Graham v. San Antonio MacHine and Supply Corp.

418 S.W.2d 303, 1967 Tex. App. LEXIS 2032
CourtCourt of Appeals of Texas
DecidedMay 31, 1967
Docket14539
StatusPublished
Cited by24 cases

This text of 418 S.W.2d 303 (Graham v. San Antonio MacHine and Supply Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Graham v. San Antonio MacHine and Supply Corp., 418 S.W.2d 303, 1967 Tex. App. LEXIS 2032 (Tex. Ct. App. 1967).

Opinion

CADENA, Justice.

This is an appeal from a judgment in favor of a subcontractor and the subcontractor’s materialman against a prime contractor on a public construction project and his surety on a payment bond executed in conformity with the provisions of the Mc-Gregor Act, Article 5160, Vernon’s Ann. Civ.St. (1962).

Appellant, H. Gillis Graham, d/b/a Graham Construction Company, herein called *306 “Graham,” was the prime contractor under a contract with the Alice Water Authority for the construction of a water supply system and treatment plant in the City of Alice, Jim Wells County. Appellant National Surety Corporation, herein called “National,” was the surety on the payment bond furnished by Graham. Appellee, San Antonio Machine and Supply Corporation, herein referred to as “SAMSCO,” as subcontractor, contracted with Graham to fabricate and erect, in connection with the Alice water project, a storage tank and a wash tank for the sum of $64,000.00. In addition, SAMSCO furnished Graham, on what is referred to in the record as an open account, materials and supplies used by Graham in the performance of his contract with the Alice Water Authority. Eureka Machine Tools, Inc., herein called “Eureka,” furnished materials to SAMSCO which were used in the construction of the Alice water project.

On November 9, 1964, Graham filed this action, in the form of a bill of interpleader, in the District Court of Jim Wells County, alleging that SAMSCO had substantially performed the work called for in its contract with Graham, as a result of which Graham was indebted to SAMSCO in the sum of $55,010.63. The pleading then recited that rival and conflicting claims, including a claim by Eureka in the amount of $9,203.43, had been made upon Graham for moneys due SAMSCO. The other rival claimants named by Graham have filed disclaimers and are no longer parties to this litigation.

Meanwhile, on a date not revealed by the record in this case, SAMSCO had been adjudged bankrupt, and on November 18, 1964, the bankrupt court, being the United States District Court for the Western District of Texas, San Antonio Division, issued its order enjoining all parties to the interpleader suit from continuing the litigation. National, which at this stage of the proceedings had not been made a party to this suit, was not named in such stay order.

Thereafter, on February 1, 1965, Eureka filed in this case what it designated an “intervention,” alleging that SAMSCO was indebted to it from materials furnished SAMSCO and used in construction of the Alice water project, in the sum of $9,203.43, and that to this extent its claim to the funds held by Graham was superior to that of all other claimants. In addition, Eureka alleged that National had executed, as surety for Graham, the payment bond described above, and prayed for recovery from Graham and National. Eureka also sought recovery of attorney’s fees.

On April 5, 1965, National having filed no answer to Eureka’s claim, the trial court entered an interlocutory default judgment in favor of Eureka against National in the sum of $9,203.43, plus $500.00 for attorney’s fees.

On August 2, 1965, the stay order entered by the United States District Court in the SAMSCO bankruptcy proceedings was terminated. On, August 3, 1965, SAMSCO filed its answer in Eureka’s suit, including a cross-action against Graham and National, alleging that Graham was indebted to SAMSCO in the sum of $62,081.67 for labor and materials furnished Graham by SAMSCO in connection with the Alice project.

On August 26, 1965, National filed its answer to SAMSCO’s cross-action, and on November 5, 1965, National filed its motion to set aside the default judgment rendered against it and in favor of Eureka on April 5, 1965. This motion to set aside the default judgment was denied by the trial court on December 20, 1965.

On March 2, 1966, Graham and National filed their amended answer to SAMSCO’s cross-action, including a cross-action against SAMSCO for damages allegedly resulting from SAMSCO’s delay in fabricating and installing the water tanks. On March 16, 1966, after a trial without a *307 jury, the trial court entered judgment as follows:

1. The default judgment in favor of Eureka against National was made final.

2. Eureka was granted recovery against SAMSCO in the sum of $9,203.43, plus $1,000.00 as attorney’s fees. SAMSCO does not complain of this portion of the judgment.

