Baker-Crow Construction Co. v. Hames Electric, Inc.

566 P.2d 153
CourtCourt of Civil Appeals of Oklahoma
DecidedJune 23, 1977
Docket48115
StatusPublished
Cited by1 cases

This text of 566 P.2d 153 (Baker-Crow Construction Co. v. Hames Electric, Inc.) is published on Counsel Stack Legal Research, covering Court of Civil Appeals of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Baker-Crow Construction Co. v. Hames Electric, Inc., 566 P.2d 153 (Okla. Ct. App. 1977).

Opinion

ROMANG, Judge:

Plaintiff was the general construction contractor for the construction of an apartment complex at Oklahoma City. Defendant was the electrical subcontractor on the project. This suit is based upon the electrical subcontracts, of which there were three, because the complex was constructed in three phases. Plaintiff alleged that defendant’s electrical work failed to comply with City ordinances, codes, rules and regulations, and that plaintiff had to correct the same at an expense of $17,780.15, for which judgment was asked.

After issues were joined, this case proceeded to trial. Plaintiff presented its pri-ma facie case. Defendant demurred to plaintiffs evidence, and the demurrer was sustained. Plaintiff has appealed. Plaintiff’s first proposition for reversal, reads:

“The trial court erred in construing the twelve-month proviso as being appellant’s exclusive remedy under the construction contracts.”

The ruling of the trial judge was based upon a provision in each of the electrical subcontracts which reads:

“Contractor [defendant] shall, at his own cost, amend and make good any defects in his work (whether of workmanship or of materials) which may appear within twelve (12) months after the completion of this Contract. Should Contractor refuse or neglect to amend and make good such defects within a reasonable time after receiving notice requesting such remedial work, then Agent shall be entitled to make good such defective work at the expense of the Contractor.” The trial judge in sustaining the demurrer stated:
“I think that by the terms of this contract, any time within one year after completion that there are defects that they can call upon the defendant who did the work and if he does not do it within a reasonable time, he would be liable for the costs of doing it.
“I think that the contract was completed as a matter of law when the plaintiff or the plaintiff’s assignee took physical possession of these apartment houses and started renting them out and had tenants, and according to the plaintiff’s testimony, this was all more than one year prior to July of 1973 when these defects were shown.
“I find no evidence offered by the plaintiff to show that any of the defects complained of were latent or hidden. There was no evidence that any of the defects were buried under the ground or behind any wall or the like, so I am simply holding as a matter of law that these parties entered into a contract and said you’ve got to complain within one year after completion of defects,
“I think the parties can by contract limit the time in which they can proceed against one another for defects.
* sf; * * * *
“And I think when you draw a contract and say you’ve got to complain within one year, you are bound by it, . . . .”

Plaintiff states in its brief as follows:

“. . . [A]ppellant was notified by the City of Oklahoma City of the substantial and numerous defects and deficiencies' in the electrical job performed by appellee, and such notice by the City to appellant was more than one year after the final payment under all the contracts; . . .."

It is undisputed that no defects were called to defendant’s attention and no demand was made upon defendant for correction of its work within one year from final payment on the subcontracts.

This suit was filed within the five year period for bringing suits on breach of contract, so the controlling issue is whether the twelve-month provision should be construed as the contractor’s sole remedy for the subcontractor’s breach.

The question as stated by defendant is whether plaintiff had to complain to de *155 fendant of the defects within one year from the date of completion in order to bring an action for breach within the statutory period of time.

Plaintiff relies heavily upon the case of Board of Regents v. Wilson, 27 Ill.App.3d 26, 326 N.E.2d 216 (1975), which arose out of inadequate anchoring of precast concrete panels which formed the exterior walls of residence halls constructed by defendant. The court held that the claim based on defects which appeared more than one year after final payment, was not barred by the one year limitation in the contract. The one year contract provision involved in Wilson, reads:

“The Contractor shall remedy any defects due to faulty materials or workmanship * * *, which shall appear within a period of one year from the date of final payment, * * *.”

In the Wilson opinion the court said:

“It is a basic principle of contract law that parties by an express agreement may contract for an exclusive remedy that limits their rights, duties and obligations. . . . The contract, however, must clearly indicate that the intent of the parties was to make the stipulated remedy exclusive.
* * * * * *
“The ‘Correction of work’ and ‘Guarantee’ provisions place a duty upon the contractor, after notice from the owner, to correct any defects due to faulty workmanship or materials which may appear or develop within one year after final payment. These two provisions do nothing more than establish that for a period of one year defendant has a duty to rectify any such defects; the provisions in no way limit plaintiff, after that one year, from claiming damages as the result of faulty work or material. The duty imposed upon defendant for the one year period carries the corresponding right which allows it to rectify such defects prior to any action being taken by the plaintiff. Neither of these provisions state that they are exclusive remedies available to the plaintiff or that they were in lieu of plaintiff’s rights as provided by the ‘Final Payment’ provision.
* * * * * *
“. . . [T]he owner’s claim for faulty work and failure to follow plans and specifications survives final payment without the one year limitation period found in the other specific provisions. ******

Free access — add to your briefcase to read the full text and ask questions with AI

Related

First Nat. Bank of Akron v. Cann
503 F. Supp. 419 (N.D. Ohio, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
566 P.2d 153, Counsel Stack Legal Research, https://law.counselstack.com/opinion/baker-crow-construction-co-v-hames-electric-inc-oklacivapp-1977.