City of Midland v. Waller

430 S.W.2d 473, 11 Tex. Sup. Ct. J. 484, 1968 Tex. LEXIS 279
CourtTexas Supreme Court
DecidedJune 26, 1968
DocketB-536
StatusPublished
Cited by30 cases

This text of 430 S.W.2d 473 (City of Midland v. Waller) is published on Counsel Stack Legal Research, covering Texas Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Midland v. Waller, 430 S.W.2d 473, 11 Tex. Sup. Ct. J. 484, 1968 Tex. LEXIS 279 (Tex. 1968).

Opinion

GRIFFIN, Justice.

The City of Midland, Texas, as plaintiff, brought this suit against Leonard E. Waller, a general contractor, hereinafter called contractor, and Travelers Indemnity Company, hereinafter referred to as surety, the contractor’s surety on a performance bond, to recover damages for breach of a contract for the construction of a municipal swimming pool. In the trial court contractor and surety each moved for a summary judgment. The trial court granted the motions and entered a judgment that the City take nothing by its suits against contractor and surety. On appeal this judgment was affirmed. Tex.Civ.App., 418 S.W.2d 915.

Following the advertisement for competitive bids, as required by law, the City of Midland, Texas, entered into a general construction contract with contractor dated December 28, 1962, calling for the construction of a 50-meter, Olympic size swimming pool in one of the City’s public parks. In addition to voluminous, detailed plans and specifications, said contract incorporated and included the A. I. A. Standard Contract Documents, consisting of various general and special conditions.

Pursuant to the requirements of the contract and of Article 5160 Vernon’s Ann. *475 Civ.St., as amended, contractor furnished City with his performance bond, dated January 3, 1963, in the full amount of the contract price, with Travelers Indemnity Company as surety, conditioned that contractor would faithfully perform said contract according to the plans and specifications. Contractor then commenced construction of the pool.

We will first dispose of the City’s application for writ of error against the surety. In answer to this application the surety contends it is not liable because suit was not filed on the bond within one year from September 15, 1963, the date the City accepted the pool and began to use the same.

The parties attached a copy of the bond to their “Stipulations and Agreed Statement of Facts.” The stipulation recites: “ * * * that pursuant to said contract documents and Article 5160 Revised Civil Statutes of Texas, 1926, as amended, the defendant Leonard E. Waller, as principal, and the defendant, The Travelers Indemnity Company, as surety, duly made and entered into a performance bond * * The copy of the attached performance bond contained the following provision: “Provided, however, that this bond is executed pursuant to the provisions of Article 5160 of the Revised Civil Statutes of Texas, as amended by the Acts of the 56th Legislature, Regular Session, 1959, and all liabilities on this bond shall be determined in accordance with the provisions of said Article to the same extent as if it were copied at length herein.”

The pertinent provisions of Art. 5160 are: “No suit shall be instituted on the performance bond after the expiration of one (1) year after the date of final completion of such contract.”

It is stipulated that the Certificate of Acceptance by the City’s architect was dated September 15, 1963. The City’s pleadings and the proof on the hearing established that the City accepted the swimming pool and paid to the contractor the balance due on the contract price on September 15, 1963, and opened the pool to the use of the public on that date. The City alleged that about May 27, 1965, defects of various kinds were discovered in the pool; that these defects were due to the failure of contractor to construct same according to the plans and specifications, and in a good and workmanlike manner, and under the exercise of ordinary care, all of which he was bound to do under the terms of the contract and according to common law. On November 12, 1965, this suit was filed against the contractor and the surety on the performance bond for damages. This was more than two years after the City had accepted and begun the use of the pool.

The present suit was filed more than one year after the City accepted the pool and paid the contractor. The limitation imposed by Art. 5160 applies, and the trial court correctly rendered a summary judgment that the City take nothing against the surety. The Court of Civil Appeals correctly affirmed that judgment. We affirm the judgment of both courts below in favor of the surety.