3. SAMSCO was granted recovery of $62,081.67 on its cross-action against Graham and National, but National was allowed a credit in the amount of $4,650.00, representing the extent of the claim perfected by Eureka against National under the provisions of Article 5160. SAMSCO was granted a further recovery of $12,000.00 against Graham for attorney’s fees.

Some of appellants’ points of error assail the rendition of the default judgment in favor of Eureka, with the remainder being directed to the rendition of the judgment in favor of SAMSCO. We shall discuss the Eureka and SAMSCO claims separately.

1. THE JUDGMENT IN FAVOR OF EUREKA

National contends that the trial court erred in rendering default judgment in favor of Eureka because Eureka’s pleadings did not state a cause of action against National; that the trial court erred in refusing to set aside the interlocutory default judgment; and that, in any event, Eureka was not entitled to recover, as against National, attorney’s fees.

a. The Entry of the Default Judgment

Eureka alleged, in substance, that it had furnished materials to SAMSCO which were used in connection with the Alice water project described in Graham’s petition, and that, therefore, Graham and SAMSCO were indebted to it in the sum of $9,203.43. Eureka further alleged that National had issued a payment bond in connection with such project; that National was obligated to pay Eureka for the materials furnished; and that Eureka had complied with the legal requirements for judgment against National.

Eureka’s pleadings, by reference to Graham’s petition in interpleader, show that the project in question was a public construction project in which Graham was the “prime contractor,” and that such project was subject to the provisions of Article 5160, which require that the prime contractor furnish a payment bond. This sufficiently identified Graham as the principal on the payment bond issued by National. In determining whether pleadings are sufficient to support a default judgment, the claimant’s pleading will be tested by the rules which would have been applied under the old general demurrer practice. Odom v. Pinkston, 193 S.W.2d 888 (Tex.Civ.App., 1946, writ ref’d n. r. e.). That is, the default judgment will stand if the pleadings give fair notice to the adversary of the nature of the claim against him, even though the pleadings would be vulnerable to attack by special exception. 4 McDonald, Texas Civil Procedure, p. 1372 (1950). Tested by these rules, Eureka’s pleadings, although cast in general terms which, perhaps, would not have withstood challenge by special exception, were sufficient, except the portion seeking recovery of attorney’s fees, to state a cause of action against National.

b.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

La Ash, Inc. v. Texas A&M University
Court of Appeals of Texas, 2008
Gramercy Insurance Co. v. Arcadia Financial Ltd.
96 S.W.3d 320 (Court of Appeals of Texas, 2001)
Burton v. National Bank of Commerce of Dallas
679 S.W.2d 115 (Court of Appeals of Texas, 1984)
Rosestone Properties, Inc. v. Schliemann
662 S.W.2d 49 (Court of Appeals of Texas, 1983)
Wheeler v. Wheeler
263 S.E.2d 763 (Supreme Court of North Carolina, 1980)
Braugh v. Phillips
557 S.W.2d 155 (Court of Appeals of Texas, 1977)
Blue Bell, Inc. v. Isbell
545 S.W.2d 563 (Court of Appeals of Texas, 1976)
Magic Carpet Co. v. Pharr
508 S.W.2d 696 (Court of Appeals of Texas, 1974)
Wheat v. United States
353 F. Supp. 720 (S.D. Texas, 1973)
Pioneer Casualty Co. v. Feldman
468 S.W.2d 910 (Court of Appeals of Texas, 1971)
Tex-Craft Builders, Inc. v. Allied Constructors of Houston, Inc.
465 S.W.2d 786 (Court of Appeals of Texas, 1971)
United States Fidelity & Guaranty Co. v. Bimco Iron & Metal Corp.
455 S.W.2d 828 (Court of Appeals of Texas, 1970)
Hancock v. OK Rental Equipment Company
441 S.W.2d 955 (Court of Appeals of Texas, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
418 S.W.2d 303, 1967 Tex. App. LEXIS 2032, Counsel Stack Legal Research, https://law.counselstack.com/opinion/graham-v-san-antonio-machine-and-supply-corp-texapp-1967.