Krause v. Oscar Daniels Co.

22 N.E.2d 544, 61 Ohio App. 337, 28 Ohio Law. Abs. 661, 15 Ohio Op. 225, 1939 Ohio App. LEXIS 407
CourtOhio Court of Appeals
DecidedMarch 20, 1939
DocketNo 2940
StatusPublished
Cited by4 cases

This text of 22 N.E.2d 544 (Krause v. Oscar Daniels Co.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Krause v. Oscar Daniels Co., 22 N.E.2d 544, 61 Ohio App. 337, 28 Ohio Law. Abs. 661, 15 Ohio Op. 225, 1939 Ohio App. LEXIS 407 (Ohio Ct. App. 1939).

Opinion

*662 OPINION

By GUERNSEY, J.

This is an appeal on questions of law from a judgment of the Common Pleas Court of Franklin’ County, Ohio, entered upon the motion of Oscar Daniels Company, defendant-appellee, for a directed, verdict in its favor upon the conclusion of the testimony offered on behalf of Walter D. Krause, plain tiff-appellant, upon the first cause of action m the petition.

The first cause of action was for personal judgment and the second cause of action involved the foreclosure of a purported mechanic’s lien for the amount alleged to be due in the first cause of action, and based upon the court’s ruling as to the first cause of action a judgment of dismissal was entered for defendant upon the second cause of action 11 om which no appeal on questions of law and fact is made.

Plaintiff as a subcontractor brought this action against Oscar Daniels Company as principal contractor to recover for alleged extra work required by sa¿d company upon Columbus limestone which plaintiff furnished as materialman for the construction of three stone structures on the Olentangy Boulevard. The defendant was the principal contractor under a contract with the Ohio Director of - Highways.

The contract entered into between plaintiff and defendant in relation to the furnishing of such materials for which recovery is claiméd, is in the words and figures following, to-wit:

“September 1st, 1936.
“Mr. W. D. Krause,
212 S. Roosevelt Ave.,
CoJumbus, Ohio
RE: PROJECT NO. 161 — OLENTANGY BLVD..-
Columbus, Ohio
Dear Sir:
We hereby accept: your., verbal proposal for furnishing all material and labor for dressing and delivering to the site all the Face Ashlar Stone required for the above named project. This includes all the stone shown on drawings. Nos. 34/66-35/66-36/66-37/66 required , for Bridge No. 11; C. & O. Railroad and drawings Nos. 48/66-49/66-50/66 required for Bridge No. 1.03 Pennsylvania Railroad..and drawings Nos. 56/66-57/66 Bridge Interchange Pennsylvania Railroad with the exception of stone actually designated on the drawings as trim stone.
“The material, labor and methods shall be in accordance with the State of Ohio, Department of Highways supplemental Specification dated February 13, 1936 Item S-121'; S121.01; S121.02 and S121.03.
• “In consideration of the above we agree to pay you the sum of seventy-five cents ($) .75 per cubic foot of stone facing. ’ Payments to be made twice monthly for stone that is dressed and-ready ior delivery, based upon estimated cubage, measured as per Supplemental Specifications SJ21, less 15% retention. Final payments will be made on the cubage accepted and measured by the State of Ohio, Department of Highways ¿5 days after complete delivery of stone and as accepted by the State of Ohio.
“It is understood that the stone will be delivered when and as required by our local representative.
“It is further understood that the above price includes Workmen’s Compensation, Public Liability and Property Damage Insurance.
“Your signature to this proposition shall constitute an acceptance and a contract.
Very truly yours,
OSCAR DANIELS COMPANY,
By A. A. Pedersen
A. A. Pedersen, Engineer.
ACCEPTED
Walter D. Krause, September 3, 1936."

The petition alleged that plaintiff was to receive 75c per cubic foot on stone facing under the terms of said contract, but because of extra work required thereon by defendant, defendant was indebted to plaintiff to the extent of $5835.34 beyond the amount of said contract price which amount included a loss of profit on certain stone which defendant secured elsewhere after plaintiff ceased to furnish stone upon defendant’s refusal to pay for said extra work. .

- It was alleged in the petition that said extra work involved conforming the stone-to maximum joint limitations of three-fourths inch instead of an average of three-fourths inch; that the heads of stone, be squared to provide uniform projection of: joint in the wall,; that no projections were allowed on the face of the stone in excess of one inch; that small-stone were not permitted to be used in filling spaces; that the length of all stone used was required to be. within the limits of one and one-half to three, times the height; that all head-, joints *663 were required to be squared back for at least six inches; and that all bed joints were required to be of uniform thickness at least six inches back.

■ It is further alleged that by reason of the foregoing requirements, said stone could not substantially all be hammer dressed out on the contrary it was necessary to mainly use points and pitching tools in dressing said stone.

On the drawings referred to in the contract between plaintiff and defendant, above set 'forth, there was a notation as follows:

“All facing stone shall be best quality Columbus limestone. All work shall conform with ‘Item S-12i S-stone, F-face, 4 Concrete Masonry.’ For example of stone work see bridge over the Scioto River at Dublin 12 miles n.w. of Columbus.”

The State of Ohio, Department of Highways Supplemental Specification, dated February 13, 1936 — S-121; S121.01; S121.02 and S121.03 referred to in the contract between plaintiff and defendant contained detailed specifications of material, labor and methods. There is no provision for “tolerances” or “variations”; and there is no reference of any kind to the bridge over the Scioto River at Dublin.

Plaintiff offered evidence tending ' to prove that in the construction of said Dublin Bridge referred to in tne notation above set forth, certain “tolerances” or “variations” were permitted in the quarrying, dressing and laying of stone therefor, manliest from the structure itself, and that he had been required to furnish the material provided for in his contract with defendant without such “tolerances” or “variations” and that the refusal of the defendant to accept said materials with such “tolerances” or “variations” occasioned the extra work for which compensation is sought.

Evidence was also offered on behalf of plaintiff tending to prove that in quarrying, dressing and laying Columbus limestone in the district in which said limestone is produced there existsed certain usages and customs known as “tolerances” or “variations”, comprehending “tolerances” or “variations” of the character existing in the structure of the Dublin ondge, but there is no evidence tending to prove that the defendant had any notice or knowledge of such usages” or customs.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bamcor LLC v. Jupiter Aluminum Corp.
767 F. Supp. 2d 959 (N.D. Indiana, 2011)
Musci v. Musci, Unpublished Decision (11-8-2006)
2006 Ohio 5882 (Ohio Court of Appeals, 2006)
First Nat. Bank of Akron v. Cann
503 F. Supp. 419 (N.D. Ohio, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
22 N.E.2d 544, 61 Ohio App. 337, 28 Ohio Law. Abs. 661, 15 Ohio Op. 225, 1939 Ohio App. LEXIS 407, Counsel Stack Legal Research, https://law.counselstack.com/opinion/krause-v-oscar-daniels-co-ohioctapp-1939.