Sands Motel v. Hargrave

358 S.W.2d 670, 1962 Tex. App. LEXIS 2534
CourtCourt of Appeals of Texas
DecidedJune 12, 1962
Docket7398
StatusPublished
Cited by12 cases

This text of 358 S.W.2d 670 (Sands Motel v. Hargrave) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sands Motel v. Hargrave, 358 S.W.2d 670, 1962 Tex. App. LEXIS 2534 (Tex. Ct. App. 1962).

Opinion

CHADICK, Chief Justice.

This is a suit for damages for breach of contract. The judgment of the trial court is affirmed.

The plaintiff, Sands Motel, instituted an action against the defendant, Paul Har-grave, to collect $5,656.00 as damage the motel alleged it suffered by reason of Har-grave’s breach of a contract to furnish and install plumbing and heating equipment according to certain plans and specifications *671 agreed upon by the parties in an annex to the motel. Hargrave’s answer interposed special exceptions, entered a general denial and affirmatively plead performance of the contract in accordance with plans and specifications and the motel architect’s acceptance and approval of the completed undertaking. In the alternative, defendant Har-grave plead defenses of estoppel and waiver.

The trial judge submitted ten special issues to the jury. By answer to the first two issues the jury established that Har-grave did not install certain hot and cold water pipes in a workmanlike manner, but that he performed the contract in accordance with the plans and specifications. In following issues the jury found that the architect was an agent of the motel, but at the completion of the work he did not have full knowledge of all material facts relative to installation of the hot and cold water pipes in controversy, and did not accept the completed work with full knowledge of the manner the pipes were installed. The jury also found that Hargrave advised the motel’s manager of the likelihood of a transference of heat from the hot water pipes to the cold water pipes prior to the time he installed them, and that the motel’s manager stated to Hargrave that the motel would assume the risk of such heat transference, and then found on other issues that this representation was false, that it was made with the intent that Hargrave rely on it, and that it caused Hargrave to act as he did in the completion of the contract.

The plaintiff motel moved for judgment on the verdict and for judgment non ob-stante veredicto, as well as for the court to disregard the jury’s answer to the special issue on performance in accordance with plans, etc., and the issues presenting the theory of estoppel and waiver. The defendant moved in his own behalf for judgment on the jury findings and alternatively for the court to disregard the jury’s verdict on Hargrave's workmanship. Then, also in the alternative, the defendant’s motion plead that if the court was of the opinion the jury’s verdict on the issue of Hargrave’s performance and the issue of Hargrave’s workmanship were in conflict, that judgment be rendered upon the jury’s answers to the estoppel and waiver issues. The court overruled the motel’s motions, failed to indicate any disposition of Hargrave’s, and entered its written judgment which recited all special issues submitted and the jury’s answers thereto, and stated that “ * * * in accordance with the above findings of the jury in response to the special issues submitted to them the court is of the opinion and finds that the defendant is entitled to judgment, * * * ”, and proceeded to adjudge that Sands Motel take nothing by its suit, etc.

Prior to November 20, 1958, the Sands Motel began preparation to add to its motel plant. It employed an architect to draw plans and prepare specifications for the proposed annex. No general or prime contract was made. The construction and installation to be done was divided into several parts and contracts let accordingly. Contract for furnishing and installing the plumbing and heating equipment was let to Hargrave on an independent basis.

The contract between Hargrave and the motel dated November 20, 1958, specified the material Hargrave was to furnish, and referred to the architect’s plans and specifications for the work that he was to do. Printed in the contract form was this language : “I guarantee all materials used in this contract to be first class, and the entire job to be done in a neat and substantial manner.” Additionally, the specifications carried this language:

“CORRECTION OF WORK AFTER FINAL PAYMENT: Neither the final certificate nor payment nor any provision in the contract documents shall relieve the contractor of responsibility for faulty materials or workmanship and he shall remedy any defects due thereto and pay for any damage to other work resulting therefrom, which *672 shall appear within a period of one year from the date of substantial completion. The owner shall give notice of observed defects with reasonable promptness. * * *
“GUARANTEE. In addition to specific warranties on equipment this contractor will be responsible for all material and workmanship under his jurisdiction for a period of one year from date of finished job, and shall, without charge, replace any item that fails and correct any malfunction in equipment for the stated one year period.”

A drawing, the architect’s plumbing layout, was introduced in evidence. This drawing required a six inch inside diameter sewer line, a two inch gas line, a three inch cold water pipe, a two inch hot water pipe, and a two inch hot water circulating pipe to be laid between the outer foundation of the motel building and the property line, a space four feet in width. The specifications required all piping to be pitched so the entire system could be drained, with exterior lines to be buried at least eighteen inches underground. Evidence was offered, which is not disputed, that it was ■customary that the sewer line be first laid at the lowest level in the area in which the several systems were to be located, and its depth from the surface was dictated by drainage into the city sewage system and varied from five to.six feet. A City Ordinance required the gas line be not less than thirty inches distant from other lines and the building foundation. The four systems of pipes were confined by the plans to a cross section space four feet in width and from five to six feet in depth.

Hargrave testified, and there is no contention to the contrary, that he inquired of the architect whether or not the plans and specifications required him to insulate the hot and cold water lines to prevent heat transference, and that he was advised that the specifications did not require lines buried in the ground to be insulated. The testimony doesn’t fix the time, but it is in evidence that a conversation between Har-grave and the motel manager took place after a substantial amount of the work called for by the contract had been performed wherein Hargrave advised the manager that in his opinion installation in accordance with the plans would cause heat to be transferred from the hot to the cold water lines, unless the lines were insulated against it. The manager requested an estimate of the additional cost of insulation, and when he was advised declined to authorize insulation, remarking that, “We will worry about it when the time comes.”

The motel offered testimony that shortly after the newly constructed facilities were put into operation guests began complaining that the cold water taps ran hot water. Investigation by the motel management confirmed the complaint, and Hargrave was called upon to rectify his work to the end that the hot and cold water system be made to function properly, tie refused. An experienced plumber was employed by the motel to locate and correct the malfunction. A trench was opened along one side of the motel in the area the plans locate the pipe systems.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

John Dori v. Bondex International, Inc.
Court of Appeals of Texas, 2006
Chappell Hill Bank v. Lane Bank Equipment Co.
38 S.W.3d 237 (Court of Appeals of Texas, 2001)
Kraatz v. Faubion
617 S.W.2d 273 (Court of Appeals of Texas, 1981)
Pearcy/Christon, Inc. v. Cutler Construction Co.
601 S.W.2d 490 (Court of Appeals of Texas, 1980)
Potler v. MCP Facilities Corp.
471 F. Supp. 1344 (E.D. New York, 1979)
Southern Roofing & Sheet Metal Co. v. Paramount Construction Co.
512 S.W.2d 781 (Court of Appeals of Texas, 1974)
Sutton v. Reagan & Gee
405 S.W.2d 828 (Court of Appeals of Texas, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
358 S.W.2d 670, 1962 Tex. App. LEXIS 2534, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sands-motel-v-hargrave-texapp-1962.