Keeton v. Hinkle, Unpublished Decision (3-10-2000)

CourtOhio Court of Appeals
DecidedMarch 10, 2000
DocketNo. CA 871.
StatusUnpublished

This text of Keeton v. Hinkle, Unpublished Decision (3-10-2000) (Keeton v. Hinkle, Unpublished Decision (3-10-2000)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Keeton v. Hinkle, Unpublished Decision (3-10-2000), (Ohio Ct. App. 2000).

Opinions

OPINION
Appellants Linda and Dennis Keeton appeal from the June 29, 1998, judgment entry of the Morrow County Court of Common Pleas.

STATEMENT OF THE FACTS AND CASE
On or about August 21, 1995, Appellants Linda and Dennis Keeton entered into an agreement with Appellee Hinkle Builders (hereinafter referred to as appellee) for the construction of a house on appellants' land at a cost of $121,800. Appellee procured the design engineer who drew the construction blueprints. The construction was financed by a loan through State Savings Bank. Pursuant to the terms of the agreement, all work on the house was to be "substantially completed" by appellee within ninety working days. The completion date of the house was a matter of great concern to appellants because they had to reside in a replacement residence by mid-April 1996 in order to avoid capital gains taxes. For this reason, appellants informed appellee of their potential capital gains tax problem and of their need to be in their home by April. Appellee does not dispute that he was told of appellants' potential tax problem and their need for a mid-April completion date. Before construction on the house commenced, an unreleased oil pipeline easement was discovered by State Savings Bank's title examiner that had to be released. Construction of appellants' house began on November 22, 1995, after the easement was released and the title matter was resolved to State Savings' satisfaction. Despite the lengthy delay caused by the easement, appellee did not obtain an extension of the ninety-day period contained in the parties' agreement since he believed he could complete the project on time "[i]f everything went right." Tr. at 257. Appellee, however, conceded that "it was a tight schedule." Id. at 256. Appellee, on November 22, 1995, started digging the foundation for appellants' house. During the first week of December, the footers were poured. Thereafter, construction proceeded slowly because of the adverse weather conditions. According to appellee, due to rain and snow, the hole for the foundation kept filling with water making it impossible for him to lay block for the foundation. Finally, in March 1996, the foundation for appellants' home was completed. Although the house was under roof by late April 1996, appellants did not move into the house until July 23, 1996, causing them to incur increased income taxes of $5,491.05. On this date, the air conditioning and heating were not hooked up and some of the carpeting and molding still had to be installed. However, due to financial pressures, appellants were forced to move into the house despite its unfinished condition. In late August 1996, after appellants sent appellee a letter stating that no additional monies would be paid to appellee until appellants had been made whole on the contract, appellee ceased work. Thereafter, on October 3, 1996, Baldauf Lumber Do-It Center, which had supplied materials to appellants' home, filed a mechanic's lien against appellants' property in the amount of $10,384.82. On May 20, 1997, appellants filed a complaint against Appellee State Savings Bank, which held certain undisbursed funds from appellants' construction loan, and Straight and Lamp Group, Inc. dba Baldauf Lumber Do-It Center. Appellants, in their complaint, alleged that appellee breached its contract with appellants and breached both express and implied warranties and violated the Ohio Consumer Sales Practices Act, O.R.C. 1345.01 et seq. Appellants further alleged that State Savings refused to release remaining loan proceeds, which totaled $23,000, in the absence of appellee's approval. Both appellee and State Savings Bank filed answers on June 19, 1997. Appellee, on such date, also filed a "counter-complaint" against appellants seeking payment of the balance of the contract price and for some "extras" it allegedly incurred during construction. Appellants filed an answer to the same on June 27, 1997, with leave of court. Straight Lamp Group, Inc., dba Baldauf Lumber Do-It Center on July 31, 1997, filed an answer and counterclaim against appellants and a cross claim against appellee and State Savings Bank. State Savings Bank filed an answer to such cross-claims on August 13, 1997. Two weeks thereafter, appellants filed an answer to Straight Lamp Group, Inc.'s counterclaim. Pursuant to an order filed on December 9, 1997, the trial court scheduled the matter for a bench trial and ordered that "the claims of Baldauf Lumber Do-It Center and the potential claims of State Savings Bank are hereby bifurcated with both parties reserving its claims until such time as plaintiffs' and defendants' claims against one another are adjudicated." A bench trial was held on March 5 and 6, 1998. At trial, appellants' expert, Dr. Vedaie, testified. Dr. Vedaie has a Bachelor's Degree in Commercial Engineering, a Master's Degree in Structure and a PhD in Engineering. Dr. Vedaie testified that the workmanship on appellants' house was poor. Dr. Vedaie further testified that "my main concern when I saw the pictures and that footer went through a freeze and thaw and makes the concrete weaker, it makes the concrete crack, it makes the concrete to have a macho crack, inside extensive crack. So that was my main concern of looking at the structure." Id. at 120. According to Dr. Vedaie, the footer went through a freeze and thaw cycle which would, in his opinion, destroy the usefulness of the concrete if it was not of a proper type. Dr. Vedaie, whose report was admitted into evidence, further testified as to numerous other problems with the house. Dr. Vedaie, for example, testified that the support beam in appellants' house was settling and that if too many people stood in the hallway of appellants' house, the house could collapse. In addition to Dr. Vedaie, Don Davis, a real estate appraiser and business consultant, also testified on behalf of appellants. Davis, relying on the report prepared by Dr. Vedaie and his own experience as a real estate appraiser and a business building consultant, testified that the workmanship on appellants' home was "average, overall." Id. at 174. Davis, whose expert report was admitted into evidence, estimated the total to repair the defects to appellants' home at $31,676.07. In turn, Ronald Kyser, appellee's expert, who holds a Bachelor's Degree in Construction, testified that the construction was "average" quality for a moderate or low cost house and that appellants received good value for their money. Id. at 94. Kyser, whose report was admitted into evidence, further testified that the problems with appellants' house appeared to be minor with the exception of the remedial work on the basement floor and wall and some cracks in the exterior stucco. After the conclusion of the trial, appellants and appellees filed post-trial memorandums. Pursuant to a judgment entry filed on April 13, 1998, the trial court found that appellee breached his implied duty to perform in a workmanlike manner. The trial court, in addition to awarding appellants $11,465 in damages, also granted judgment to appellee for the approximately $23,000 balance due under the parties' contract and for $1,679.35 on its counterclaim for extras. The trial court also ordered that appellee pay the $10,384.82 Balduaf's mechanic's lien. The trial court held that appellants "may offset judgment against the balance of construction loan proceeds after payment of the Baldauf mechanic's lien has been paid off, . . . ". However, the trial court denied appellants' claim for damages caused by appellee's delay and declined to find that appellee violated the Ohio Consumer Sales Practices Act. A Final Judgment Entry was filed on June 29, 1998. It is from the June 29, 1998, Judgment Entry that appellants prosecute their appeal, raising the following assignments of error:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

