Transamerica Insurance Co. v. Housing Authority of Victoria

669 S.W.2d 818, 1984 Tex. App. LEXIS 5291
CourtCourt of Appeals of Texas
DecidedMarch 29, 1984
Docket13-82-385-CV
StatusPublished
Cited by17 cases

This text of 669 S.W.2d 818 (Transamerica Insurance Co. v. Housing Authority of Victoria) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Transamerica Insurance Co. v. Housing Authority of Victoria, 669 S.W.2d 818, 1984 Tex. App. LEXIS 5291 (Tex. Ct. App. 1984).

Opinions

OPINION

BISSETT, Justice.

This is a suit arising out of a public construction contract. The Housing Authority of the City of Victoria, Texas, hereafter “the Housing Authority,” in a petition filed on July 30,1979, sought damages from Transamerica Insurance Company, Bruce Campbell & Son Construction Co., Inc., and others, for alleged construction defects arising out of a contract for the renovation of public housing in the City of Victoria, Texas. The case was submitted to the jury on special issues. Certain answers by the jury, which we do not discuss in this opinion, were disregarded by the trial court as being immaterial, but based on the jury’s answers to the remaining issues, judgment was rendered that the Housing Authority recover jointly and severally from Bruce Campbell & Son Construction Co., Inc. (the contractor for the allegedly defective construction), hereafter “Campbell,” and Transamerica Insurance Company (the surety on the performance bond given by Campbell), hereafter “Trans-america,” actual damages in the amount of $384,323.00, $66,000.00 in attorney’s fees through the trial of the case, and $20,-000.00 “for further attorney’s fees” after the trial. The additional attorney’s fees were subject to remittitur, in part or total, depending on whether there were appeals from the judgment to the appellate courts.

In addition, judgment was rendered that Transamerica recover from Campbell the sum of $384,323.00, “for actual damages, and the further sum of $39,000.00 for attorney’s fees for services rendered through the trial of this case, and the further sum of $18,000.00 for further attorneys’ fees incurred after the trial of this cause,” with [820]*820provisions for remittitur if Campbell did not appeal the judgment. Campbell has not appealed. Only Transamerica has perfected an appeal from the trial court’s judgment. Campbell, however, has filed a brief in this Court wherein it assumes the posture of an appellee in response to Trans-america’s twenty-sixth, twenty-seventh and twenty-eighth points of error. We do not reach those points of error in this appeal.

On July 1, 1974, the Housing Authority, as the owner, and Campbell, as the general contractor, entered into a construction contract for the repair and modernization of three housing projects owned by the Housing Authority and for the construction of a new community building, which was also a public building. The original contract price was $871,300.00. Transamerica issued a performance bond in favor of the Housing Authority, sometime referred to as “LHA” in the contract documents, in the amount of the original contract price.

On August 4, 1975, the Housing Authority occupied the projects, and a “Certificate and Release” was executed by Campbell to the Housing Authority. Also, on the same day, a “Certificate of Completion” was signed by the Housing Authority’s architect, Robert V. Buck, by the Housing Authority and by Campbell, which stated that the work was completed as of August 4, 1975, with the exception of certain “punch list” items in the amount of $10,200.00. Campbell was subsequently paid all sums owing under the contract except for $5,000.00.

The punch list items consisted of dirt work of $1,000.00, paving work of $4,600.00, exterior paneling of $4,400.00, and shelving of $200.00. At the time the Certificate of Completion was executed, the Housing Authority had withheld, as retain-age, the sum of $54,774.00 as called for in the contract documents. The Housing Authority, the architect and Campbell agreed that the sum of $10,200.00 should be retained by the Housing Authority until completion of such punch list items, and that the remaining amount of $44,574.00 should be paid to Campbell. On August 20, 1975, Campbell agreed to re-nail, as necessary, staples used in the construction of the roofs that needed re-nailing, and authorized the Housing Authority to retain an additional $1,000.00 until the staples were re-nailed, conditioned upon the latter’s immediate payment to the former of the previously agreed upon sum of $44,574.00, less the additional $1,000.00 retention. After the staples had been re-nailed, the Housing Authority paid the agreed upon sum of $44,574.00 to Campbell. Thereafter, the Housing Authority paid an additional $5,200.00 to Campbell but retained the sum of $5,000.00. The final payment under the contract in the amount of $5,000.00 was never made to Campbell because of its failure to remedy certain construction defects in accordance with the provisions in the contract which required it to remedy defects occurring within one year after the Housing Authority’s occupancy of the project.

