Houston Fire & Casualty Insurance Co. v. Riesel Independent School District

375 S.W.2d 323, 1964 Tex. App. LEXIS 1905
CourtCourt of Appeals of Texas
DecidedJanuary 23, 1964
Docket4151
StatusPublished
Cited by12 cases

This text of 375 S.W.2d 323 (Houston Fire & Casualty Insurance Co. v. Riesel Independent School District) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Houston Fire & Casualty Insurance Co. v. Riesel Independent School District, 375 S.W.2d 323, 1964 Tex. App. LEXIS 1905 (Tex. Ct. App. 1964).

Opinions

WILSON, Justice.

The school district sued the contractor and the performance bond surety for breach of contract to construct a school building, alleging faulty construction and failure to erect the building in accordance with the plans and specifications. Default judgment was rendered against the contractor. The jury found the contractor failed to construct the building, grade and foundation in a good and workmanlike manner in accordance with the plans and specifications, that the failures were material, that the building could not be repaired without substantial alteration of the structure as a whole, that if it had been constructed according to contract, plans and specifications, its value would have been $310,000, that its value in its condition at time of trial was $100,000, that the architect’s failure to design the building so it would be structurally sound was not the cause of plaintiff’s damages. The surety appeals from judgment against it for $210,000.

The surety’s initial attack on the judgment is that the school district either (a) made final payment to the contractor on the architect’s certificate of inspection and acceptance, which constituted a fulfillment of the contract; or (b) made such payment without the architect’s certificate, which constituted a violation of the district’s duty under the contract, and a change in its terms. It says that under either prong of this dilemma it was discharged from liability.

The surety’s postulate is based on contract provisions that monthly progress payments of 90% of the architect’s estimates would be made to the contractor, and “upon substantial completion of the entire work, a sum sufficient to increase the total payments to 90% of the contract price” ; that final payment should be due 10 days “after substantial completion of the work, provided the work be then fully completed and the contract fully performed” ; that upon receipt of written notice the work was ready for final inspection and acceptance, [325]*325the architect should inspect, “and when he finds the work acceptable under the contract and the contract fully performed, he shall issue a final certificate over his own signature, stating that the work provided for in this contract has been completed and accepted by him under the terms and conditions thereof”, and that the entire balance is due and payable; that the contract would “be considered fulfilled (save as provided in any bond or bonds or by law), when all the work has been completed, and the final inspection made by the architect and engineer, and final acceptance and final payment made by the board”. It also urges the condition of the bond that the contractor shall promptly and faithfully perform the contract; and the surety’s options upon default: to remedy the default, complete the contract, or obtain bids for completion to be submitted to the owner.

The school district made a series of payments totalling more than the original contract sum, the last of which was on the same date the board minutes show a motion was carried “to accept the building” and pay the contractor and architect the balance due. The minutes recite that about one month before the final payment was made the board authorized payment of a monthly estimate to the contractor, who “agreed not to ask for any more until the corrections have been made to the building, and final acceptance.” Thereafter the school district occupied and continued to use the building. No certificate of the architect was introduced in evidence. Appellant’s motions for instructed verdict, for judgment, and judgment non obstante vere-dicto, based on the alternative contentions above, were overruled.

It is unnecessary to decide what the legal effect of these facts would be under authorities relating to finality of the architect’s decision, such as Boettler v. Tendick, 73 Tex. 488, 11 S.W. 497, 5 L.R.A. 270, relied on by appellant. The surety’s position overlooks other important contract provisions which make unsound this premise on which its motions were based.

In the first place, the contract contained no provision making the decisions of the architect final except “in matters relating to artistic effect”, and others, which are not involved here. It expressly provided the architect was the agent of the owner “only to the extent provided in the contract documents” and should “use his power under the contract to enforce its faithful performance by both” owner and contractor. It provided that partial payments under the contract would “not in any way relieve the contractor of the responsibility herein imposed.”

Art. 20 of the general conditions reads: “Neither the final certificate, nor payment, nor any provision of the contract documents shall relieve the contractor of responsibility for faulty materials or workmanship and, unless otherwise specified, he shall remedy any defects due thereto and pay for any damage to other work resulting therefrom, which shall appear within a period of one year from the date of substantial completion.” Art. 25 provides: “No certificate issued nor payment made to the contractor, nor partial or entire use or occupancy of the work by the owner, shall be an acceptance of any work or materials not in accordance with this contract.” The agreement contained additional express recitals to the effect that the “making and acceptance of final payment” shall not constitute a waiver of the owner’s claims “from faulty work appearing after final payment”. Construing the contract as an entity by considering all its terms, as we must do in determining intent, it is clear the parties did not intend that final payment or occupancy would conclude the contractor’s duty or relieve the surety of its obligation.

The court disregarded a negative jury finding, in answer to a special issue inquiring whether the architect issued his final certificate prior to final payment, upon ap-pellee’s motion that the finding was immaterial and was without support in the evidence. Appellant complains of this action.

We recognize the general rule urged by appellant that where the contract pro[326]*326vides that payment shall he made to the contractor by the owner “only on certificate of the architect”, as in Williams v. Baldwin, Tex.Com.App., 228 S.W. 554; or “upon the architect’s certificate”, as in Park Presbyterian Church v. William Cameron & Co., Tex.Com.App., 58 S.W.2d 63, a payment in breach of the condition will relieve the surety. See 127 A.L.R. 22. There is no such prerequisite, however, in the present contract. It is agreed only that “final payment shall be due 10 days after substantial completion of the work provided the work be then fully completed and the contract fully performed.” The provision for the architect’s certificate is not related to any condition of final payment, and such payment is not made contingent on the certificate. The provision for payment “upon certificate of the architect” is only in the event “full completion is delayed through no fault of the contractor”, a circumstance not here involved. The only other provision for certification concerns partial payment estimates. There was no pleading by the surety of any breach in the latter respect.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Wolfe City v. Am. Safety Cas. Ins. Co.
557 S.W.3d 699 (Court of Appeals of Texas, 2018)
Village of Pawnee v. Azzarelli Construction Co.
539 N.E.2d 895 (Appellate Court of Illinois, 1989)
Phenix-Georgetown, Inc. v. Chas. H. Tompkins Co.
477 A.2d 215 (District of Columbia Court of Appeals, 1984)
Norair Engineering Corp. v. Saint Joseph's Hospital, Inc.
249 S.E.2d 642 (Court of Appeals of Georgia, 1978)
Baker-Crow Construction Co. v. Hames Electric, Inc.
566 P.2d 153 (Court of Civil Appeals of Oklahoma, 1977)
A. F. Conner & Sons, Inc. v. Tri-County Water Supply Corp.
541 S.W.2d 856 (Court of Appeals of Texas, 1976)
Board of Regents v. Wilson
326 N.E.2d 216 (Appellate Court of Illinois, 1975)
City of Midland v. Waller
430 S.W.2d 473 (Texas Supreme Court, 1968)
City of Midland v. Waller
418 S.W.2d 915 (Court of Appeals of Texas, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
375 S.W.2d 323, 1964 Tex. App. LEXIS 1905, Counsel Stack Legal Research, https://law.counselstack.com/opinion/houston-fire-casualty-insurance-co-v-riesel-independent-school-district-texapp-1964.