As to the City’s cause of action against the contractor, the courts below have denied the City a recovery on the ground that the architect’s certificate of completion given to the City was a final determination that the contractor had complied with his obligations set out in the contract to build the pool, and the City could not hold the contractor liable for the defects appearing for the first time some twenty months thereafter.

Reliance is placed by the contractor on! Art. 1.07 of the construction contract’s “Special Conditions,” to relieve him of any liability for damages due the City because the architect had issued his final certificate of completion and acceptance of the swimming pool September 15, 1963. The contractor also claims no liability to the City because there was nothing wrong with the pool until May, 1965, some twenty *476 months after the acceptance of the pool by the City.

The construction contract defined the scope of the contract’s special conditions as follows: “The A. I. A. General Conditions, and the Special Conditions bound herewith are included in this specification and form a part of every branch thereof, and shall govern the work under each SECTION. Where the Special Conditions conflict with the General Conditions, the Special Conditions shall govern.” Among the Special Conditions is Art. 1.07, entitled “Authority of Architect.” It provides :

“All work shall be performed under the supervision of Architect or his authorized representative in a workmanlike manner and to his satisfaction. He shall decide all questions which arise under this work regarding the following, and his decisions and estimates shall be final.
“A. Quality and acceptability of the following: 1. Materials furnished and/or proposed for use; 2. work performed; 3.- manner of performance * * *. B. Interpretation of Plans, Specifications and Contract Documents. C. Acceptable fulfillment of the contract. D. Compensation. * * * G. Determination of amount and quality of work performed and materials furnished.”

Also, there is special condition, Art. 1.12 “Guaranty Warranty”:

“Neither the final certificate of payment nor any provision in the Contract Documents, nor partial or entire use, or occupancy of the premises by the Owner will constitute an acceptance of work not done in accordance with the Contract Documents, or relieve the Contractor of liability in respect to any expressed warranties or responsibility for faulty materials or workmanship.
“The Contractor shall and does hereby guarantee for a period of one year from date of final acceptance all work as called for in the various divisions of these Specifications.”

The Construction Contract also contained the following “General Conditions”:

“Art. 20. Correction of Work After Final Payment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Michael Sloggett v. LaCore Enterprises, LLC
Court of Appeals of Texas, 2021
Gamma Group, Inc. v. Transatlantic Reinsurance Co.
242 S.W.3d 203 (Court of Appeals of Texas, 2008)
Tittle v. Enron Corp
Fifth Circuit, 2006
MCI Telecommunications Corp. v. Texas Utilities Electric Co.
995 S.W.2d 647 (Texas Supreme Court, 1999)
Polley v. Odom
957 S.W.2d 932 (Court of Appeals of Texas, 1998)
Matthews v. Wozencraft
15 F.3d 432 (Fifth Circuit, 1994)
Martinez v. Humble Sand & Gravel, Inc.
860 S.W.2d 467 (Court of Appeals of Texas, 1993)
El Paso Assoc., Ltd. v. JR Thurman & Co.
786 S.W.2d 17 (Court of Appeals of Texas, 1990)
Commercial Union Insurance Co. v. La Villa Independent School District
779 S.W.2d 102 (Court of Appeals of Texas, 1989)
Transamerica Insurance Co. v. Housing Authority of Victoria
669 S.W.2d 818 (Court of Appeals of Texas, 1984)
ETL Corp. v. Forrester
667 S.W.2d 247 (Court of Appeals of Texas, 1984)
John T. Measday v. Kwik-Kopy Corporation
713 F.2d 118 (Fifth Circuit, 1983)
City of San Antonio v. Argonaut Insurance Co.
644 S.W.2d 90 (Court of Appeals of Texas, 1982)
Vaughn Building Corp. v. Austin Co.
620 S.W.2d 678 (Court of Appeals of Texas, 1981)
Opinion No.
Texas Attorney General Reports, 1979
Untitled Texas Attorney General Opinion
Texas Attorney General Reports, 1979

Cite This Page — Counsel Stack

Bluebook (online)
430 S.W.2d 473, 11 Tex. Sup. Ct. J. 484, 1968 Tex. LEXIS 279, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-midland-v-waller-tex-1968.