First Nat. Bank of Akron v. Cann

503 F. Supp. 419, 1980 U.S. Dist. LEXIS 14131
CourtDistrict Court, N.D. Ohio
DecidedJune 4, 1980
DocketCiv. A. C78-186A
StatusPublished
Cited by29 cases

This text of 503 F. Supp. 419 (First Nat. Bank of Akron v. Cann) is published on Counsel Stack Legal Research, covering District Court, N.D. Ohio primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
First Nat. Bank of Akron v. Cann, 503 F. Supp. 419, 1980 U.S. Dist. LEXIS 14131 (N.D. Ohio 1980).

Opinion

MEMORANDUM OPINION AND ORDER

CONTIE, District Judge.

Invoking the Court’s diversity jurisdiction pursuant to 28 U.S.C. § 1332, plaintiff, First National Bank of Akron (Bank), brings the above captioned action against defendants William F. Cann and Building and Equipment Corp. of America (B.E.C.). 1 Plaintiff is a national banking association incorporated under the laws of the United States, *423 having its principal place of business in Akron, Ohio. Defendant Cann is a citizen and a resident of a state other than Ohio. Defendant B.E.C. is a Delaware corporation. The amount in controversy exceeds $10,000.00, exclusive of interest and costs. The within action was tried to the Court, and the following shall constitute the Court’s findings of fact and conclusions of law in accordance with Rule 52, Federal Rules of Civil Procedure.

I. FINDINGS OF FACT

A. The Bank’s Remodeling Project

In the mid-1960s the Bank’s management decided to refurbish the interior and exteri- or of its main building located at 106 South Main Street, Akron, Ohio. Up until that time, Harold S. Cassidy had provided all the architectural services required by the Bank since their first association in 1952. Said services included the remodeling of existing structures and the design and erection of new structures, and were performed by Cassidy as an independent contractor.

In 1966 Cassidy was involved in the design and construction of a connecting link and loading dock at the Bank’s main building and adjacent to a developing public plaza. The project required the cooperation and approval of the local City government, which Cassidy's long relationship as the Bank’s local architect facilitated securing. When the Bank approached Cassidy with the prospect of taking on the more expansive exterior and interior remodeling of the main building, however, he informed them that his office was not in a position to handle the project. This was the first Bank project requiring architectural services that Cassidy was not in charge of since the inception of their association.

B.E.C. is a corporation engaged in the business of assisting lending institutions in making improvements to their physical facilities, providing assistance in the selection of an architect, and management of the construction if the proposed improvements are undertaken. In 1966, John T. Huffman was employed by B.E.C. as a senior consultant, and represented that company in its efforts to sell its services. James L. Hilton was the Bank’s vice president in charge of property management and security. Huffman initially contacted the Bank through Hilton. The Bank eventually expressed interest in B.E.C.’s services, and the consulting and architectural agreements presented by Huffman were executed. On November 3, 1966, B.E.C. and the Bank entered into the consulting agreement. On November 17, 1966, the Bank entered into a standard architect agreement with William F. Cann, a licensed architect and employee of B.E.C.

At that time Cann was president of B.E.C. All architectual fees paid to Cann were turned over by him to the company. Cann was then paid by the company in his capacity of president; he received no separate compensation as an architect. Cann never personally disclosed this arrangement to the Bank, but held himself out as an individual architect in executing the architect agreement.

In a letter dated April 12, 1967, Cann proposed an association between himself and Cassidy, through which Cassidy would act as a local architect during the construction phase of the architectural agreement. This contact was initiated because it was B.E.C.’s common practice to hire a local architect for intricate, remote jobs such as the Bank’s remodeling project. Cassidy signed the proposal and dated it June 6, 1967. This written proposal, approved by Cassidy, was not a fully integrated agreement. By its explicit terms, the proposal covered only the principal items and left open the precise relationship between Cann and B.E.C. to further negotiations.

On June 6,1967, Cassidy met Cann at his St. Louis office to refine the terms of their relationship. It was agreed that Cassidy would both make periodic visits to the site and assist and supervise the work only when so requested. Cassidy refused to assume any greater responsibility because of the demands of his private practice. Cassidy did agree to turn over his drawings of the connecting link and loading dock. This allowed one architect to coordinate a single *424 project. From January to November, 1967, Cassidy attended a number of meetings between the Bank, Cann, and B.E.C. in order to facilitate coordination of Cann’s remodeling plans and Cassidy’s work on the connecting link and loading dock.

Thus, retaining Cassidy as the local architect was the logical choice for two reasons of considerable import: first, it achieved the necessary coordination between B.E.C.’s responsibility for the extensive remodeling project and the two minor facets of the Bank’s refurbishing already begun by Cassidy; and second, it provided B.E.C. with an experienced liaison who maintained a standing relationship with both the Bank and the City government.

On June 22, 1967, the Bank and B.E.C. entered into a management agreement to achieve the satisfactory completion of the remodeling project. The contract contained a cost incentive clause. Under the agreement B.E.C. became the construction manager for the project and was responsible for all work necessary to complete the project. Thus, B.E.C. was both the consultant and the construction manager, and its president Cann was the architect.

Actual construction commenced on the project in January, 1968, and was completed by November, 1969. The exterior remodeling included the erection of a granite facing on the Bank’s south wall. The instant action is solely directed to alleged problems involving the granite facing on the south wall, and no other aspect of the project is in dispute.

B. The Plans For The South Wall

A curtain wall construction was utilized to erect the granite facing consistent with the following specifications set out in the plans. 2 The type of curtain wall erected on the Bank’s south wall is a non-load-bearing design. The granite skin consists of some 500 individual panels two inches thick and otherwise varying in size. Some of the panels weigh up to 800 lbs. The curtain wall’s non-load-bearing design provides for intermediate steel supports at each floor level so that the total weight of the granite is not transferred to the bottom.

The south wall is comprised of three elevated sections. The west elevation is ten stories in height and approximately 45 feet in length. The center section is four stories in height and approximately 57 feet in length. The east elevation is seven stories in height and approximately 70 feet in length.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Black + Vernooy Architects v. Smith
346 S.W.3d 877 (Court of Appeals of Texas, 2011)
Information Leasing Corp. v. Chambers
789 N.E.2d 1155 (Ohio Court of Appeals, 2003)
G.M. Meredith & Associates v. Blue Pacific Management Corp.
28 Am. Samoa 2d 60 (High Court of American Samoa, 1995)
Andrulis v. Levin Construction Corp.
628 A.2d 197 (Court of Appeals of Maryland, 1993)
Sowards v. Norbar, Inc.
605 N.E.2d 468 (Ohio Court of Appeals, 1992)
Pembaur v. City of Cincinnati
745 F. Supp. 446 (S.D. Ohio, 1990)
General Acquisition, Inc. v. GenCorp Inc.
766 F. Supp. 1460 (S.D. Ohio, 1990)
Watson, Watson, Rutland/Architects, Inc. v. BD. OF EDUC.
559 So. 2d 168 (Supreme Court of Alabama, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
503 F. Supp. 419, 1980 U.S. Dist. LEXIS 14131, Counsel Stack Legal Research, https://law.counselstack.com/opinion/first-nat-bank-of-akron-v-cann-ohnd-1980.