Transamerica, in its second, third, fourth, sixth, seventh and eighth points of error, contends that the trial court erred in failing to grant it a directed verdict and in failing to withdraw the case from the jury and render judgment in its favor, because the action brought against it by the Housing Authority was barred by the one-year statute of limitations, as provided by TEX. REV.CIV.STAT.ANN. art. 5160 G (Vernon 1971).

The Housing Authority, in its brief, argues:

“1) The performance bond executed by Appellant (Transamerica) provided that suit must be instituted before the expiration of two (2) years from the date on which final payment fell due. This limitation period of two (2) years contained in the performance bond controls over the one (1) year limitation period provided in Article 5160.
2) Appellant (Transamerica) failed to submit an issue to the jury seeking a fact determination as to when ‘final completion’ of the contract occurred. Under Article 5160, the one (1) year limitation period begins to run upon ‘final comple[821]*821tion of the contract. Even if the limitation period provided in Article 5160 is held to control over the terms of the bond, absent a fact determination by the jury as to when ‘final completion’ of the contract occurred, it is impossible to now determine if the one (1) year statutory period had expired before suit was filed. 3) The issuance by the architect of the Certificate of Completion was not, in this case, a conclusive determination that ‘final completion’ of the contract had occurred.”
Article 5160 G, in relevant part, provides: “G.... No suit shall be instituted on the performance bond after the expiration of one (1) year after the date of final completion of such contract ...”

Article 5160 A (Vernon 1971), which was in effect when the subject contract was executed, required that any person who contracted with any governmental or quasi-governmental authority for the construction of public improvements to furnish a performance bond where the construction costs exceeded $2,000.00. In the instant case, the costs were greatly in excess of $2,000.00; therefore, a performance bond was required by the statute since the Housing Authority is a quasi-governmental authority. The bond stated suit must be instituted before the expiration of two years from the date when final payment became due.

The performance bond furnished by Transamerica is required by Article 5160 A, is in compliance with the provisions of that statute, and is a statutory bond. Any suit on the bond is subject to the one-year limitations period provided by Article 5160 G. “The statutory provisions [of Article 5160] governing recovery are mandatory as well as exclusive and provide the only procedure and remedy for presenting a claim against the bond.” City of San Antonio v. Argonaut Insurance Company,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Wolfe City v. Am. Safety Cas. Ins. Co.
557 S.W.3d 699 (Court of Appeals of Texas, 2018)
Hartford Fire Ins. v. CITY OF MONT BELVIEU, TEX.
611 F.3d 289 (Fifth Circuit, 2010)
Gutierrez v. Elizondo
139 S.W.3d 768 (Court of Appeals of Texas, 2004)
Untitled Texas Attorney General Opinion
Texas Attorney General Reports, 2001
Opinion No.
Texas Attorney General Reports, 2001
Augusta Court Co-Owners' Ass'n v. Levin, Roth & Kasner, P.C.
971 S.W.2d 119 (Court of Appeals of Texas, 1998)
TDIndustries, Inc. v. NCNB Texas National Bank
837 S.W.2d 270 (Court of Appeals of Texas, 1992)
Commercial Union Insurance Co. v. La Villa Independent School District
779 S.W.2d 102 (Court of Appeals of Texas, 1989)
Baxter Construction Co. v. Hou-Tex Products, Inc.
718 S.W.2d 355 (Court of Appeals of Texas, 1986)
Transamerica Insurance Co. v. Housing Authority of Victoria
669 S.W.2d 818 (Court of Appeals of Texas, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
669 S.W.2d 818, 1984 Tex. App. LEXIS 5291, Counsel Stack Legal Research, https://law.counselstack.com/opinion/transamerica-insurance-co-v-housing-authority-of-victoria-texapp-1984.