeals of Texas, 1981)
Knox-Evans Construction Co. v. Haws & Garrett General Contractors, Inc.
503 S.W.2d 669 (Court of Appeals of Texas, 1973)
Texarkana Construction Co. v. Alpine Construction Specialties, Inc.
489 S.W.2d 941 (Court of Appeals of Texas, 1972)
Bunch Electric Company v. Tex-Craft Builders, Inc.
480 S.W.2d 42 (Court of Appeals of Texas, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
465 S.W.2d 786, 1971 Tex. App. LEXIS 2448, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tex-craft-builders-inc-v-allied-constructors-of-houston-inc-texapp-1971.