Commercial Union Insurance Co. v. La Villa Independent School District

779 S.W.2d 102, 1989 Tex. App. LEXIS 2568, 1989 WL 119216
CourtCourt of Appeals of Texas
DecidedOctober 12, 1989
Docket13-88-642-CV
StatusPublished
Cited by32 cases

This text of 779 S.W.2d 102 (Commercial Union Insurance Co. v. La Villa Independent School District) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Commercial Union Insurance Co. v. La Villa Independent School District, 779 S.W.2d 102, 1989 Tex. App. LEXIS 2568, 1989 WL 119216 (Tex. Ct. App. 1989).

Opinion

OPINION

UTTER, Justice.

La Villa Independent School District (La Villa), brought suit against Commercial Union Insurance Company (Commercial), To-con Construction Corporation (Tocon), and Bill Caudle, Sr., alleging numerous theories of recovery as to each defendant for problems that developed with respect to a gymnasium that Tocon constructed. Commercial filed a performance bond on this project in favor of La Villa, and Caudle was the president, chief executive officer, and majority shareholder of Tocon. After a bench trial, the court ordered that La Villa recover $12,950.00 and attorneys’ fees from Commercial and Tocon, jointly and severally, but denied any recovery against Caudle. The trial court’s order specifically denies La Villa’s Deceptive Trade Practice Act claims, but does not otherwise specify under which theory La Villa is being permitted to recover. The court further denied all of the defendant’s counterclaims, including Tocon’s counterclaim regarding a “liquidated damage provision” in its contract with La Villa. We affirm in part and reverse in part.

La Villa entered into a construction contract with Tocon, the general contractor, dated March 16, 1983, for the construction of a new gymnasium. Pursuant to the requirements of the contract and Tex.Rev. Civ.Stat.Ann. art. 5160 (Vernon 1987), To-con furnished La Villa with a performance bond, dated March 16, 1983, for $196,-050.00, with Commercial as surety. This amount was later increased to $196,462.00 to reflect the full amount of the contract price. On April 1, 1983, Rudy Gomez, La Villa’s architect, issued notice to Tocon to proceed. This notice informed Tocon that work was to begin within ten days of the notice and that Tocon had until August 8, 1983 to complete the project. Tocon thereafter commenced construction of the gymnasium.

On November 7, 1983, a certificate of substantial completion was issued by the architect and La Villa, as reflected on that certificate, accepted the work completed and assumed full possession on January 19, 1984. Tocon was subsequently notified of various deficiencies which needed correction. A letter from Gomez dated January 16, 1984 informed Tocon that there was a problem with paint discoloration. Although Tocon corrected several other defects and represented that it would correct the problem with the paint discoloration, Tocon failed to remedy this problem. On August 13, 1985, La Villa accepted a $12,-950.00 bid to re-paint the gymnasium from another contractor. On February 20, 1986, La Villa filed this suit to recover its losses.

In considering a “no evidence”, “insufficient evidence” or “against the great weight and preponderance of the evidence” point of error, we will follow the well-established test set forth in Pool v. Ford Motor Co., 715 S.W.2d 629 (Tex.1986); Dyson v. Olin Corp., 692 S.W.2d 456 (Tex.1985); Glover v. Texas General Indemnity Co., 619 S.W.2d 400 (Tex.1981); Garza v. Alviar, 395 S.W.2d 821 (Tex.1965); Allied Finance Co. v. Garza, 626 S.W.2d 120 (Tex.App. — Corpus Christi 1981, writ ref’d n.r. e.); and Calvert, No Evidence and Insufficient Evidence Points of Error, 38 Texas L.Rev. 361 (1960).

There were no findings of fact and conclusions of law filed in this cause. Absent findings of fact and conclusions of law, all questions of fact should be presumed to support the judgment, and the judgment should be affirmed if it can be upheld on any legal theory that finds support in the pleadings and in the evidence. Point Lookout West, Inc. v. Whorton, 742 S.W.2d 277, 278 (Tex.1987); Campbell & Son Construction Co. v. Housing Authority of Victoria, 655 S.W.2d 271, 274 (Tex.App. — Corpus Christi 1983, no writ).