First Nat. Bank of Akron v. Cann
503 F. Supp. 419 (N.D. Ohio, 1980)
Thomas v. Sun Furniture & Appliance Co.
399 N.E.2d 567 (Ohio Court of Appeals, 1978)
Keiber v. Spicer Construction Co.
619 N.E.2d 1105 (Ohio Court of Appeals, 1993)
Daniels v. Albert J. Corey Co.
208 N.E.2d 150 (Ohio Court of Appeals, 1965)
Sites v. Moore
607 N.E.2d 1114 (Ohio Court of Appeals, 1992)
Karst v. Goldberg
623 N.E.2d 1348 (Ohio Court of Appeals, 1993)
Frantz v. Van Gunten
521 N.E.2d 506 (Ohio Court of Appeals, 1987)
C. E. Morris Co. v. Foley Construction Co.
376 N.E.2d 578 (Ohio Supreme Court, 1978)
Blakemore v. Blakemore
450 N.E.2d 1140 (Ohio Supreme Court, 1983)
Roberts v. United States Fidelity & Guaranty Co.
665 N.E.2d 664 (Ohio Supreme Court, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
Keeton v. Hinkle, Unpublished Decision (3-10-2000), Counsel Stack Legal Research, https://law.counselstack.com/opinion/keeton-v-hinkle-unpublished-decision-3-10-2000-ohioctapp-2000.