Commercial and Tocon’s first through third points of error contend that the trial *105 court erred in granting a recovery against Commercial upon the surety bond. They argue that the evidence conclusively showed that the claim was barred by limitations and that the trial court’s holding to the contrary was against the overwhelming weight and preponderance of the evidence.

The record reflects that the performance bond stated that “any suit under this bond must be instituted before the expiration of two (2) years from the date on which final payment under the Contract falls due.” However, the performance bond also stated that it was being “... executed pursuant to the provisions of Article 5160 of the Revised Civil Statutes of Texas as amended, and all liabilities on this bond ... shall be determined in accordance with the provisions of said Article....” Gomez filed a certificate of substantial completion on November 7, 1983, and Tocon requested final payment on November 29, 1983. Gomez sent La Villa a letter dated December 1, 1983, wherein he submitted Tocon’s request for final payment, but stated various amounts were going to be retained to correct deficiencies and for liquidated damages. La Villa made this payment by check dated February 14, 1984. La Villa filed this suit to recover its losses on February 20, 1986.

The issues are whether the one or two year statute of limitations is applicable, and whether the trial court’s determination that the case was not barred by limitations is supported by the evidence.

The events of this transaction occurred as follows:

1. March 16,1983 — parties enter a contract and bond
2. April 1, 1983 — notice to proceed is issued by the architect
3. August 8, 1983 — date of completion as specified in the architect’s notice to proceed
4. November 7, 1983 — date of substantial completion signed by architect
5. January 16, 1984 — architect states that there is a problem with paint discoloration
6. January 19, 1984 — date of substantial completion accepted by school district
7. February 14, 1984 — last payment made by school district received by Tocon
8. March 26, 1984 — letter by architect regarding paint problem
9. November 27, 1984 — Caudle/Tocon letter stating that paint work will be subcontracted out
10. October 1, 1985 — attorney demand letter
11. February 20, 1986 — suit filed.

Under Tex.Rev.Civ.Stat.Ann. art. 5160 G, no suit shall be instituted on a bond after the expiration of one year after the date of final completion of such contract. However, the performance bond in question stated that any suit must be instituted before the expiration of two years from the date on which final payment under the contract falls due.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Wolfe City v. Am. Safety Cas. Ins. Co.
557 S.W.3d 699 (Court of Appeals of Texas, 2018)
Russell Scott Mize v. Robin Michelle Mize
Court of Appeals of Texas, 2009
Fluid Concepts, Inc. v. Da Apartments Ltd. Partnership
159 S.W.3d 226 (Court of Appeals of Texas, 2005)
Richard Charles Mengel v. State
Court of Appeals of Texas, 2004
GXG, INC. v. Texacal Oil & Gas
977 S.W.2d 403 (Court of Appeals of Texas, 1998)
Augusta Court Co-Owners' Ass'n v. Levin, Roth & Kasner, P.C.
971 S.W.2d 119 (Court of Appeals of Texas, 1998)
KC Roofing Co., Inc. v. Abundis
940 S.W.2d 375 (Court of Appeals of Texas, 1997)
Stanley Stores, Inc. v. Chavana
909 S.W.2d 554 (Court of Appeals of Texas, 1995)
Staff Industries, Inc. v. Hallmark Contracting, Inc.
846 S.W.2d 542 (Court of Appeals of Texas, 1993)
In Re Independent American Real Estate, Inc.
146 B.R. 546 (N.D. Texas, 1992)
Perez v. Bagous
833 S.W.2d 671 (Court of Appeals of Texas, 1992)
Phillips v. Phillips
820 S.W.2d 785 (Texas Supreme Court, 1992)
Baker v. International Record Syndicate, Inc.
812 S.W.2d 53 (Court of Appeals of Texas, 1991)
Lacy v. First National Bank of Livingston
809 S.W.2d 362 (Court of Appeals of Texas, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
779 S.W.2d 102, 1989 Tex. App. LEXIS 2568, 1989 WL 119216, Counsel Stack Legal Research, https://law.counselstack.com/opinion/commercial-union-insurance-co-v-la-villa-independent-school-district-texapp-1989.